Mallacoota - Hall Upgrade

Share Mallacoota - Hall Upgrade on Facebook Share Mallacoota - Hall Upgrade on Twitter Share Mallacoota - Hall Upgrade on Linkedin Email Mallacoota - Hall Upgrade link


This project is in delivery.

Updates are provided in the news feed tab below.



The Mallacoota Hall was the relief and recovery facility during the 2019-20 Victorian bushfires.

This project will upgrade the hall to improve its functionality for day-to-day use by:

  • relocating the main entry
  • addressing existing accessibility barriers
  • redeveloping the toilets and change rooms to improve accessibility and functionality
  • futureproofing the building to prevent bushfire smoke entering the facility
  • creating new internal storage space
  • expanding the existing kitchen
  • creation of additional community and office spaces

A concept design was produced in collaboration with a local project reference group to meet the funding criteria. Detailed design was completed by a local designer.

This process progressed to construction of a fit for purpose facility using local contractors.

Funding is provided by the Victorian State Government through Emergency Recovery Victoria's Local Economic Recovery Program.


We welcome your continued interest in this initiative. Updates will be provided on Your Say. Please click 'Subscribe' at the top of the page to follow this project and receive important information directly to your inbox. If you want to search for other projects near you, simply type the town name in the search bar.


This project is in delivery.

Updates are provided in the news feed tab below.



The Mallacoota Hall was the relief and recovery facility during the 2019-20 Victorian bushfires.

This project will upgrade the hall to improve its functionality for day-to-day use by:

  • relocating the main entry
  • addressing existing accessibility barriers
  • redeveloping the toilets and change rooms to improve accessibility and functionality
  • futureproofing the building to prevent bushfire smoke entering the facility
  • creating new internal storage space
  • expanding the existing kitchen
  • creation of additional community and office spaces

A concept design was produced in collaboration with a local project reference group to meet the funding criteria. Detailed design was completed by a local designer.

This process progressed to construction of a fit for purpose facility using local contractors.

Funding is provided by the Victorian State Government through Emergency Recovery Victoria's Local Economic Recovery Program.


We welcome your continued interest in this initiative. Updates will be provided on Your Say. Please click 'Subscribe' at the top of the page to follow this project and receive important information directly to your inbox. If you want to search for other projects near you, simply type the town name in the search bar.

  • Official opening celebration - 14 November 2025

    Share Official opening celebration - 14 November 2025 on Facebook Share Official opening celebration - 14 November 2025 on Twitter Share Official opening celebration - 14 November 2025 on Linkedin Email Official opening celebration - 14 November 2025 link
    Great to join the Mallacoota community, volunteers, local tradies, a few visitors and our team to open three major Mallacoota upgrade projects:
    • Mallacoota Hall
    • Streetscape
    • Mudbrick Pavilion
    Cutting the ribbon at the hall to mark the completion of the works were Cr Arthur Allen, our project supervisor Dale Stephenson, and Mallacoota Halls and Rec Committee leaders Don Ashby and Gail Sands.


  • November 2025

    Share November 2025 on Facebook Share November 2025 on Twitter Share November 2025 on Linkedin Email November 2025 link

    ๐—ช๐—ฒ'๐—ฟ๐—ฒ ๐—ฐ๐˜‚๐˜๐˜๐—ถ๐—ป๐—ด ๐˜๐—ต๐—ฒ ๐—ฟ๐—ถ๐—ฏ๐—ฏ๐—ผ๐—ป ๐—ผ๐—ป ๐˜๐—ต๐—ฟ๐—ฒ๐—ฒ ๐— ๐—ฎ๐—น๐—น๐—ฎ๐—ฐ๐—ผ๐—ผ๐˜๐—ฎ ๐—ฝ๐—ฟ๐—ผ๐—ท๐—ฒ๐—ฐ๐˜๐˜€

    Come along Friday 14 November 2025 to the official opening of the newly refurbished hall, the Mudbrick Pavilion and new streetscape at noon at 25 Greer Street.
    Chat to Councillors and staff - and you can even have your say on a name for the lane that will become Mudbrick Pavilion's new address. Bring a friend and bring ideas.

    See you there!


  • ๐Ÿ“… October 2025

    Share ๐Ÿ“… October 2025 on Facebook Share ๐Ÿ“… October 2025 on Twitter Share ๐Ÿ“… October 2025 on Linkedin Email ๐Ÿ“… October 2025 link

    The Mallacoota Community Hall renovation is nearing completion, with significant milestones now achieved:

    • Toilet areas have been completed and are functional.
    • The kitchen area is finished and ready for use.
    • Carpet tiles have been laid throughout the front area, finalising the internal flooring works.
    • The DDA-compliant carpark has been successfully constructed, enhancing accessibility.
    • Landscaping works have progressed well, with a new garden bed installed and existing beds refreshed with mulch, contributing to a welcoming exterior.

    Final finishing touches are underway to bring the project to full completion.


  • September 2025

    Share September 2025 on Facebook Share September 2025 on Twitter Share September 2025 on Linkedin Email September 2025 link

    The Mallacoota Community Hall project remains on track, with ongoing works steadily transforming the space for community use.

