Buchan - Recreation Reserve Upgrade

Share Buchan - Recreation Reserve Upgrade on Facebook Share Buchan - Recreation Reserve Upgrade on Twitter Share Buchan - Recreation Reserve Upgrade on Linkedin Email Buchan - Recreation Reserve Upgrade link

Updates are provided in the tab below


The local Buchan community welcomed Council’s intention to upgrade and revitalise the recreation reserve with better sporting and community facilities to enrich the lifestyle, character, and resilience of the Buchan, Gelantipy and district communities.

Works commenced following the award of the contract for construction of the Netball / Tennis Courts at the 25 June 2024 Council meeting. We commend the local Buchan community and Project Reference Group in their efforts to progress the project to this key milestone.



Background

East Gippsland Shire Council, with the support of State and Federal Government, and Community funding, is investing in the development of the Buchan Recreational Reserve Master Plan.

Sport and recreation play a vital role in bringing the local community together and this investment in the Buchan Recreational Reserve reflects Council’s strategic vision to recognise that an active and connected community is better placed to build resilience and recover following the difficulties experienced by small communities, like Buchan, during times of natural disaster events.

The Buchan Recreation Reserve is a large community open space reserve located within the village precinct of Buchan and adjacent to the beautiful Buchan River. The reserve provides the local community with a critical staging and refuge facility during natural disaster events and is a well-used local sports ground and community hall facility, being home to four local sporting clubs – pony, netball, tennis, football, and cricket.

The Master Plan was developed in 2021 following community consultation. The local Buchan community welcomed Council’s intention to upgrade and revitalise the reserve with new and improved sporting and community facilities. The plan addresses the community’s preferences by providing a revitalised modern community hub and sporting facility. Areas identified by the plan for improvement include the netball and tennis courts, shared pavilion and amenities, carparking, lighting, football oval, pony club and cricket facilities. Other exciting features of the master plan include a new children’s playground.

This project is jointly funded by the Victorian Government and Commonwealth Government under the Commonwealth-State Disaster Recovery Funding Arrangements


Updates are provided in the tab below


The local Buchan community welcomed Council’s intention to upgrade and revitalise the recreation reserve with better sporting and community facilities to enrich the lifestyle, character, and resilience of the Buchan, Gelantipy and district communities.

Works commenced following the award of the contract for construction of the Netball / Tennis Courts at the 25 June 2024 Council meeting. We commend the local Buchan community and Project Reference Group in their efforts to progress the project to this key milestone.



Background

East Gippsland Shire Council, with the support of State and Federal Government, and Community funding, is investing in the development of the Buchan Recreational Reserve Master Plan.

Sport and recreation play a vital role in bringing the local community together and this investment in the Buchan Recreational Reserve reflects Council’s strategic vision to recognise that an active and connected community is better placed to build resilience and recover following the difficulties experienced by small communities, like Buchan, during times of natural disaster events.

The Buchan Recreation Reserve is a large community open space reserve located within the village precinct of Buchan and adjacent to the beautiful Buchan River. The reserve provides the local community with a critical staging and refuge facility during natural disaster events and is a well-used local sports ground and community hall facility, being home to four local sporting clubs – pony, netball, tennis, football, and cricket.

The Master Plan was developed in 2021 following community consultation. The local Buchan community welcomed Council’s intention to upgrade and revitalise the reserve with new and improved sporting and community facilities. The plan addresses the community’s preferences by providing a revitalised modern community hub and sporting facility. Areas identified by the plan for improvement include the netball and tennis courts, shared pavilion and amenities, carparking, lighting, football oval, pony club and cricket facilities. Other exciting features of the master plan include a new children’s playground.

This project is jointly funded by the Victorian Government and Commonwealth Government under the Commonwealth-State Disaster Recovery Funding Arrangements


  • 📅 March 2026

    Share 📅 March 2026 on Facebook Share 📅 March 2026 on Twitter Share 📅 March 2026 on Linkedin Email 📅 March 2026 link

    Works are continuing to move ahead steadily.

