June 2025

Despite the rain and wind slowing progress over the last 2 weeks, the works are well advanced thanks to the builder's robust resourcing; including 7-8 carpenters and 3 plumbers on-site.

  • flat roof sections installed
  • wall framing complete.
  • windows have been site measured and are in production.
  • some reflective foil insulation has been installed together with battens to some of the outside walls.

What's next?

  • soaker-flashings being installed to accommodate the angled roof sections.
  • hydraulic services to the sub floor area will start next week along with electrical cable trays.

The project remains on track for completion in 2026.