Slip Road Marina Precinct Upgrade is progressing and due for completion June 2026.

What’s happening now:

  • Marina Jetty 2 is nearing completion
  • Jetty number 3 is in the prefabrication stage.
  • Boat ramp prefabrication complete and ready for installation.
  • Service Jetty prefabrication nearing completion and expected to be installed in a couple of months.
  • Fire and potable water design complete and ready for construction in the next 2 months.
  • Hydro seeding of southern section complete, with regular watering happening to ensure maximum seed strike.

What’s happening next:

  • Underground services installation is expected to be completed in January.
  • Boat ramp and jetty installations.
  • Kerbing, landscaping, and carpark asphalting will be completed once the above works have been completed.