    What’s been happening on site

    Significant progress has been made across the pavilion and surrounding facilities:

    • Kitchen and bar areas are now taking shape; the stainless-steel benchtops are installed and approximately 385 square metres of wall tiles completed.
    • All floor coverings have now been installed throughout the pavilion.
    • Veranda decking is complete, with handrails and balustrades to follow soon.
    • Footpaths around the pavilion are finished, paving the way for installation of the bleacher seating framework.
    • External signage has been installed above the social room doors.
    • Plumbing works are well advanced, including installation of fixtures, hot water systems and firefighting tanks.
    • Electrical works are nearing completion.
    • Painters are currently on-site applying finishing touches.
    • Subfloor cladding is underway, providing important ember protection for the building.
    • Concrete pads for stairs have been poured, and stair fabrication is underway.

    Sustainable and supporting infrastructure

    • Installation of 85 solar panels with 65kW battery storage is progressing, supporting long‑term sustainability.
    • Pipework for power and water has been installed from the new pavilion to the cricket and football facilities.
    • Trenching and preparation for the football and cricket storage sheds is complete, with slabs poured and works continuing.

    Sports and recreation improvements

    • Works to the netball fencing have enabled shelter installation.
    • The old mesh has been removed from the existing cricket nets.
    • 80 tonnes of arena sand and fertiliser have been applied to top dress the oval.

    What’s next

    Over the coming weeks, the focus will be on:

    • Completing electrical and plumbing fit‑off.
    • Installing balustrades and handrails.
    • Finalising bleacher seating and stairs.
    • Completing storage sheds and remaining external works.


    This project is really starting to show its potential, with many key elements now complete and the pavilion coming together both inside and out. Thank you to the Buchan community for your patience and support as works continue. We look forward to sharing more updates as we get closer to completion.

    Subscribe to receive updates directly to your inbox.



    Works are continuing to move ahead steadily.

    What’s been happening on site

    Significant progress has been made across the pavilion and surrounding facilities:

    • Kitchen and bar areas are now taking shape; the stainless-steel benchtops are installed and approximately 385 square metres of wall tiles completed.
    • All floor coverings have now been installed throughout the pavilion.
    • Veranda decking is complete, with handrails and balustrades to follow soon.
    • Footpaths around the pavilion are finished, paving the way for installation of the bleacher seating framework.
    • External signage has been installed above the social room doors.
    • Plumbing works are well advanced, including installation of fixtures, hot water systems and firefighting tanks.
    • Electrical works are nearing completion.
    • Painters are currently on-site applying finishing touches.
    • Subfloor cladding is underway, providing important ember protection for the building.
    • Concrete pads for stairs have been poured, and stair fabrication is underway.

    Sustainable and supporting infrastructure

    • Installation of 85 solar panels with 65kW battery storage is progressing, supporting long‑term sustainability.
    • Pipework for power and water has been installed from the new pavilion to the cricket and football facilities.
    • Trenching and preparation for the football and cricket storage sheds is complete, with slabs poured and works continuing.

    Sports and recreation improvements

    • Works to the netball fencing have enabled shelter installation.
    • The old mesh has been removed from the existing cricket nets.
    • 80 tonnes of arena sand and fertiliser have been applied to top dress the oval.

    What’s next

    Over the coming weeks, the focus will be on:

    • Completing electrical and plumbing fit‑off.
    • Installing balustrades and handrails.
    • Finalising bleacher seating and stairs.
    • Completing storage sheds and remaining external works.


    This project is really starting to show its potential, with many key elements now complete and the pavilion coming together both inside and out. Thank you to the Buchan community for your patience and support as works continue. We look forward to sharing more updates as we get closer to completion.

    Subscribe to receive updates directly to your inbox.



  • 📅 January 2026

    Share 📅 January 2026 on Facebook Share 📅 January 2026 on Twitter Share 📅 January 2026 on Linkedin Email 📅 January 2026 link

    Construction has resumed at the Buchan Recreation Reserve Pavilion following the Christmas break, and the new pavilion is continuing to take shape. The project is progressing well and is currently tracking towards completion in April 2026.

    Just before Christmas, we had the opportunity to take the Buchan Recreation Reserve Committee of Management through the building. The size of the pavilion and the progress made to date generated a lot of excitement, and the site visit was a great opportunity to share a milestone moment in the project.

