The building has progressed beyond the lock-up stage.

  • All internal doors installed and some wall tiling completed.
  • Prefinished ceiling linings in the social rooms have been installed.
  • The kitchen exhaust rangehood is now in place.
  • Internal and external roller doors for the pavilion have been fitted.
  • Carpenters are working on the external decking, focusing on the plant area.
  • Civil contractors have installed a new fire main and upgraded stormwater infrastructure.
  • Works on the wastewater treatment area are scheduled to commence.
  • Wall and roof cladding for the new netball and tennis storage shed have been completed.

The project is on track for completion in early 2026.