π November 2025
The building has progressed beyond the lock-up stage.
- All internal doors installed and some wall tiling completed.
- Prefinished ceiling linings in the social rooms have been installed.
- The kitchen exhaust rangehood is now in place.
- Internal and external roller doors for the pavilion have been fitted.
- Carpenters are working on the external decking, focusing on the plant area.
- Civil contractors have installed a new fire main and upgraded stormwater infrastructure.
- Works on the wastewater treatment area are scheduled to commence.
- Wall and roof cladding for the new netball and tennis storage shed have been completed.
The project is on track for completion in early 2026.