The contract for construction of Moroney Street stage-3A was awarded at the 28 November Council meeting.

The contractor Whelans Group Investments Pty Ltd is scheduled to take possession of site on 22 January 2024 to commence site survey and set out.

We anticipate construction to commence the following week on 29 January 2024.