Slip Road Marina Precinct Upgrade is progressing and due for completion June 2026.
Whatβs happening now:
- Marina Jetty 2 is nearing completion
- Jetty number 3 is in the prefabrication stage.
- Boat ramp prefabrication complete and ready for installation.
- Service Jetty prefabrication nearing completion and expected to be installed in a couple of months.
- Fire and potable water design complete and ready for construction in the next 2 months.
- Hydro seeding of southern section complete, with regular watering happening to ensure maximum seed strike.
Whatβs happening next:
- Underground services installation is expected to be completed in January.
- Boat ramp and jetty installations.
- Kerbing, landscaping, and carpark asphalting will be completed once the above works have been completed.
Share π
January 2026 on Facebook
Share π
January 2026 on Twitter
Share π
January 2026 on Linkedin
Email π
January 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends