Share ๐
August 2025 on Facebook
Share ๐
August 2025 on Linkedin
Email ๐
August 2025 link
- The northern seawall is nearing completion.
- Construction of the new carpark is underway, helping to improve access and convenience for all visitors.
The new seawall and carpark have been designed in a way that allows flood water to overflow into the carpark during flood related lake level rises and then dissipate more quickly through an improved carpark drainage system. This design approach aims to ensure that upgrade works donโt transfer flooding from the public carpark into surrounding areas such as roads & private property.
The new seawall doesn't impact McMillan Strait flows as it is located outside the main channel and tidal flows. The revised documents are available in the documents section on this page:
Behind the scenes, the redesigned boat ramp is being prefabricated, and work on the floating pontoon jetties are progressing well. These upgrades will make launching and docking safer and easier for everyone.
On the ground, crews are busy installing service conduits, kerbing, and drainage, laying the foundation for a more functional and welcoming space.
Share ๐
July 2025 on Facebook
Share ๐
July 2025 on Linkedin
Email ๐
July 2025 link
MEDIA RELEASE
Paynesvilleโs Slip Road Maritime Precinct is taking shape, with East Gippsland Shire Council confirming the next phase of construction to improve car parking and drainage at the site.
The Slip Road Maritime Precinct project was initiated in response to strong demand for additional berthing in Paynesville and across the Gippsland Lakes โ one of Australiaโs premier boating destinations. While the precinct supports recreational users, it also plays a critical role in servicing the local marine industry, a key economic driver for East Gippsland.
Visitors to the precinct can already see progress underway, including a concrete panel seawall that now protects the foreshore and sets the footprint for the new facilities.
At its meeting on Tuesday night, Council approved a variation to the existing construction contract with Carter Marine Group. This variation enables the delivery of critical works, including the redesigned car park, kerb and channel, underground drainage, infrastructure, pathways and service connections.
These upgrades follow extensive engineering advice and geotechnical investigations, ensuring the new infrastructure is built to withstand coastal conditions and reduce the impact of flooding.
read more...
Share ๐
May 2025 on Facebook
Share ๐
May 2025 on Linkedin
Email ๐
May 2025 link
Things are moving along well, and weโre hitting some great milestones.
- Northern seawall panels: Pre-fabrication is approx. 75% complete, a major step forward in strengthening our coastal resilience.
- Service jetty: Pile driving is around 70% complete, with beams and deck prefabrication underway.
- Floating pontoon jetties: Design and general layout were endorsed by the CFA, and pre-fabrication commenced.
- We've completed 120m of Boardwalk and only have around 30m to go!
We appreciate the communityโs continued support and patience as we work to deliver a safer, more accessible, and future-ready waterfront.
Share 9 December 2024 on Facebook
Share 9 December 2024 on Linkedin
Email 9 December 2024 link
The front section of southern seawall is now complete.
Share 14 November 2024 on Facebook
Share 14 November 2024 on Linkedin
Email 14 November 2024 link
We are pleased to report significant progress on the maritime precinct upgrade:
- Southern Slip Road Seawall: Installation of concrete panels has now commenced for the southern section of the seawall.
- Northern Slip Road Seawall: Pile driving activities will continue over the coming months for the northern section. Following completion of this work, concrete panels will be installed.
- Floating Pontoons: The design phase for the floating pontoons is nearing completion, and we anticipate offsite prefabrication starting in February 2025.
- Boat Ramp & Service Jetty: Construction is scheduled to begin in March 2025.
We will continue to monitor progress and provide updates as Carter Marine progresses work on these key components.
We welcome your continued interest in this project. Please feel free to share this update with your local network and choose to follow this project on YourSay to receive important information regarding this project directly to your inbox.
Share 16 September 2024 on Facebook
Share 16 September 2024 on Linkedin
Email 16 September 2024 link
Further updates will be provided on YourSay following the Council Election on 26 October 2024, and the questions/feedback tab will be reinstated.
From 12.00 noon Tuesday 17 September until 6.00 pm on Saturday 26 October (Election Day) we will be in the Local Government Election Period (also known as Caretaker Period).