    Recently Completed:

    • The front entry extension has now been fully plastered and the fix-out works throughout this area are complete.
    • The lift shaft has been demolished, with the base re-poured and a Besser block wall constructed in preparation for the new lift installation.
    • The vinyl flooring in the kitchen is currently being laid.
    • A new accessible car park has been installed and line-marked, improving access to the facility.
    • The external facade of the hall has been freshly painted, enhancing the buildingโ€™s appearance.

    Next Steps:

    • Internal and remaining external painting of the hall.
    • Fit-off works in the remaining hall areas.
    • Garden preparation, including re-mulching of existing garden beds to refresh the landscaping.


    We appreciate the communityโ€™s ongoing support and look forward to delivering a revitalised facility that meets the needs of all users.


  • project update

    Share project update on Facebook Share project update on Twitter Share project update on Linkedin Email project update link

    Key milestone reached: lock-up

    The hall has reached lock-up, meaning itโ€™s fully enclosed and secure.

    Recently completed

    • Exterior cladding and roof flashings
    • Kitchen plastering
    • Concrete footpath poured at the rear of the building
    • drainage pits - to help direct water away from the building

    Whatโ€™s happening now

    • front entry extension
    • Installation of the new kitchen

    Whatโ€™s next

    • Painting - starting with the outside of the hall and the ceilings in the kitchen and foyer.
    • Prepare for the lift installation, improving accessibility.
    • Vinyl flooring in the kitchen.
    • Final plastering of the remaining internal areas.
    • Install a new accessible car park.


  • ๐Ÿ“… August 2025

    Share ๐Ÿ“… August 2025 on Facebook Share ๐Ÿ“… August 2025 on Twitter Share ๐Ÿ“… August 2025 on Linkedin Email ๐Ÿ“… August 2025 link

    What's happening now:

    • Cladding installation: The majority of external cladding has been completed. The builder is progressing toward lock-up stage, expected in the coming weeks.
    • Generator relocation: The generator has been relocated to the new storage shed and is now up and running to supply power to the hall.
    • Internal linings: Plastering contractors have commenced the remaining internal wall and ceiling linings throughout the hall.

    What's next:

    • Completion of external cladding and transition to lock-up
    • Finalisation of internal plastering
    • Commencement of internal fit-off, including joinery, fixtures, and finishes



  • ๐Ÿ“… July 2025

    Share ๐Ÿ“… July 2025 on Facebook Share ๐Ÿ“… July 2025 on Twitter Share ๐Ÿ“… July 2025 on Linkedin Email ๐Ÿ“… July 2025 link

    ๐Ÿ”จ๐Ÿ‘ท๐Ÿปโ€โ™‚๏ธ Construction is progressing well on site -

    • Front entry is framed
    • All windows installed

    The plumber has completed the remaining roofing and is now moving ahead with the final rough-in works. The electrician is also on site, completing the last of the rough-in tasks.

    Whatโ€™s coming up in the next two weeks:

    • The builder will begin installing the external cladding, which will start to bring the buildingโ€™s exterior to life.
    • Internal toilet areas will be fully fitted off, marking another important milestone.
  • 26 June update

    Share 26 June update on Facebook Share 26 June update on Twitter Share 26 June update on Linkedin Email 26 June update link

    Plastering has been completed in both the toilet and foyer areas, and the installation of the windows and internal fix-out has also been finalised in the toilet areas.

    All painting within the toilet areas is now complete.

    The builder has poured the front entry slab and is currently working on framing the remaining entry section.

    Over the next two weeks, the team will focus on completing all framing, installing the remaining sections of the roof, and fitting out the toilet areas with fixtures and finishes.

  • ๐Ÿ“… June 2025

    Share ๐Ÿ“… June 2025 on Facebook Share ๐Ÿ“… June 2025 on Twitter Share ๐Ÿ“… June 2025 on Linkedin Email ๐Ÿ“… June 2025 link

    Work is steadily progressing on the upgrade of the Hall, with more milestones recently reached.

    Plasterboard sheeting has now been installed throughout the upgraded toilet areas, and the plumber has completed all under-slab rough-in works.

    Despite ongoing wet weather affecting ground conditions in Mallacoota, the builderโ€™s team is continuing with slab preparation to keep the project moving forward.

    We appreciate the communityโ€™s patience as we work through these weather challenges and look forward to delivering a more functional and improved facility for all to enjoy.



  • ๐Ÿ“… May 2025

    Share ๐Ÿ“… May 2025 on Facebook Share ๐Ÿ“… May 2025 on Twitter Share ๐Ÿ“… May 2025 on Linkedin Email ๐Ÿ“… May 2025 link

    The building contractor has completed work on the retaining wall, an important structural element of the upgrade. Now complete, attention has turned to finishing the front entrance slab and progressing with the lift installation, both of which are key to improving accessibility and functionality.

    โœ… Milestone Achieved
    The asbestos ceiling removal and re-roofing have been successfully completed. This marks a major milestone in the project, ensuring a safer and more modern facility for the community.

    ๐Ÿ› ๏ธ Upcoming Works
    Plastering is scheduled to begin at the end of May, starting with the toilet area and the higher sections of the foyer. The first stage of plastering is expected to be completed within a couple of weeks.

    Thank you for your continued support and patience as we work to deliver a safer, more accessible, and revitalised community hall for everyone to enjoy.

Page last updated: 14 Nov 2025, 02:30 PM