July 2025

Despite recent delays caused by heavy rainfall and flooding of the Buchan River, the upgrade works at the Buchan Recreation Reserve are progressing well, with strong momentum behind the construction of the new pavilion.

  • Roof installation is nearing completion with capping and flashing to be installed shortly.
  • Window frames installed, glazing to follow soon.
  • Hydraulic, mechanical, and electrical services to start roughing in this week.
  • Plasterers have started installing furring channels ready to support the internal wall linings.


We were pleased to welcome Emergency Recovery Victoria CEO Mariela Diaz, members of the Buchan Recreation Reserve Committee of Management, and our own General Manager Assets and Environment, Stuart McConnell, along with the projects team, for a site visit to review progress firsthand. Their support and engagement are greatly appreciated as we work together to deliver this important community asset.

Share July 2025 on Facebook Share July 2025 on Twitter Share July 2025 on Linkedin Email July 2025 link
#<Object:0x0000000011675e88>