The construction contract was awarded to GBM Contractors Pty Ltd.
Construction is scheduled to commence after the Easter break and is anticipated to be completed by the end of June 2026, weather and site conditions permitting.
What’s happening?
The project will deliver upgraded recreation infrastructure at the Marlo Foreshore, improving accessibility, safety and comfort at this popular fishing and community destination.
Works include:
- Replacement of the existing barbeque and shelter.
- New picnic tables and bench seating.
- Construction of accessible (DDA‑compliant) footpaths.
- Upgraded parking, including accessible parking and shared areas.
- New supporting infrastructure, such as bins and bicycle stands.
What to expect during construction
- Access to the boat ramp will be maintained throughout construction.
- Minimal disruption is expected during works.
- Traffic management will be in place to ensure public and worker safety.
Thank you for your patience while these improvements are delivered.
We look forward to providing enhanced foreshore facilities for locals and visitors to enjoy.
Further updates will be shared on this page as works progress. Subscribe to receive project updates directly to your inbox.

Share 📅 August 2025 on Facebook
Share 📅 August 2025 on Linkedin
Email 📅 August 2025 link
Completed elements:
- Toilet block completed in Stage-1.
Stage-2 scope:
Formalised parking and road upgrades along Foreshore Road have been excluded from the scope. This decision reflects community feedback, which expressed a strong preference for the area to retain its natural and underdeveloped character.
Angling Club area:
- Shelter
- BBQ and 2 accessible picnic tables
- Rubbish bin
- Accessible footpaths
Lyre Bird turn around:
- Bike rack
- Accessible picnic table
- Rubbish bin.
Stage-2 design:
🏅 Design contract awarded to Chris Obrien.
Detailed design progressing.
Timeline:
Design: completion anticipated end of October 2025
Tender: November 2025 to 3 December 2025
Delivery: 2026
Share Project Update - 05 December 2023 on Facebook
Share Project Update - 05 December 2023 on Linkedin
Email Project Update - 05 December 2023 link
Check out the new Proposed Works Document to find out the interesting things happening behind the scenes with this project.
Proposed Works Document
Share Project Update - 9 August 2023 on Facebook
Share Project Update - 9 August 2023 on Linkedin
Email Project Update - 9 August 2023 link
The Erosion Assessment Report has been completed.
Council will use the results of the Erosion Assessment Report and the Marlo Drainage Assessment to prioritise works to reduce the erosion caused by drainage issues on the Marlo foreshore, and to ease drainage concerns within Marlo.
Initial site visits and consultation with local community groups has informed the development of the Preliminary Masterplan, which contains proposed actions for improvements.
The feature and level survey has been completed for the boat ramp area along Beach Road and also some of the trails within the foreshore area. The survey results will inform the development of concept plans, which will be made available to the public once completed.
Share Project Update 4/04/2023 on Facebook
Share Project Update 4/04/2023 on Linkedin
Email Project Update 4/04/2023 link
The Marlo Foreshore management plan implementation project is progressing well.
EGSC have engaged Water Technology to complete an erosion assessment along the foreshore. This is also considering the findings from the Marlo Drainage assessment which is being finalised by Water Technology. Water Technology will provide options for remediation works along the foreshore within the final report and this will support the prioritisation and further development of the project .
The toilet block design has been finalised (see attached document for final layout). Construction of the toilet block will not commence until after June 2023.