    What’s happening on site

    A range of works will be underway over the next fortnight, including:

    • Vinyl flooring being installed in the toilet and shower areas.
    • Internal painting progressing in several rooms.
    • Builders returning to site and continuing works on the large outdoor deck.
    • Mechanical services contractors reconnecting air‑handling systems.
    • Kitchen and bar stainless‑steel benchtops measured, with installation expected in the coming weeks.
    • Installation of the roof‑mounted safety arrest system.
    • Preparation for solar panels and battery systems, scheduled to be installed shortly.
    • Soil spoil being sieved for reuse on site at a later stage.
    • Awaiting delivery of fibreglass mesh decking for installation on the all‑abilities ramp.
    • Delivery expected soon for toilet and shower partitions, as well as internal player seating.
    • Bushfire fighting tanks and the football and cricket storage shed now ordered.

    This steady progress continues to build momentum toward completion and is creating strong anticipation for the finished facility.

    Construction has resumed at the Buchan Recreation Reserve Pavilion following the Christmas break, and the new pavilion is continuing to take shape. The project is progressing well and is currently tracking towards completion in April 2026.

    Just before Christmas, we had the opportunity to take the Buchan Recreation Reserve Committee of Management through the building. The size of the pavilion and the progress made to date generated a lot of excitement, and the site visit was a great opportunity to share a milestone moment in the project.

    What’s happening on site

    A range of works will be underway over the next fortnight, including:

    • Vinyl flooring being installed in the toilet and shower areas.
    • Internal painting progressing in several rooms.
    • Builders returning to site and continuing works on the large outdoor deck.
    • Mechanical services contractors reconnecting air‑handling systems.
    • Kitchen and bar stainless‑steel benchtops measured, with installation expected in the coming weeks.
    • Installation of the roof‑mounted safety arrest system.
    • Preparation for solar panels and battery systems, scheduled to be installed shortly.
    • Soil spoil being sieved for reuse on site at a later stage.
    • Awaiting delivery of fibreglass mesh decking for installation on the all‑abilities ramp.
    • Delivery expected soon for toilet and shower partitions, as well as internal player seating.
    • Bushfire fighting tanks and the football and cricket storage shed now ordered.

    This steady progress continues to build momentum toward completion and is creating strong anticipation for the finished facility.

  • 📅 November 2025

    Share 📅 November 2025 on Facebook Share 📅 November 2025 on Twitter Share 📅 November 2025 on Linkedin Email 📅 November 2025 link

    The building has progressed beyond the lock-up stage.

    • All internal doors installed and some wall tiling completed.
    • Prefinished ceiling linings in the social rooms have been installed.
    • The kitchen exhaust rangehood is now in place.
    • Internal and external roller doors for the pavilion have been fitted.
    • Carpenters are working on the external decking, focusing on the plant area.
    • Civil contractors have installed a new fire main and upgraded stormwater infrastructure.
    • Works on the wastewater treatment area are scheduled to commence.
    • Wall and roof cladding for the new netball and tennis storage shed have been completed.

    The project is on track for completion in early 2026.


    The building has progressed beyond the lock-up stage.

    • All internal doors installed and some wall tiling completed.
    • Prefinished ceiling linings in the social rooms have been installed.
    • The kitchen exhaust rangehood is now in place.
    • Internal and external roller doors for the pavilion have been fitted.
    • Carpenters are working on the external decking, focusing on the plant area.
    • Civil contractors have installed a new fire main and upgraded stormwater infrastructure.
    • Works on the wastewater treatment area are scheduled to commence.
    • Wall and roof cladding for the new netball and tennis storage shed have been completed.

    The project is on track for completion in early 2026.


  • 📅 October 2025

    Share 📅 October 2025 on Facebook Share 📅 October 2025 on Twitter Share 📅 October 2025 on Linkedin Email 📅 October 2025 link

    The building is now at lock up stage.

    • The changeroom has been fully plastered – painters are now undercoating the walls and painting the ceilings prior to the installation of wall tiles and fixtures.
    • Some wall tiling has been completed.
    • The social room walls have been plastered, and prefinished ceiling panels will arrive soon.
    • The carpenters are working tirelessly to install the decking around the outside of the building.
    • Civil contractors are installing a new fire main and new stormwater infrastructure.
    • The new netball and tennis storage shed wall and roof framing has been installed.

    The project is on track for completion in early 2026.



    The building is now at lock up stage.

