Bairnsdale - WORLD Sporting Precinct Redevelopment

Share Bairnsdale - WORLD Sporting Precinct Redevelopment on Facebook Share Bairnsdale - WORLD Sporting Precinct Redevelopment on Twitter Share Bairnsdale - WORLD Sporting Precinct Redevelopment on Linkedin Email Bairnsdale - WORLD Sporting Precinct Redevelopment link

About the Project

Women's Organisation for Recreation, Leisure and Development (WORLD)

This project originates from Council’s adoption of the Bairnsdale Sporting Facilities Plan in September 2018, which identified the project as a high priority due to the strong participation and growth in Netball, Hockey, Soccer and Futsal.

The project has attracted significant investment from both the Australian Government and the Victorian State Government in collectively providing grant funding and the Victorian Government providing funds through a low interest loan scheme.

Construction Package 1 – Main Car Park and Hockey Pitches, Hockey and soccer carparking, infrastructure.

Construction Package 2 – Netball Courts and Carparking construction.

Construction Package 3 – Netball and Hockey Pavilion (WORLD pavilion) construction.

Construction Package 4 – Soccer Precinct.

Project Scope

When complete, this project will provide the following regional level sporting facilities:

  • eight court netball precinct with Marshall’s building
  • synthetic hockey pitch with lighting
  • grass hockey pitch with lighting
  • synthetic soccer field with lighting
  • grass soccer field with lighting
  • all associated works including access roads, paths, electrical kiosk, car parking, landscaping, and water metering system
  • two new pavilions to service multiple clubs across the sporting codes

The staged construction has allowed the kindergarten to continue to provide services to the community, and a second Bairnsdale Netball Association season to go ahead. The footprint for the construction of the new soccer fields and soccer pavilion is currently undergoing environmental assessment and Environment Protection and Biodiversity Conservation Act 1999 (EPBC) approvals.



About the Project

Women's Organisation for Recreation, Leisure and Development (WORLD)

This project originates from Council’s adoption of the Bairnsdale Sporting Facilities Plan in September 2018, which identified the project as a high priority due to the strong participation and growth in Netball, Hockey, Soccer and Futsal.

The project has attracted significant investment from both the Australian Government and the Victorian State Government in collectively providing grant funding and the Victorian Government providing funds through a low interest loan scheme.

Construction Package 1 – Main Car Park and Hockey Pitches, Hockey and soccer carparking, infrastructure.

Construction Package 2 – Netball Courts and Carparking construction.

Construction Package 3 – Netball and Hockey Pavilion (WORLD pavilion) construction.

Construction Package 4 – Soccer Precinct.

Project Scope

When complete, this project will provide the following regional level sporting facilities:

  • eight court netball precinct with Marshall’s building
  • synthetic hockey pitch with lighting
  • grass hockey pitch with lighting
  • synthetic soccer field with lighting
  • grass soccer field with lighting
  • all associated works including access roads, paths, electrical kiosk, car parking, landscaping, and water metering system
  • two new pavilions to service multiple clubs across the sporting codes

The staged construction has allowed the kindergarten to continue to provide services to the community, and a second Bairnsdale Netball Association season to go ahead. The footprint for the construction of the new soccer fields and soccer pavilion is currently undergoing environmental assessment and Environment Protection and Biodiversity Conservation Act 1999 (EPBC) approvals.



  • 6 June 2024

    Share 6 June 2024 on Facebook Share 6 June 2024 on Twitter Share 6 June 2024 on Linkedin Email 6 June 2024 link

    The WORLD Sporting Precinct caters to a diverse range of sports, promoting unity and inclusion through engaged recreation.

    These modern fit-for-purpose facilities promote inclusivity by accommodating the needs of all participants regardless of gender and ability, ensuring every player feels valued and respected.

    WORLD Pavilion

    The WORLD Pavilion was completed in June 2024, and comprises:

    • four gender neutral change rooms
    • umpires changerooms and amenities
    • first aid room
    • function space that is furnished to accommodate 80 seated patrons
    • a commercial kitchen with two canteens to service east and west sporting fields/ courts
    • toilet facilities
    • disabled access across the building and precinct


    This facility is home to Bairnsdale Netball Association, East Gippsland Hockey Association, Bairnsdale Hockey Club, Nagle Hockey Club, Swan Reach Hockey Club.

    The new WORLD Pavilion is a valuable asset for our community and is available for hire.

    Promoting social interaction, recreation, education, and community engagement across a wide spectrum of activities, these versatile facilities serve various purposes beyond sports. The function space with its commercial kitchen and accommodations for 80 patrons makes it an ideal venue for community events such as fundraisers, social gatherings, meetings, and workshops, fitness classes, art classes, wellness programs and health screenings, hosting volunteer recruitment drives, voting stations during elections, and other community service programs – the possibilities are endless!

    Key inclusions in the precinct are an eight-court precinct with Marshall’s building, a synthetic playing surface with lighting, a turf field, associated access roads, paths, car parking, and landscaping.

    We are grateful for the financial support of the Australian and Victorian Governments, which was invaluable in realising our vision of creating inclusive and accessible recreational spaces for all members of the community.


  • Project Update - 5 March 2024

    Share Project Update - 5 March 2024 on Facebook Share Project Update - 5 March 2024 on Twitter Share Project Update - 5 March 2024 on Linkedin Email Project Update - 5 March 2024 link

    Works at the WORLD are progressing well.

    The power in the pavilion has been turned on, the joinery has been installed, and the internal vinyl work is nearing completion.

    A large external concrete pour around the exterior of the building was completed last week, and the first section of exposed aggregate was poured on Thursday.

    The pavilion is on schedule to be completed by May 2024.

    Additional photos are available in the photos tab:

    Photos - WORLD Sporting Precinct Redevelopment


  • Project Update - 12 February 2024

    Share Project Update - 12 February 2024 on Facebook Share Project Update - 12 February 2024 on Twitter Share Project Update - 12 February 2024 on Linkedin Email Project Update - 12 February 2024 link

    The WORLD pavilion is quickly taking shape, with the following activities already complete:

    • Brickwork
    • Internal rough-in
    • Plastering - complete.
    • External high-level cladding – The cladding will provide enhanced insulation and weather protection.
    • Painting of ceilings
    • Internal lights to be installed this week
    • Storm water drainage
    • Mains power wiring


    Installation of the perforated mesh cladding has commenced.


    The installation of vinyl flooring, wall cladding, and external concreting will be commencing in the next two weeks.






  • Project Update - 17 January 2024

    Share Project Update - 17 January 2024 on Facebook Share Project Update - 17 January 2024 on Twitter Share Project Update - 17 January 2024 on Linkedin Email Project Update - 17 January 2024 link

    The WORLD pavilion is progressing well.

    The pavilion brickwork and internal rough-in are now complete, and plastering inside the pavilion is underway.

    External high-level cladding is underway, which will provide enhanced insulation and weather protection.

  • Project Update - 22 December 2023

    Share Project Update - 22 December 2023 on Facebook Share Project Update - 22 December 2023 on Twitter Share Project Update - 22 December 2023 on Linkedin Email Project Update - 22 December 2023 link

    Soccer

    Council has appointed an architect for the design of the WORLD soccer pavilion and two soccer fields.

    A project reference group (PRG) has been established and are scheduled to meet with the Project Supervisor and architect in February 2024.

    The PRG is a representative section of the most significant community interest groups that will use the new facilities. The group has been assembled on a voluntary basis with the intention of providing a representative viewpoint on the design options and to support and facilitate community involvement in identifying problems and evaluating solutions.


  • Project Update - 10 November 2023

    Share Project Update - 10 November 2023 on Facebook Share Project Update - 10 November 2023 on Twitter Share Project Update - 10 November 2023 on Linkedin Email Project Update - 10 November 2023 link

    The WORLD is aglow

    We have reached a significant milestone, achieving certification on the floodlights across the netball courts and hockey field at the WORLD Sporting Precinct.

    Matches can now be played under lights, extending playing hours, promoting increased physical activity, community engagement, and potentially fostering local sports events during evenings.

    The final lux level testing shows the lighting has achieved industry standards for hockey and netball.

    Well done and thanks to all involved for their work and patience.


  • Project Update - 25 October 2023

    Share Project Update - 25 October 2023 on Facebook Share Project Update - 25 October 2023 on Twitter Share Project Update - 25 October 2023 on Linkedin Email Project Update - 25 October 2023 link

    Council's contractor, Brooker Builders has made great progress at the WORLD with the new pavilion beginning to really take shape.

    The doors and windows have been installed, the brickwork has been completed, and mechanical services are being roughed in.

    The sporting precinct lights have been installed and were tested last week. Further testing is still required to meet the required lux levels prior to issuing of compliance certificate to have the lights available for permanent use.


  • Project Update - 23 October 2023

    Share Project Update - 23 October 2023 on Facebook Share Project Update - 23 October 2023 on Twitter Share Project Update - 23 October 2023 on Linkedin Email Project Update - 23 October 2023 link

    Watch the first netball games here


  • Project update - 25 September 2023

    Share Project update - 25 September 2023 on Facebook Share Project update - 25 September 2023 on Twitter Share Project update - 25 September 2023 on Linkedin Email Project update - 25 September 2023 link


  • Project Update - 14 September 2023

    Share Project Update - 14 September 2023 on Facebook Share Project Update - 14 September 2023 on Twitter Share Project Update - 14 September 2023 on Linkedin Email Project Update - 14 September 2023 link

    All works on the netball courts and carpark are now complete, including the balustrade and placement of the netball post padding.

    The Netball Association are now able to use the courts during daylight hours.

    The power connection to the precinct is progressing and is scheduled for energization early October. The lighting systems will then require adjusting and certification to the required lux levels as per the current sporting standards.

    • Hockey complex – synthetic pitch complete, grass pitch almost complete (further irrigation works will be undertaken once the power connection is complete)
    • Access roads, paths, car parking and landscaping are all complete
    • Pavilion 1 - Netball Marshall building is complete
    • Pavilion 2 - WORLD pavilion is currently under construction (see photos)


Page last updated: 29 Oct 2024, 08:11 PM