Completed elements:

  • Toilet block completed in Stage-1.

Stage-2 scope:

Formalised parking and road upgrades along Foreshore Road have been excluded from the scope. This decision reflects community feedback, which expressed a strong preference for the area to retain its natural and underdeveloped character.

Angling Club area:

  • Shelter
  • BBQ and 2 accessible picnic tables
  • Rubbish bin
  • Accessible footpaths

Lyre Bird turn around:

  • Bike rack
  • Accessible picnic table
  • Rubbish bin.

Stage-2 design:

🏅 Design contract awarded to Chris Obrien.

Detailed design progressing.

Timeline:

Design: completion anticipated end of October 2025

Tender: November 2025

Delivery: 2026