📅 August 2025
What's happening now:
- Cladding installation: The majority of external cladding has been completed. The builder is progressing toward lock-up stage, expected in the coming weeks.
- Generator relocation: The generator has been relocated to the new storage shed and is now up and running to supply power to the hall.
- Internal linings: Plastering contractors have commenced the remaining internal wall and ceiling linings throughout the hall.
What's next:
- Completion of external cladding and transition to lock-up
- Finalisation of internal plastering
- Commencement of internal fit-off, including joinery, fixtures, and finishes
![]() |
![]() |
![]() |
![]() |