project update

Key milestone reached: lock-up

The hall has reached lock-up, meaning it’s fully enclosed and secure.

Recently completed

  • Exterior cladding and roof flashings
  • Kitchen plastering
  • Concrete footpath poured at the rear of the building
  • drainage pits - to help direct water away from the building

What’s happening now

  • front entry extension
  • Installation of the new kitchen

What’s next

  • Painting - starting with the outside of the hall and the ceilings in the kitchen and foyer.
  • Prepare for the lift installation, improving accessibility.
  • Vinyl flooring in the kitchen.
  • Final plastering of the remaining internal areas.
  • Install a new accessible car park.