πŸ”¨πŸ‘·πŸ»β€β™‚οΈ Construction is progressing well on site -

  • Front entry is framed
  • All windows installed

The plumber has completed the remaining roofing and is now moving ahead with the final rough-in works. The electrician is also on site, completing the last of the rough-in tasks.

What’s coming up in the next two weeks:

  • The builder will begin installing the external cladding, which will start to bring the building’s exterior to life.
  • Internal toilet areas will be fully fitted off, marking another important milestone.