Share March 2025 on Facebook
Share March 2025 on Linkedin
Email March 2025 link
Check out the new flooring in the office and meeting room!
Share 20 December 2024 on Facebook
Share 20 December 2024 on Linkedin
Email 20 December 2024 link
Share 7 August 2024 on Facebook
Share 7 August 2024 on Linkedin
Email 7 August 2024 link
We are excited to share that significant progress has been made on the Pavilion renovation project - here's an update!
Internal Plastering: The plastering work inside the Mudbrick Pavilion has been successfully completed. The new walls are now ready for the next stages of finishing.
Lighting: The installation of the new lighting system has been finalised, enhancing the facility's ambiance and functionality.
Sound Booth Wall: The wall for the sound booth in the theatre is complete. We consulted with a sound engineer from the Forge in Bairnsdale to ensure the design meets our acoustic needs and provides the best possible sound experience.
What's next? All remaining components for the project are now on hand, and we are in the process of scheduling their installation over the coming weeks.
We are working diligently to complete the renovations and are enthusiastic about the improvements that will benefit everyone in the community. Our goal is to hand over the upgraded Mudbrick Pavilion to the Mallacoota Recreation Reserve and Halls Committee of Management by the end of August 2024.
Thank you for your continued support and patience. We look forward to unveiling the enhanced Mudbrick Pavilion and celebrating its new features with you soon!
Share Project Update - 13 February 2024 on Facebook
Share Project Update - 13 February 2024 on Linkedin
Email Project Update - 13 February 2024 link
The Stage-1 upgrades to the kitchen are now complete.
Works to upgrade the toilets and the workshop store have commenced.
 |
 |
Kitchen installation, late 2023 |
Share Project Update - 18 August 2023 on Facebook
Share Project Update - 18 August 2023 on Linkedin
Email Project Update - 18 August 2023 link
Upgrades to the Mallacoota Mudbrick Pavilion have commenced.
The kitchen is undergoing a transformation, with new equipment and cabinetry being installed and designed in a way to retain the original character of the building. Much of the building upgrade works are being completed by Council teams to meet budget requirements and project deadlines.
Any required closures will be limited to minimise interruption to the operation schedule of the pavilion and will be advised in advance.
Share Project Update 6/04/2023 on Facebook
Share Project Update 6/04/2023 on Linkedin
Email Project Update 6/04/2023 link
Design drawings were received last week.
We are currently waiting for the engineering design for the removal of structural elements.
Due to delays with design documents the project is likely to begin in the 2023/24 financial year.
Share Project Update 28/02/2023 on Facebook
Share Project Update 28/02/2023 on Linkedin
Email Project Update 28/02/2023 link
The detailed design of the kitchen is complete.
Construction is planned to commence in mid 2023 under the supervision of the EGSC building crew.