Buchan - Recreation Reserve Upgrade

Share Buchan - Recreation Reserve Upgrade on Facebook Share Buchan - Recreation Reserve Upgrade on Twitter Share Buchan - Recreation Reserve Upgrade on Linkedin Email Buchan - Recreation Reserve Upgrade link

The local Buchan community welcomed Council’s intention to upgrade and revitalise the recreation reserve with better sporting and community facilities to enrich the lifestyle, character, and resilience of the Buchan, Gelantipy and district communities.

Works commenced following the award of the contract for construction of the Netball / Tennis Courts at the 25 June 2024 Council meeting. We commend the local Buchan community and Project Reference Group in their efforts to progress the project to this key milestone.



Background

East Gippsland Shire Council, with the support of State and Federal Government, and Community funding, is investing in the development of the Buchan Recreational Reserve Master Plan.

Sport and recreation play a vital role in bringing the local community together and this investment in the Buchan Recreational Reserve reflects Council’s strategic vision to recognise that an active and connected community is better placed to build resilience and recover following the difficulties experienced by small communities, like Buchan, during times of natural disaster events.

The Buchan Recreation Reserve is a large community open space reserve located within the village precinct of Buchan and adjacent to the beautiful Buchan River. The reserve provides the local community with a critical staging and refuge facility during natural disaster events and is a well-used local sports ground and community hall facility, being home to four local sporting clubs – pony, netball, tennis, football, and cricket.

The Master Plan was developed in 2021 following community consultation. The local Buchan community welcomed Council’s intention to upgrade and revitalise the reserve with new and improved sporting and community facilities. The plan addresses the community’s preferences by providing a revitalised modern community hub and sporting facility. Areas identified by the plan for improvement include the netball and tennis courts, shared pavilion and amenities, carparking, lighting, football oval, pony club and cricket facilities. Other exciting features of the master plan include a new children’s playground.

This project is jointly funded by the Victorian Government and Commonwealth Government under the Commonwealth-State Disaster Recovery Funding Arrangements


The local Buchan community welcomed Council’s intention to upgrade and revitalise the recreation reserve with better sporting and community facilities to enrich the lifestyle, character, and resilience of the Buchan, Gelantipy and district communities.

Works commenced following the award of the contract for construction of the Netball / Tennis Courts at the 25 June 2024 Council meeting. We commend the local Buchan community and Project Reference Group in their efforts to progress the project to this key milestone.



Background

East Gippsland Shire Council, with the support of State and Federal Government, and Community funding, is investing in the development of the Buchan Recreational Reserve Master Plan.

Sport and recreation play a vital role in bringing the local community together and this investment in the Buchan Recreational Reserve reflects Council’s strategic vision to recognise that an active and connected community is better placed to build resilience and recover following the difficulties experienced by small communities, like Buchan, during times of natural disaster events.

The Buchan Recreation Reserve is a large community open space reserve located within the village precinct of Buchan and adjacent to the beautiful Buchan River. The reserve provides the local community with a critical staging and refuge facility during natural disaster events and is a well-used local sports ground and community hall facility, being home to four local sporting clubs – pony, netball, tennis, football, and cricket.

The Master Plan was developed in 2021 following community consultation. The local Buchan community welcomed Council’s intention to upgrade and revitalise the reserve with new and improved sporting and community facilities. The plan addresses the community’s preferences by providing a revitalised modern community hub and sporting facility. Areas identified by the plan for improvement include the netball and tennis courts, shared pavilion and amenities, carparking, lighting, football oval, pony club and cricket facilities. Other exciting features of the master plan include a new children’s playground.

This project is jointly funded by the Victorian Government and Commonwealth Government under the Commonwealth-State Disaster Recovery Funding Arrangements


  • 📅 May 2025

    Share 📅 May 2025 on Facebook Share 📅 May 2025 on Twitter Share 📅 May 2025 on Linkedin Email 📅 May 2025 link

    On Friday 9 May, we hosted representatives from Emergency Recovery Victoria (ERV) and the Project Reference Group (PRG) for a site visit to the pavilion construction site.

    Attendees were impressed by the scale and progress of the works, particularly the fully erected steel frame, and provided encouraging feedback. Community interest and enthusiasm for the project remain strong.

    Tennis / Netball courts

    • SP Ausnet has connected power to the new Main Switchboard (MSSB), bringing electricity to the Netball lights, Pony Club shed, and social rooms.
    • The Netball contractor conducted testing of the Netball and Tennis court lights last night. We are currently awaiting the results.
    • Netball training was held under the new lighting system, a great milestone for the project and the local sporting community.