    • The changeroom has been fully plastered – painters are now undercoating the walls and painting the ceilings prior to the installation of wall tiles and fixtures.
    • Some wall tiling has been completed.
    • The social room walls have been plastered, and prefinished ceiling panels will arrive soon.
    • The carpenters are working tirelessly to install the decking around the outside of the building.
    • Civil contractors are installing a new fire main and new stormwater infrastructure.
    • The new netball and tennis storage shed wall and roof framing has been installed.

    The project is on track for completion in early 2026.



  • 📅 September 2025

    Share 📅 September 2025 on Facebook Share 📅 September 2025 on Twitter Share 📅 September 2025 on Linkedin Email 📅 September 2025 link

    Construction continues to progress well, with several new developments:

    • Structural steel installation has begun on the west side all-ability ramp.
    • Concrete works are underway on the east side ramp.
    • The external linings and soffit cladding are nearly complete.
    • The elevated slab for the new generator is being formed.
    • Internal wall and ceiling linings are advancing, with joint finishing in progress.
    • The tennis and netball storage shed floor has been poured.

    The builder remains on track for completion in 2026.


    Thank you for your ongoing support.

    Construction continues to progress well, with several new developments:

    • Structural steel installation has begun on the west side all-ability ramp.
    • Concrete works are underway on the east side ramp.
    • The external linings and soffit cladding are nearly complete.
    • The elevated slab for the new generator is being formed.
    • Internal wall and ceiling linings are advancing, with joint finishing in progress.
    • The tennis and netball storage shed floor has been poured.

    The builder remains on track for completion in 2026.


    Thank you for your ongoing support.

  • 📅 26 August 2025

    Share 📅 26 August 2025 on Facebook Share 📅 26 August 2025 on Twitter Share 📅 26 August 2025 on Linkedin Email 📅 26 August 2025 link

    Recently completed

    • veranda floor joists


    What's happening on site

    • West ramp structural steel installation
    • External linings and claddings
    • Civil concrete works
    • Internal linings
    • Preparation for the tennis and netball storage shed concrete floor
    • Hydraulic, mechanical, and electrical services roughed in
    • Soffit lining

    We are still on track for completion in 2026.


    Recently completed

    • veranda floor joists


    What's happening on site

    • West ramp structural steel installation
    • External linings and claddings
    • Civil concrete works
    • Internal linings
    • Preparation for the tennis and netball storage shed concrete floor
    • Hydraulic, mechanical, and electrical services roughed in
    • Soffit lining

    We are still on track for completion in 2026.


  • 📅 August 2025

    Share 📅 August 2025 on Facebook Share 📅 August 2025 on Twitter Share 📅 August 2025 on Linkedin Email 📅 August 2025 link

    Current activities on site -

    • Plumbing, electrical, data/security and mechanical rough-in
    • Window installation
    • Deck framing
    • Wall cladding
    • Eave/soffit lining

    Works are currently on schedule for completion in 2026.

    Current activities on site -

    • Plumbing, electrical, data/security and mechanical rough-in
    • Window installation
    • Deck framing
    • Wall cladding
    • Eave/soffit lining

    Works are currently on schedule for completion in 2026.

  • July 2025

    Share July 2025 on Facebook Share July 2025 on Twitter Share July 2025 on Linkedin Email July 2025 link

    Despite recent delays caused by heavy rainfall and flooding of the Buchan River, the upgrade works at the Buchan Recreation Reserve are progressing well, with strong momentum behind the construction of the new pavilion.

    • Roof installation is nearing completion with capping and flashing to be installed shortly.
    • Window frames installed, glazing to follow soon.
    • Hydraulic, mechanical, and electrical services to start roughing in this week.
    • Plasterers have started installing furring channels ready to support the internal wall linings.


    We were pleased to welcome Emergency Recovery Victoria CEO Mariela Diaz, members of the Buchan Recreation Reserve Committee of Management, and our own General Manager Assets and Environment, Stuart McConnell, along with the projects team, for a site visit to review progress firsthand. Their support and engagement are greatly appreciated as we work together to deliver this important community asset.

    Despite recent delays caused by heavy rainfall and flooding of the Buchan River, the upgrade works at the Buchan Recreation Reserve are progressing well, with strong momentum behind the construction of the new pavilion.

    • Roof installation is nearing completion with capping and flashing to be installed shortly.
    • Window frames installed, glazing to follow soon.
    • Hydraulic, mechanical, and electrical services to start roughing in this week.
    • Plasterers have started installing furring channels ready to support the internal wall linings.


