June 2025
Despite the rain and wind slowing progress over the last 2 weeks, the works are well advanced thanks to the builder's robust resourcing; including 7-8 carpenters and 3 plumbers on-site.
- flat roof sections installed
- wall framing complete.
- windows have been site measured and are in production.
- some reflective foil insulation has been installed together with battens to some of the outside walls.
What's next?
- soaker-flashings being installed to accommodate the angled roof sections.
-
hydraulic services to the sub floor area will start next week along with electrical cable trays.
The project remains on track for completion in 2026.
![]() |
![]() |
![]() |