With significant progress made over recent months, the Mudbrick Pavilion building works are nearing completion.
- Vinyl Plank Flooring: Installation is now complete.
- Stage Refurbishment: The stage has been successfully refurbished, adding to the versatility of the venue.
- Cleaners Mop Basin: To be installed early 2025
- Studio/workshop: This will be prefabricated off-site and delivered in the New Year.
These updates mark a significant step forward for the Mudbrick Pavilion, ensuring the pavilion is available during the holiday break to accommodate existing bookings whilst maintaining its community-focused goals.
The revised project completion date is set for the end of March 2025.