    Pavilion Construction

    • All structural steel has been erected on site.
    • The builder is completing the last sections of flooring and has commenced infilling the external walls.
    • Roof materials have been ordered and are expected to arrive soon. If weather and conditions permit, initial roof installation may begin in the coming weeks.
    • Site measurements for windows are scheduled for next week.

    The structure is substantial, incorporating around 50 tonnes of steel and 1.5 kilometres of floor joists. This phase alone involves the installation of 400 joist hangers and approximately 29,000 nails!

    The project remains on track and within budget; we are targeting project completion in 2026.


  • update on the golden poplar trees

    Share update on the golden poplar trees on Facebook Share update on the golden poplar trees on Twitter Share update on the golden poplar trees on Linkedin Email update on the golden poplar trees link

    Feedback on the proposed removal of the two large golden poplar trees at the entrance to the Buchan Recreation Reserve revealed strong community sentiment.

    Thank you to everyone who shared their thoughts and experiences regarding the golden poplar trees at the Buchan Recreation Reserve.

    Feedback reflects a diverse range of community perspectives; some expressed deep emotional and cultural connections to the trees, while others voiced concerns of safety, maintenance, and long-term sustainability.

    All feedback has been thoughtfully considered, and we’ve also sought independent arborist advice to help guide our approach. The health, safety, and heritage of the site are all being carefully weighed as part of this process.

    We're waiting for the arborist to finish additional investigation before making a final decision.

    Thank you again for your contribution and for your understanding as we continue to work through this important matter with care and consideration.

  • 1 May 2025

    Share 1 May 2025 on Facebook Share 1 May 2025 on Twitter Share 1 May 2025 on Linkedin Email 1 May 2025 link

    🏐 Netball courts

    • Court surface & markings - the court coating and line marking have been successfully completed.
    • Fixtures & handover - All court fixtures have been installed. The courts have now been officially handed over and are available for netball training and games.
    • Electrical infrastructure - SP AusNet has completed the installation of the new power pole and transformer on the street, along with the underground cabling.
    • Lighting status - The netball court lights remain non-operational until SP AusNet completes the final power connection.
    • Power connection follow-up - we have been actively engaging with SP AusNet to secure a connection date. However, a confirmed timeline for the power connection has not yet been provided.

    Pavilion construction

    • Steelwork Installation:

      • 100% of the pavilion steelwork has been delivered to site.
      • Approximately 95% of the subfloor steel and 80% of the roof structure have been installed.
      • Steel erection will continue over the coming weeks.
    • Carpentry works - carpenters are currently installing floor joists onto the steel bearers as part of the next construction phase.

    • Project timeline - the builder remains on schedule with the current works program, targeting project completion in 2026.


  • April 2025 update

    Share April 2025 update on Facebook Share April 2025 update on Twitter Share April 2025 update on Linkedin Email April 2025 update link

    Some 80% of the steel framing for the Recreation Reserve pavilion – part of the Buchan Recreation Reserve Master Plan – has been delivered to site and the builders are busily putting it together.

    Read more >>>

  • February - March 2025 progress update

    Share February - March 2025 progress update on Facebook Share February - March 2025 progress update on Twitter Share February - March 2025 progress update on Linkedin Email February - March 2025 progress update link

    Netball and Tennis Court

    Everyone's buzzing with excitement as significant progress is made on the netball and tennis courts.

    The new light poles and lights have been installed and tested, ensuring bright and safe play areas. The new asphalt will soon be ready for the contractor to begin preparations for coating and line marking. Weather permitting, the coating is expected to be completed by the end of March 2025.

    The court fencing is nearly finished, with gates soon to be installed. Following the coating, netball rings and tennis posts will be set up, complementing the already installed basketball ring.

    A power upgrade is scheduled, with SP Ausnet installing a new pole and transformer in the first week of April 2025. We are eagerly awaiting the power connection date to light up the new courts.

    Pavilion Project

    The pavilion project is also on track. All concrete footings are complete, along with some stormwater drainage and pits.

    The pavilion will feature a robust steel frame with a timber substructure, promising a sturdy and welcoming facility for all. With 80% of the steel subfloor delivered, contractors have begun erecting it.

    The builder remains on schedule, aiming for completion in 2026.

    Stay tuned for more updates as these exciting projects continue to unfold!

    Pavilion subfloor steel work
    New lights being tested
    New court fencing
  • proposed tree removal

    Share proposed tree removal on Facebook Share proposed tree removal on Twitter Share proposed tree removal on Linkedin Email proposed tree removal link

    The Buchan Recreation Reserve Committee of Management has asked us to consider removing three trees at the reserve.

