Bairnsdale - Moroney Street upgrade

Share on Facebook Share on Twitter Share on Linkedin Email this link

About the Project

Council is improving the road and drainage infrastructure in Moroney Street, Bairnsdale.

The overall objective is to upgrade Moroney Street with a consistent seal width, new underground drainage, kerb and channel, footpath installation as required, parking lanes, tree planting and upgrades to all intersections to improve road safety.

This project involves upgrading the whole of Moroney Street and will be completed in three stages.

There is no cost to residents or property owners for this project.

Stage 1 – Dawson Street to McKean Street

Stage 1 completed May 2022

Stage 2 - McKean Street to Birchwood Court

Works are expected to begin in early November 2022 and continue through until July 2023. Cranes Asphalting and Bitumen Pty Ltd have been awarded the tender to undertake these construction works.

Stage 3 – Birchwood Court to Riley Street

Works are expected to begin in late 2023/early 2024 with the current progress at design stage. Council will provide relevant updates through the ‘Your Say’ page as Stage 3 progresses through to Tender and Construction.


From Monday 28 August 2023 the intersection of Moroney Street and Taylor Street, Bairnsdale saw significant changes.

Taylor Street traffic no longer has right of way, with give-way line marking installed for traffic direction.

Moroney Street will have the right of way.

Appropriate signage, including ‘Changed Traffic Conditions’ regulatory signage will be installed in the coming days.

As well as Line Marking and Signage, the Taylor Street intersections approaches have two x flat top road humps installed to pacify motorists’ approach to the intersection (like the McCulloch Street intersection).

These changes were recognised as appropriate measures through a ‘Road Safety Audit’ undertaken during the design of the Moroney Street upgrade (3 Stages).



For updates on the progress of the project please see the News Feed tab below

If you would like to search for other past, current or future projects in your town, simply type your town name in the search bar.

About the Project

Council is improving the road and drainage infrastructure in Moroney Street, Bairnsdale.

The overall objective is to upgrade Moroney Street with a consistent seal width, new underground drainage, kerb and channel, footpath installation as required, parking lanes, tree planting and upgrades to all intersections to improve road safety.

This project involves upgrading the whole of Moroney Street and will be completed in three stages.

There is no cost to residents or property owners for this project.

Stage 1 – Dawson Street to McKean Street

Stage 1 completed May 2022

Stage 2 - McKean Street to Birchwood Court

Works are expected to begin in early November 2022 and continue through until July 2023. Cranes Asphalting and Bitumen Pty Ltd have been awarded the tender to undertake these construction works.

Stage 3 – Birchwood Court to Riley Street

Works are expected to begin in late 2023/early 2024 with the current progress at design stage. Council will provide relevant updates through the ‘Your Say’ page as Stage 3 progresses through to Tender and Construction.


From Monday 28 August 2023 the intersection of Moroney Street and Taylor Street, Bairnsdale saw significant changes.

Taylor Street traffic no longer has right of way, with give-way line marking installed for traffic direction.

Moroney Street will have the right of way.

Appropriate signage, including ‘Changed Traffic Conditions’ regulatory signage will be installed in the coming days.

As well as Line Marking and Signage, the Taylor Street intersections approaches have two x flat top road humps installed to pacify motorists’ approach to the intersection (like the McCulloch Street intersection).

These changes were recognised as appropriate measures through a ‘Road Safety Audit’ undertaken during the design of the Moroney Street upgrade (3 Stages).



For updates on the progress of the project please see the News Feed tab below

If you would like to search for other past, current or future projects in your town, simply type your town name in the search bar.

  • Project Update - 15 February 2024

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Design for Moroney Street 3B (Bredt Street to Riley Street) is nearing completion.

    Once the completed designs have been reviewed by council, tender for construction will be release. Further updates will be provided once the review process has been completed.



    Please feel free to share this update with your local network and choose to follow this project on YourSay to receive important information regarding this project directly to your inbox.

  • Project Update - 3 January 2024

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Moroney Street - stage 3B - the section of Moroney Street between Bredt Street to Riley Street is in the final stage of design and is anticipated to go out for tender shortly.

    Stage 3B includes the following activities:

    • Construction of new kerb and channel
    • Installation of new underground drainage pits and pipes
    • Installation of new footpaths and pram crossings
    • Installation of new line marking and signage
    • Construction of new parking lanes
    • Upgrades to the intersections
    • New road seal and wearing course.
  • Project Update - 21 December 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The contract for construction of Moroney Street stage-3A was awarded at the 28 November Council meeting.

    The contractor Whelans Group Investments Pty Ltd is scheduled to take possession of site on 22 January 2024 to commence site survey and set out.

    We anticipate construction to commence the following week on 29 January 2024.



    East Gippsland Shire Council Meeting - 28 November 2023 (youtube.com)

    2:32:27 Bemm River Footpath development

  • Project Update - 09 November 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Works on stage 2 are almost complete, the tender for stage 3A has now closed and is currently being reviewed by Council.

    Tender documents for stage 3B are near completion and will be tendered shortly.

  • Project Update - 13 October 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Council's contractor, Cranes Civil and Surfacing is currently working on the Morgan Street bus stop intersection. The bus stop hardstand has been demolished; a new bus stop will be installed using the existing bus shelter and a new hardstand poured to meet DDA (Disability Discrimination Act) requirements.

    New roadside kerb has been poured and the nature strips and disturbed areas will be corrected and reseeded with grass.

    The contract to award Stage 3 construction works is scheduled to be presented at the 28 November Council Meeting.

  • Notice of temporary road closure on Friday 25 August 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    TEMPORARY ROAD CLOSURE NOTIFICATION

    FRIDAY 25 August 2023 7:00 AM to 5:00 PM
    Intersection of Moroney Street and Taylor Street, Bairnsdale

    The intersection of Moroney Street and Taylor Street, Bairnsdale, will be closed on Friday 25 August 2023 between the hours of 7.00 am to 5.00 pm, in order to undertake asphalting and line marking works. The contractor has advised property access will be maintained for local residents.

    Visitors to the area are asked to observe the construction site signage and any directions from the contractor including following traffic management direction in the precinct during the works.


  • Project Update - 24 July 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    NOTICE OF TEMPORARY ROAD CLOSURE

    Monday 31 July 2023 through to Friday 4 August 2023, 7:00 AM to 5:00 PM
    Intersection of Moroney Street and Taylor Street, Bairnsdale

    The intersection of Moroney Street and Taylor Street, Bairnsdale will be closed on Monday 31 July 2023 through to Friday 4 August 2023, between the hours of 7.00 am to 5.00 pm, in order to undertake works.

    The road closure will ensure the safety of community and contractors and ensure the work is able to be completed as quickly as possible.

    Please observe the construction signage and any directions from the contractor during the works. Thank you for your patience and understanding while we undertake these necessary works.

    Should you have any queries, please do not hesitate to contact the Project Supervisor on 03 5153 9500.

  • Project Update 1 June 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Moroney Street - Stage 2 - McKean Street to Birchwood Court

    All drainage infrastructure between McKean Street and Taylor Street is complete.

    The contractor is preparing the road surface for sealing works later this week between the McKean Street and Taylor Street intersection. The nature strips in this entire block will then be rehabilitated, and the works will progress beyond Taylor Street to Birchwood Court.

  • Project Update 16/05/2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Moroney Street - Stage 2 is progressing. It is anticipated that the works will continue for the next 6-8 weeks, weather permitting.

    Underground drainage infrastructure is now almost complete with the contractor focusing on construction of kerb and channel.

  • Project Update 18/01/2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Works are progressing well between the McKean Street roundabout and the Taylor Street intersection.

    Drainage works have almost been completed throughout this section with pavement works now underway.

    The contractor has advised they are still on track for completion of Stage 2 by the end of the 2022/23 financial year.

Page last updated: 02 Apr 2024, 10:16 AM