πŸ“… October 2025

The building is now at lock up stage.

  • The changeroom has been fully plastered – painters are now undercoating the walls and painting the ceilings prior to the installation of wall tiles and fixtures.
  • Some wall tiling has been completed.
  • The social room walls have been plastered, and prefinished ceiling panels will arrive soon.
  • The carpenters are working tirelessly to install the decking around the outside of the building.
  • Civil contractors are installing a new fire main and new stormwater infrastructure.
  • The new netball and tennis storage shed wall and roof framing has been installed.

The project is on track for completion in early 2026.