    The reason for this request is due to their proximity to existing buildings and court infrastructure, as outlined in the attached plan. During the design phase, every effort was made to retain trees where feasible, but trees situated too close to infrastructure - where their root systems could be compromised or pose potential structural risks - have been identified for removal.

    We are intending to progress with this Committee of Management request for the removal of the trees; however, if you have any questions or concerns about the tree removal, please contact us by 31 March 2025.

    We acknowledge the environmental and community value of trees, and this decision has not been made lightly. We appreciate your understanding as we work to enhance the safety and sustainability of Buchan Recreation Reserve for all users.

    If you represent a local group that could utilise the timber from the removed trees for a positive purpose, please contact Mark Tickner at 5153 9500 to discuss potential opportunities.

  • 18 December 2024

    Share 18 December 2024 on Facebook Share 18 December 2024 on Twitter Share 18 December 2024 on Linkedin Email 18 December 2024 link

    Sports courts

    • The proof roll and compaction test for the 2nd layer of court base has been approved.
    • Most of the perimeter fence posts have been installed so our concreter can start the formwork for the spoon drain and concrete pathways beside the netball court.
    • The steel reinforcement cages for the light poles have been delivered and pole footings will be dug in the new year.
    • The rebound hit-up wall concrete panel has been made off site and ready for delivery and installation in the new year.
    • We are hoping that asphalt will be installed late January [weather permitting].


    Pavilion

    Set out of the new pavilion works has taken place with the builder excavating and pouring more than 50% of the building's footings.


  • 19 November 2024

    Share 19 November 2024 on Facebook Share 19 November 2024 on Twitter Share 19 November 2024 on Linkedin Email 19 November 2024 link

    Netball /Tennis courts

    • The proof roll and compaction test for the 1st layer of the court base has been ticked off.
    • The court contractor will bring in stabilising material and compact it over the next few weeks.
    • The steel reinforcement cages for the light poles have been delivered; the light pole footings to be excavated soon.
    • Our fencing contractor is scheduled to start works shortly as many of these components need to be in before the concrete works can occur.
    • Structural plans for the rebound wall have been approved and the contractor has placed the order for production.

    Pavilion

    • A building permit for the new pavilion has been issued.
    • The builders now have possession of the site.
    • Set out of the new pavilion works to take place this week.
  • 4 October 2024

    Share 4 October 2024 on Facebook Share 4 October 2024 on Twitter Share 4 October 2024 on Linkedin Email 4 October 2024 link

    Netball court project

    The removal of soil for the retaining wall has been completed, and the pier holes for the wall were successfully finished with the posts now securely concreted in place.

    Installation of the concrete sleepers into the retaining wall has commenced this week. After the footings cure, compacted fill will be added against the retaining wall to create a solid foundation for both the netball court and the surrounding footpath.

    What's Next - Our contractor is set to begin the installation of new stormwater pipes designed to efficiently collect runoff from the courts and the new pavilion.

    Each workday involves trenching, laying pipes, and backfilling to ensure that there are no open trenches left overnight, with appropriate barricades in place for safety. Once the stormwater work is completed, the existing roadway into the reserve from Centre Road will be reopened for access.

    Pavilion project

    It is anticipated that the footings may be installed prior to Christmas, allowing for steel shop drawings to be approved, and the steel to be manufactured for erection early in the new year. A construction schedule will be put in place shortly.



    We welcome your continued interest in this project. Please choose to follow this project on YourSay to receive important information directly to your inbox.

  • 9 September 2024

    Share 9 September 2024 on Facebook Share 9 September 2024 on Twitter Share 9 September 2024 on Linkedin Email 9 September 2024 link

    Our contractor for the netball/tennis court construction is bringing in additional fill from the local quarry to reach the subbase level. Compaction of this material is scheduled to occur in the next few days.

    The demolition of the existing toilet block was completed on Tuesday, and site cleanup will continue throughout this week. A request for quote will be released in the coming weeks for the mobile tennis net.

    A contract has been signed and a site meeting held with Cadbuild Construction Pty Ltd, contractor for the changeroom pavilion. The construction schedule is being prepared with a tentative start date of early November 2024, pending building approvals.

    Demolished changerooms and toilet block area.

    Existing court Asphalt stripped, and fill being placed up to the subbase.

    Local quarry material being placed.



    We welcome your continued interest in this project. Please choose to follow this project on YourSay to receive important information directly to your inbox.

Page last updated: 28 May 2025, 03:47 PM