project update
Key milestone reached: lock-up
The hall has reached lock-up, meaning it’s fully enclosed and secure.
Recently completed
- Exterior cladding and roof flashings
- Kitchen plastering
- Concrete footpath poured at the rear of the building
- drainage pits - to help direct water away from the building
What’s happening now
- front entry extension
- Installation of the new kitchen
What’s next
- Painting - starting with the outside of the hall and the ceilings in the kitchen and foyer.
- Prepare for the lift installation, improving accessibility.
- Vinyl flooring in the kitchen.
- Final plastering of the remaining internal areas.
- Install a new accessible car park.
![]() |
![]() |
![]() |