Lakes Entrance - Marine Parade Upgrade

Share Lakes Entrance - Marine Parade Upgrade on Facebook Share Lakes Entrance - Marine Parade Upgrade on Twitter Share Lakes Entrance - Marine Parade Upgrade on Linkedin Email Lakes Entrance - Marine Parade Upgrade link

About the Project

Council secured funding through the Australian government for the upgrade and redevelopment of Marine Parade in Lakes Entrance. The project area extends from the entry roundabout at Marine Parade and the Princes Highway along to the Barkes Avenue intersection. The project aims to achieve traffic calming measures, improve pedestrian safety and improve on-road parking safety.

The type of works being undertaken will include:

  • Installation of pedestrian crossings and footpaths
  • Installation of raised asphalt platforms at key locations to control traffic speed
  • Road widening in multiple locations to allow for indented on-road parking
  • The reconstruction of the intersection at Barkes Avenue and Marine Parade

Although the concept design stage has considered the interaction between foreshore and road use, committed funding to the project ($1.2 M) from the Australian Government and Council allows for the construction within the footprint of the road reserve and exclude off-road parking and the foreshore area. Council will continue to advocate for funding for further construction stages as opportunities arise in coming years.

Community Engagement

Community consultation in October and November 2022 led to the development of the concept plan. Thank you to everyone who took the time to provide feedback on the concept plan. All feedback is important and was considered.

Changes to the design included:

  • New raised pedestrian crossings
  • New parallel parking bays
  • New 1.8 metre footpaths along the residential side

Project Reference Group

A Project Reference Group (PRG) was established to help guide this project moving forward. The group was assembled on a voluntary basis with the intention to support and co-operate with all parties in the spirit of goodwill and working towards the common purpose. The PRG will provide a representative viewpoint on the design options and will be included in communications of detailed design. Reference Group members will contribute their knowledge about issues that are relevant to the project and provide representation for a variety of stakeholder interests.

Specifically, the PRG will:

  • Provide input, advice, and recommendations to the Project Control Group;
  • Review and comment on draft project documents;
  • Ensure that the views and interests of their organisation/interest group and the community are represented, and that relevant stakeholders are engaged;
  • Provide an active and positive contribution to the project;
  • Champion the project within the community;
  • Help achieve community participation;

Funding

Funding for this project is provided by the Department of Infrastructure, Transport, Regional Development, Communications and the Arts through the Victorian Infrastructure Investment Program, and East Gippsland Shire Council.



Project updates will be provided on this page in the tab below.

Should you wish to search for other projects in your town, simply type the town name in the search bar.

About the Project

Council secured funding through the Australian government for the upgrade and redevelopment of Marine Parade in Lakes Entrance. The project area extends from the entry roundabout at Marine Parade and the Princes Highway along to the Barkes Avenue intersection. The project aims to achieve traffic calming measures, improve pedestrian safety and improve on-road parking safety.

The type of works being undertaken will include:

  • Installation of pedestrian crossings and footpaths
  • Installation of raised asphalt platforms at key locations to control traffic speed
  • Road widening in multiple locations to allow for indented on-road parking
  • The reconstruction of the intersection at Barkes Avenue and Marine Parade

Although the concept design stage has considered the interaction between foreshore and road use, committed funding to the project ($1.2 M) from the Australian Government and Council allows for the construction within the footprint of the road reserve and exclude off-road parking and the foreshore area. Council will continue to advocate for funding for further construction stages as opportunities arise in coming years.

Community Engagement

Community consultation in October and November 2022 led to the development of the concept plan. Thank you to everyone who took the time to provide feedback on the concept plan. All feedback is important and was considered.

Changes to the design included:

  • New raised pedestrian crossings
  • New parallel parking bays
  • New 1.8 metre footpaths along the residential side

Project Reference Group

A Project Reference Group (PRG) was established to help guide this project moving forward. The group was assembled on a voluntary basis with the intention to support and co-operate with all parties in the spirit of goodwill and working towards the common purpose. The PRG will provide a representative viewpoint on the design options and will be included in communications of detailed design. Reference Group members will contribute their knowledge about issues that are relevant to the project and provide representation for a variety of stakeholder interests.

