Project Update - 25 October 2023

Council's contractor, Brooker Builders has made great progress at the WORLD with the new pavilion beginning to really take shape.

The doors and windows have been installed, the brickwork has been completed, and mechanical services are being roughed in.

The sporting precinct lights have been installed and were tested last week. Further testing is still required to meet the required lux levels prior to issuing of compliance certificate to have the lights available for permanent use.