Things are moving along well, and weโ€™re hitting some great milestones.

  • Northern seawall panels: Pre-fabrication is approx. 75% complete, a major step forward in strengthening our coastal resilience.
  • Service jetty: Pile driving is around 70% complete, with beams and deck prefabrication underway.
  • Floating pontoon jetties: Design and general layout were endorsed by the CFA, and pre-fabrication commenced.
  • We've completed 120m of Boardwalk and only have around 30m to go!


We appreciate the communityโ€™s continued support and patience as we work to deliver a safer, more accessible, and future-ready waterfront.