๐ May 2025
The building contractor has completed work on the retaining wall, an important structural element of the upgrade. Now complete, attention has turned to finishing the front entrance slab and progressing with the lift installation, both of which are key to improving accessibility and functionality.
โ
Milestone Achieved
The asbestos ceiling removal and re-roofing have been successfully completed. This marks a major milestone in the project, ensuring a safer and more modern facility for the community.
๐ ๏ธ Upcoming Works
Plastering is scheduled to begin at the end of May, starting with the toilet area and the higher sections of the foyer. The first stage of plastering is expected to be completed within a couple of weeks.
Thank you for your continued support and patience as we work to deliver a safer, more accessible, and revitalised community hall for everyone to enjoy.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |

Thank you for your contribution!