September 2025
The Mallacoota Community Hall project remains on track, with ongoing works steadily transforming the space for community use.
Recently Completed:
- The front entry extension has now been fully plastered and the fix-out works throughout this area are complete.
- The lift shaft has been demolished, with the base re-poured and a Besser block wall constructed in preparation for the new lift installation.
- The vinyl flooring in the kitchen is currently being laid.
- A new accessible car park has been installed and line-marked, improving access to the facility.
- The external facade of the hall has been freshly painted, enhancing the building’s appearance.
Next Steps:
- Internal and remaining external painting of the hall.
- Fit-off works in the remaining hall areas.
- Garden preparation, including re-mulching of existing garden beds to refresh the landscaping.
We appreciate the community’s ongoing support and look forward to delivering a revitalised facility that meets the needs of all users.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |