25 May 2021
Contract Awarded - Stage 1
15 June 2022
Construction commenced
06 May 2023
First hockey matches played on the synthetic field
14 July 2023
Hockey light towers installed
05 December 2024
Official opening of stages 1, 2, & 3
21 July 2026
Announcement of works beginning soon