26 August 2025

Recently completed

  • veranda floor joists


What's happening on site

  • West ramp structural steel installation
  • External linings and claddings
  • Civil concrete works
  • Internal linings
  • Preparation for the tennis and netball storage shed concrete floor
  • Hydraulic, mechanical, and electrical services roughed in
  • Soffit lining

We are still on track for completion in 2026.