WORLD Sporting Precinct - May 2021 update

A flyover of early construction works at the WORLD Sporting Precinct. Check out our later video to see progress at the site.


Take a bird's-eye look at progress at the WORLD Sporting Precinct site
Take a bird's-eye look at progress at the WORLD Sporting Precinct site
The WORLD Sporting Precinct project Is making great progress - take a look. The WORLD Sporting Project has faced the combined challenges of heavy rain and Covid with its related staffing and materials shortages. Despite these challenges we’re making good progress, with the new carpark south of Westdale Kindergarten being opened for kindergarten use. We’ve commenced site works on the new netball courts and parking area. The hockey pitch work is progressing, with upgrades to the pitch installations (a synthetic surface to one pitch and improved drainage design to the grass pitch) being managed. Pad preparation for the new pavilion is in progress. Our contractors are working hard to complete the pavilion, netball and hockey playing surfaces by the end of 2022, allowing for a summer opening of these facilities. The soccer precinct in the southern section of the site will include two pitches and a pavilion similar to the WORLD pavilion. The area where the field and pavilion will be built is currently undergoing Federal Government environmental approvals under the EPBC Act. Council is awaiting an initial assessment from the department (DAWE), which will clarify timeframes for the broader approvals process.
WORLD Sporting Precinct - May 2021 update
WORLD Sporting Precinct - May 2021 update
A flyover of early construction works at the WORLD Sporting Precinct. Check out our later video to see progress at the site.
Update: new synthetic hockey pitch and progress report on netball courts
Update: new synthetic hockey pitch and progress report on netball courts
Update 7 March 2023: new synthetic hockey pitch and netball courts weeks away from completion.
Saturday 6 May 2023 saw the first hockey matches played on the synthetic field.
Saturday 6 May 2023 saw the first hockey matches played on the synthetic field.
Congratulations to all involved in for helping us reach this significant milestone for the sporting community of East Gippsland! We are sure all players, families and officials were excited to put the field to use.
WORLD construction update - 25 September 2023
WORLD construction update - 25 September 2023
Hockey - completed. Netball - completed.
First netball games played at the WORLD on Thursday 19 October 2023
First netball games played at the WORLD on Thursday 19 October 2023