📅 September 2025

Construction continues to progress well, with several new developments:

  • Structural steel installation has begun on the west side all-ability ramp.
  • Concrete works are underway on the east side ramp.
  • The external linings and soffit cladding are nearly complete.
  • The elevated slab for the new generator is being formed.
  • Internal wall and ceiling linings are advancing, with joint finishing in progress.
  • The tennis and netball storage shed floor has been poured.

The builder remains on track for completion in 2026.


Thank you for your ongoing support.

Share 📅 September 2025 on Facebook Share 📅 September 2025 on Twitter Share 📅 September 2025 on Linkedin Email 📅 September 2025 link
#<Object:0x00007f4942a106c0>