Work on the Mallacoota Hall is well underway:
- Structural rectifications: The extension at the rear of the hall is now at lockup.
- Roof ridge capping: Redesigned to prevent leaks and enhance fireproofing; 80% complete.
- Interior works: Commenced, with materials ordered and solutions being developed for bathroom floor falls and finishes.
Discussions with the Committee of Management have continued throughout the delivery of this project.
The project timeline has been extended to June 2025, allowing our in-house teams to work with local Mallacoota businesses.
Share 16 September 2024 on Facebook
Share 16 September 2024 on Linkedin
Email 16 September 2024 link
Further updates will be provided on YourSay following the Council Election on 26 October 2024, and the questions/feedback tab will be reinstated.
From 12.00 noon Tuesday 17 September until 6.00 pm on Saturday 26 October (Election Day) we will be in the Local Government Election Period (also known as Caretaker Period).
During this time, we will limit our printed communications, website content, social media activity, and community consultations. The ability for people to comment on our social media content will also be disabled during the Election Period.
Each of these steps is to ensure our content does not affect voting in the election and is consistent with steps taken by other Victorian Councils and the Local Government Act 2020.
These changes are only temporary; we'll be back to normal communication activity after the election.
Share Project update 7 August 2024 on Facebook
Share Project update 7 August 2024 on Linkedin
Email Project update 7 August 2024 link
The Mallacoota Hall upgrade is aimed at enhancing functionality and accessibility.
Recent Site Meeting: On 30 July 2024, a site meeting was conducted with Council officers and our contractor to review the progress of the project and outline the remaining activities. This meeting was instrumental in ensuring that all parties are aligned and informed about the current status and next steps.
Progress Overview: Despite recent challenges posed by wet weather, which temporarily halted exterior works, significant progress has been made. The following updates are noteworthy:
- Footings for Rear Extension: The footings for the rear extension of the Hall have now been successfully completed. This critical stage was achieved as planned, and we are moving forward with the next phases of construction.
- Concrete Pour: Early this week, we conducted the concrete pour for the rear extension. This marks a significant milestone in the project, allowing us to proceed with further construction activities.
Next Steps:
- Continued work on the rear extension will be prioritised.
- Addressing remaining activities, including relocation of the main entry, redevelopment of toilets and change rooms, and expansion of the kitchen will then follow.
We appreciate your patience and continued support as we work to enhance the Hall's functionality and accessibility. Further updates will be provided as we reach new milestones and progress through the remaining activities within the project.
Share Project Update - 16 January 2024 on Facebook
Share Project Update - 16 January 2024 on Linkedin
Email Project Update - 16 January 2024 link
Works are progressing well, underpinning and the preliminary construction works have commenced. Once the stabilisation of the existing structure is complete the proposed new outline of the wall will be constructed.
Further updates will be made when available. Please choose to follow this project to receive important project updates directly to your inbox.
Share Project Update - 18 August 2023 on Facebook
Share Project Update - 18 August 2023 on Linkedin
Email Project Update - 18 August 2023 link
The Mallacoota Hall Upgrade has reached a milestone, with commencement of construction scheduled for October 2023.
The new design layout for the upgrade of the Mallacoota Hall has improved functional requirements, allowing flexibility for the Hall to be utilised as a sports venue, a place for meeting, and an important facility for refuge and recovery.
The new design meets all current Australian Regulations, Acts, Standards, and the requirements outlined in the design brief.
Council will undertake some of the works to meet budget requirements and program delivery deadlines.
A program for construction is now in development. Further updates and future venue closure notifications will be provided on YourSay once the program is established.
Share Project Update 28/02/2023 on Facebook
Share Project Update 28/02/2023 on Linkedin
Email Project Update 28/02/2023 link
- Detailed design for the building is in progress.
- A Building Surveyor has been engaged to advise on design regulatory compliance.
- Detailed design is scheduled to be completed by mid 2023.
- Construction by the EGSC building crew will commence shortly after the detailed design is finalised.