Specifically, the PRG will:

  • Provide input, advice, and recommendations to the Project Control Group;
  • Review and comment on draft project documents;
  • Ensure that the views and interests of their organisation/interest group and the community are represented, and that relevant stakeholders are engaged;
  • Provide an active and positive contribution to the project;
  • Champion the project within the community;
  • Help achieve community participation;

Funding

Funding for this project is provided by the Department of Infrastructure, Transport, Regional Development, Communications and the Arts through the Victorian Infrastructure Investment Program, and East Gippsland Shire Council.



Project updates will be provided on this page in the tab below.

Should you wish to search for other projects in your town, simply type the town name in the search bar.

  • 16 September 2024

    Share 16 September 2024 on Facebook Share 16 September 2024 on Twitter Share 16 September 2024 on Linkedin Email 16 September 2024 link

    Further updates will be provided on YourSay following the Council Election on 26 October 2024, and the questions/feedback tab will be reinstated.

    From 12.00 noon Tuesday 17 September until 6.00 pm on Saturday 26 October (Election Day) we will be in the Local Government Election Period (also known as Caretaker Period).

    During this time, we will limit our printed communications, website content, social media activity, and community consultations. The ability for people to comment on our social media content will also be disabled during the Election Period.

    Each of these steps is to ensure our content does not affect voting in the election and is consistent with steps taken by other Victorian Councils and the Local Government Act 2020.

    These changes are only temporary; we'll be back to normal communication activity after the election.

  • 3 September 2024

    Share 3 September 2024 on Facebook Share 3 September 2024 on Twitter Share 3 September 2024 on Linkedin Email 3 September 2024 link

    TEMPORARY BOAT RAMP CLOSURE


    War Memorial boat ramp & carpark

    Friday 6 September 2024 to Friday 29 November 2024

    while we carry out improvements to Marine Parade.


    Alternative boat ramps are to the west at -

    North Arm Boat Ramp (next to Apex Park playground)

    Skate Park Boat Ramp.



    The closure of the boat ramp will ensure we complete the work as quickly as possible.

    Alternative boat ramps are North Arm Boat Ramp (next to Apex Park playground) and the Skate Park Boat Ramp.

    Visitors to the area are asked to observe the construction signage and all directions from the contractor during the works.

  • 26 August 2024

    Share 26 August 2024 on Facebook Share 26 August 2024 on Twitter Share 26 August 2024 on Linkedin Email 26 August 2024 link

    Our contractor, Cranes Asphalting and Bitumen Sealing, has made visible headway into the construction of the car parking along the north side of Marine Parade, which will provide an anticipated total of 50 formalised parking spaces when completed.

    In addition to the current project scope, improvements will be made to the intersection of Marine Parade and Carstairs Avenue to significantly reduce localised flooding in the area.

    There were some delays due to design issues and wet weather, however, Cranes is diligently working to complete the project before the busy Christmas holiday season.



    Additional photos are available in the photos tab: Lakes Entrance Marine Parade Upgrade - Photos

    We welcome your continued interest in this project. Please choose to follow this project on YourSay to receive important information directly to your inbox.

  • 29 July 2024

    Share 29 July 2024 on Facebook Share 29 July 2024 on Twitter Share 29 July 2024 on Linkedin Email 29 July 2024 link

    Construction works on Marine Parade commenced on 24 June 2024, as planned.

    Our contractors, Cranes Asphalting and Bitumen Sealing have since made significant progress and you can already see the carparking bays taking shape.

    Drainage infrastructure works have also commenced at the main boat ramp carpark and the Laura Street intersection.

    The wet weather has caused some minor delays; however, the Cranes' crew continues to work between weather events when possible.

    Works have been staged to minimise disruptions, and road safety measures have been implemented including signage, traffic lights, and fencing.

    Please follow all directions from our contractor during this time, to ensure safety for all.


    We welcome your continued interest in this project. Please choose to follow this project on YourSay to receive important information directly to your inbox.



  • Marine Parade upgrades set to commence!

    Share Marine Parade upgrades set to commence! on Facebook Share Marine Parade upgrades set to commence! on Twitter Share Marine Parade upgrades set to commence! on Linkedin Email Marine Parade upgrades set to commence! link

    🚧 NOTIFICATION OF ROADWORKS 🚧

    We're excited to announce the Marine Parade upgrades are set to commence!

