Bairnsdale - Moroney Street upgrade

Share Bairnsdale - Moroney Street upgrade on Facebook Share Bairnsdale - Moroney Street upgrade on Twitter Share Bairnsdale - Moroney Street upgrade on Linkedin Email Bairnsdale - Moroney Street upgrade link

About the Project

Council is improving the road and drainage infrastructure in Moroney Street, Bairnsdale.

The overall objective is to upgrade Moroney Street with a consistent seal width, new underground drainage, kerb and channel, footpath installation as required, parking lanes, tree planting and upgrades to all intersections to improve road safety.

This project involves upgrading the whole of Moroney Street and will be completed in three stages.

There is no cost to residents or property owners for this project.

Stage 1 – Dawson Street to McKean Street

Stage 1 completed May 2022

Stage 2 - McKean Street to Birchwood Court

Works are expected to begin in early November 2022 and continue through until July 2023. Cranes Asphalting and Bitumen Pty Ltd have been awarded the tender to undertake these construction works.

Stage 3 – Birchwood Court to Riley Street

Works are expected to begin in late 2023/early 2024 with the current progress at design stage. Council will provide relevant updates through the ‘Your Say’ page as Stage 3 progresses through to Tender and Construction.


From Monday 28 August 2023 the intersection of Moroney Street and Taylor Street, Bairnsdale saw significant changes.

Taylor Street traffic no longer has right of way, with give-way line marking installed for traffic direction.

Moroney Street will have the right of way.

Appropriate signage, including ‘Changed Traffic Conditions’ regulatory signage will be installed in the coming days.

As well as Line Marking and Signage, the Taylor Street intersections approaches have two x flat top road humps installed to pacify motorists’ approach to the intersection (like the McCulloch Street intersection).

These changes were recognised as appropriate measures through a ‘Road Safety Audit’ undertaken during the design of the Moroney Street upgrade (3 Stages).



For updates on the progress of the project please see the News Feed tab below

If you would like to search for other past, current or future projects in your town, simply type your town name in the search bar.

About the Project

Council is improving the road and drainage infrastructure in Moroney Street, Bairnsdale.

The overall objective is to upgrade Moroney Street with a consistent seal width, new underground drainage, kerb and channel, footpath installation as required, parking lanes, tree planting and upgrades to all intersections to improve road safety.

This project involves upgrading the whole of Moroney Street and will be completed in three stages.

There is no cost to residents or property owners for this project.

Stage 1 – Dawson Street to McKean Street

Stage 1 completed May 2022

Stage 2 - McKean Street to Birchwood Court

Works are expected to begin in early November 2022 and continue through until July 2023. Cranes Asphalting and Bitumen Pty Ltd have been awarded the tender to undertake these construction works.

Stage 3 – Birchwood Court to Riley Street

Works are expected to begin in late 2023/early 2024 with the current progress at design stage. Council will provide relevant updates through the ‘Your Say’ page as Stage 3 progresses through to Tender and Construction.


From Monday 28 August 2023 the intersection of Moroney Street and Taylor Street, Bairnsdale saw significant changes.

Taylor Street traffic no longer has right of way, with give-way line marking installed for traffic direction.

Moroney Street will have the right of way.

Appropriate signage, including ‘Changed Traffic Conditions’ regulatory signage will be installed in the coming days.

As well as Line Marking and Signage, the Taylor Street intersections approaches have two x flat top road humps installed to pacify motorists’ approach to the intersection (like the McCulloch Street intersection).

These changes were recognised as appropriate measures through a ‘Road Safety Audit’ undertaken during the design of the Moroney Street upgrade (3 Stages).



For updates on the progress of the project please see the News Feed tab below

If you would like to search for other past, current or future projects in your town, simply type your town name in the search bar.

  • Project Update 18/01/2023

    Share Project Update 18/01/2023 on Facebook Share Project Update 18/01/2023 on Twitter Share Project Update 18/01/2023 on Linkedin Email Project Update 18/01/2023 link
    supporting image

    Works are progressing well between the McKean Street roundabout and the Taylor Street intersection.

    Drainage works have almost been completed throughout this section with pavement works now underway.

    The contractor has advised they are still on track for completion of Stage 2 by the end of the 2022/23 financial year.

  • Project Update 14/12/2022

    Share Project Update 14/12/2022 on Facebook Share Project Update 14/12/2022 on Twitter Share Project Update 14/12/2022 on Linkedin Email Project Update 14/12/2022 link
    supporting image

    Works are progressing on the drainage infrastructure between McKean Street roundabout and the Taylor Street intersection.

    Cranes Asphalting and Bitumen Pty Ltd have been awarded the tender to undertake these construction works. Works are expected to continue through until July 2023.

  • Project Update 10/11/2022 - Stage 2

    Share Project Update 10/11/2022 - Stage 2 on Facebook Share Project Update 10/11/2022 - Stage 2 on Twitter Share Project Update 10/11/2022 - Stage 2 on Linkedin Email Project Update 10/11/2022 - Stage 2 link

    Contractor Cranes Asphalting have mobilised some equipment to site and will look to undertake a ‘letter drop’ to residents in the neighbourhood in the coming days.

    They are still on track to commence works next week, through until the end of June 2023.