Project Update - 12 February 2024

The WORLD pavilion is quickly taking shape, with the following activities already complete:

  • Brickwork
  • Internal rough-in
  • Plastering - complete.
  • External high-level cladding – The cladding will provide enhanced insulation and weather protection.
  • Painting of ceilings
  • Internal lights to be installed this week
  • Storm water drainage
  • Mains power wiring


Installation of the perforated mesh cladding has commenced.


The installation of vinyl flooring, wall cladding, and external concreting will be commencing in the next two weeks.