The building is now at lock up stage.
- The changeroom has been fully plastered β painters are now undercoating the walls and painting the ceilings prior to the installation of wall tiles and fixtures.
- Some wall tiling has been completed.
- The social room walls have been plastered, and prefinished ceiling panels will arrive soon.
- The carpenters are working tirelessly to install the decking around the outside of the building.
- Civil contractors are installing a new fire main and new stormwater infrastructure.
- The new netball and tennis storage shed wall and roof framing has been installed.
The project is on track for completion in early 2026.
![]() |
![]() |
![]() |
![]() |
![]() |