During this time, we will limit our printed communications, website content, social media activity, and community consultations. The ability for people to comment on our social media content will also be disabled during the Election Period.
Each of these steps is to ensure our content does not affect voting in the election and is consistent with steps taken by other Victorian Councils and the Local Government Act 2020.
These changes are only temporary; we'll be back to normal communication activity after the election.
Share 12 September 2024 on Facebook
Share 12 September 2024 on Linkedin
Email 12 September 2024 link
- Using the barge, piles are installed ready for splicing/welding.
- A third-party contractor is conducting tests on the driven piles to ensure they have reached the necessary refusal strength. This process allows us to quickly evaluate key factors such as the pileโs load-bearing capacity, the stress on the steel, the overall integrity of the pile, and the effectiveness of the pile driving process.
- Once the piles have successfully passed these tests, we will move forward with installing the seawall panels.
- Carter Marine are anticipated to complete the seawall, jetties, and all associated works by December 2025.
The carpark design is in the concept stage and will progress to the preliminary stage over the coming month. The preliminary design will be made available on YourSay following the Council Election period.
Share 14 August 2024 on Facebook
Share 14 August 2024 on Linkedin
Email 14 August 2024 link
Carter Marine is progressing well.
The pile driving is well underway and is anticipated to continue over the coming months.
Coming up.... carpark design.
A consultant has been engaged to design the upgrade of the carpark, enhancing usability for all while protecting the natural environment of the precinct. The consultant will undertake investigations in the carpark area, which are scheduled to commence in the coming weeks. Outcomes of the investigations will provide insight on the existing pavement conditions within the proposed carpark location and inform the development of the carpark concept design.
A project reference group (PRG) will help progress the development of the carpark concept design; successful PRG applicants will soon be notified by our Project Engineer.
Assembled on a voluntary basis, the PRG includes representation of Slip Road businesses and regular users of the area. The PRG members will support and co-operate with all parties and inform the consultant of their needs and use of the area.
The first PRG meeting will be scheduled to occur after the 2024 council caretaker period (17 September 2024 to 26 October 2024) and all pavement investigations have been completed.
Additional photos are available in the photos tab: Slip Road Maritime Precinct - Photos
Further project updates will be provided following the 2024 council caretaker period (17 September 2024 to 26 October 2024). In the meantime, we encourage your continued interest in this project and other projects available on YourSay. Please choose to follow projects on YourSay to receive important information directly to your inbox.
Share 17 July 2024 on Facebook
Share 17 July 2024 on Linkedin
Email 17 July 2024 link
Despite the poor weather, works at Slip Road continue to progress. Our contractor, Carter Marine have completed fabrication of the concrete seawall panels and are now in the process of driving extra piles to increase the horizontal stability of the seawall.

Share 28 May 2024 on Facebook
Share 28 May 2024 on Linkedin
Email 28 May 2024 link
Representatives from our funding partners, the Department of Jobs, Skills, Industry, and Regions, visited the site on Friday 24 May 2024 to check on the progress.
Our officers shared insights on the design and layout, giving them a firsthand look at the project. They saw several of the 57 new seawall panels already poured, galvanised piles ready for installation, and the general layout of the site.
We're pleased to have their continued interest and support in this shared project. A big thank you to our contractor, Carter Marine Group, for their hard work and dedication in bringing the Slip Road Maritime Precinct project to life - their expertise and commitment has been invaluable in making this project a success.
The next steps -
- Panels to be installed between piles to form seawall
- Backfill behind seawall in preparation for new carpark
- Prefabrication of pontoons and service jetty to happen offsite
PHOTO [from left to right]: Renee Wicks โ Manager Infrastructure Projects East Gippsland Shire Council; Shayna Millar - Visitor Economy Project Delivery Coordinator - Department of Jobs, Skills, Industry and Regions; Sean Heinemann โ Project Supervisor East Gippsland Shire Council; Katrina Cranwell - Department of Jobs, Skills, Industry and Regions; Nick George โ Carter Marine Group โ Principal Contractor; Johan Janse Van Rensburg โ Project Engineer East Gippsland Shire Council.