    Our Contractors, Cranes Asphalting and Bitumen Sealing P/L, anticipate starting on Monday 24 June 2024, with completion expected within 6 months, weather permitting. Their team is committed to minimising inconvenience and ensuring access to properties throughout the project.

    Due to the size of the project, the works will be staged and will commence eastwards from Laura Street.

    Your patience and cooperation are greatly appreciated as we work together to improve our community's infrastructure! Stay tuned for updates and thank you for your understanding.

    As we strive to enhance safety and accessibility, please note:

    • delays are expected.
    • there may be variations in access during construction.
    • temporary parking restrictions may apply along some sections.
    • remediation work will be undertaken as needed to minimise disruptions.


    This project includes:

    • additional carparking
    • new accessible footpaths
    • road infrastructure upgrades
    • raised pedestrian crossings
    • enhanced safety and overall appeal of the surroundings
  • 9 May 2024

    Share 9 May 2024 on Facebook Share 9 May 2024 on Twitter Share 9 May 2024 on Linkedin Email 9 May 2024 link

    The contract for construction was awarded to Cranes Asphalting and Bitumen Sealing Pty Ltd (Cranes) at the 30 April 2024 Council meeting.

    Programming for construction will be advised when available - we look forward to working again with Cranes.

    This project includes a range of infrastructure upgrades aimed at improving both functionality and aesthetics, including widening of the road, the implementation of car parking solutions, and the integration of road calming measures to ensure smoother traffic operations.

    Footpath upgrades and the installation of raised pedestrian crossings are prioritised not only for safety but also to enhance the overall appeal of the surroundings.

    Additional measures include improved safety protocols at intersections, upgraded drainage infrastructure for efficient flood management, and the formalisation of boat trailer parking areas.

  • Contract for construction awarded

    Share Contract for construction awarded on Facebook Share Contract for construction awarded on Twitter Share Contract for construction awarded on Linkedin Email Contract for construction awarded link

    The contract for construction was awarded to Cranes Asphalting and Bitumen Sealing Pty Ltd at the 30 April 2024 Council meeting.

    Commencement of construction will be advised once the programming has been established. We look forward to working with Cranes on this project.


    We welcome your continued interest in this project. Please choose to follow this project on YourSay to receive important information regarding this project directly to your inbox.

  • Project Update - 10 January 2024

    Share Project Update - 10 January 2024 on Facebook Share Project Update - 10 January 2024 on Twitter Share Project Update - 10 January 2024 on Linkedin Email Project Update - 10 January 2024 link

    Tender for construction will be released soon.

    Tender documentation will be available at - Tenders (eastgippsland.vic.gov.au)


  • Project Update - 21 November 2023

    Share Project Update - 21 November 2023 on Facebook Share Project Update - 21 November 2023 on Twitter Share Project Update - 21 November 2023 on Linkedin Email Project Update - 21 November 2023 link

    We are pleased to announce that we have secured $1.2 million to complete the proposed road safety improvements for Marine Parade, Lakes Entrance. Thanks to the successful outcome of the Government's review, this project will now proceed to tender stage.

    The project area extends from the entry roundabout at Princes Highway, along Marine Parade to the Barkes Avenue intersection, and will include traffic calming measures to improve pedestrian safety and on-road parking.

    Works are scheduled to be completed during 2024. This is a great outcome for our community.

    In addition to this positive outcome, Council was advised of increased funding through the Roads to Recovery and Black Spot Funding programs.

  • Project Update - 12 July 2023

    Share Project Update - 12 July 2023 on Facebook Share Project Update - 12 July 2023 on Twitter Share Project Update - 12 July 2023 on Linkedin Email Project Update - 12 July 2023 link

    Detailed design is progressing well.

    The Project Reference Group has now been confirmed with the first meeting scheduled for Tuesday 25 July 2023.

    Thank you to all of the people who expressed their interest in joining the PRG and taking the time to submit their application. The PRG contains a limited number of spots and not all of the applicants were chosen due to the high level of interest. In the meantime, we encourage your continued interest in this project and welcome your participation in community consultation and engagement scheduled throughout the delivery of this project. Dates and times will be advised on YourSay, when available. Thank you for your understanding, and we extend our best wishes for your continued engagement in this project.

Page last updated: 17 Sep 2024, 10:34 AM