    We were pleased to welcome Emergency Recovery Victoria CEO Mariela Diaz, members of the Buchan Recreation Reserve Committee of Management, and our own General Manager Assets and Environment, Stuart McConnell, along with the projects team, for a site visit to review progress firsthand. Their support and engagement are greatly appreciated as we work together to deliver this important community asset.

  • June 2025

    Share June 2025 on Facebook Share June 2025 on Twitter Share June 2025 on Linkedin Email June 2025 link

    Despite the rain and wind slowing progress over the last 2 weeks, the works are well advanced thanks to the builder's robust resourcing; including 7-8 carpenters and 3 plumbers on-site.

    • flat roof sections installed
    • wall framing complete.
    • windows have been site measured and are in production.
    • some reflective foil insulation has been installed together with battens to some of the outside walls.

    What's next?

    • soaker-flashings being installed to accommodate the angled roof sections.
    • hydraulic services to the sub floor area will start next week along with electrical cable trays.

    The project remains on track for completion in 2026.


    Despite the rain and wind slowing progress over the last 2 weeks, the works are well advanced thanks to the builder's robust resourcing; including 7-8 carpenters and 3 plumbers on-site.

    • flat roof sections installed
    • wall framing complete.
    • windows have been site measured and are in production.
    • some reflective foil insulation has been installed together with battens to some of the outside walls.

    What's next?

    • soaker-flashings being installed to accommodate the angled roof sections.
    • hydraulic services to the sub floor area will start next week along with electrical cable trays.

    The project remains on track for completion in 2026.


  • 📅 May 2025

    Share 📅 May 2025 on Facebook Share 📅 May 2025 on Twitter Share 📅 May 2025 on Linkedin Email 📅 May 2025 link

    On Friday 9 May, we hosted representatives from Emergency Recovery Victoria (ERV) and the Project Reference Group (PRG) for a site visit to the pavilion construction site.

    Attendees were impressed by the scale and progress of the works, particularly the fully erected steel frame, and provided encouraging feedback. Community interest and enthusiasm for the project remain strong.

    Tennis / Netball courts

    • SP Ausnet has connected power to the new Main Switchboard (MSSB), bringing electricity to the Netball lights, Pony Club shed, and social rooms.
    • The Netball contractor conducted testing of the Netball and Tennis court lights last night. We are currently awaiting the results.
    • Netball training was held under the new lighting system, a great milestone for the project and the local sporting community.

    Pavilion Construction

    • All structural steel has been erected on site.
    • The builder is completing the last sections of flooring and has commenced infilling the external walls.
    • Roof materials have been ordered and are expected to arrive soon. If weather and conditions permit, initial roof installation may begin in the coming weeks.
    • Site measurements for windows are scheduled for next week.

    The structure is substantial, incorporating around 50 tonnes of steel and 1.5 kilometres of floor joists. This phase alone involves the installation of 400 joist hangers and approximately 29,000 nails!

    The project remains on track and within budget; we are targeting project completion in 2026.


    On Friday 9 May, we hosted representatives from Emergency Recovery Victoria (ERV) and the Project Reference Group (PRG) for a site visit to the pavilion construction site.

    Attendees were impressed by the scale and progress of the works, particularly the fully erected steel frame, and provided encouraging feedback. Community interest and enthusiasm for the project remain strong.

    Tennis / Netball courts

    • SP Ausnet has connected power to the new Main Switchboard (MSSB), bringing electricity to the Netball lights, Pony Club shed, and social rooms.
    • The Netball contractor conducted testing of the Netball and Tennis court lights last night. We are currently awaiting the results.
    • Netball training was held under the new lighting system, a great milestone for the project and the local sporting community.

    Pavilion Construction

    • All structural steel has been erected on site.
    • The builder is completing the last sections of flooring and has commenced infilling the external walls.
    • Roof materials have been ordered and are expected to arrive soon. If weather and conditions permit, initial roof installation may begin in the coming weeks.
    • Site measurements for windows are scheduled for next week.

    The structure is substantial, incorporating around 50 tonnes of steel and 1.5 kilometres of floor joists. This phase alone involves the installation of 400 joist hangers and approximately 29,000 nails!

    The project remains on track and within budget; we are targeting project completion in 2026.


Page last updated: 26 Mar 2026, 10:31 AM