26 June update
Plastering has been completed in both the toilet and foyer areas, and the installation of the windows and internal fix-out has also been finalised in the toilet areas.
All painting within the toilet areas is now complete.
The builder has poured the front entry slab and is currently working on framing the remaining entry section.
Over the next two weeks, the team will focus on completing all framing, installing the remaining sections of the roof, and fitting out the toilet areas with fixtures and finishes.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |