Share Bairnsdale Airport - Rehabilitation of Taxiway and Hangar Apron on Facebook Share Bairnsdale Airport - Rehabilitation of Taxiway and Hangar Apron on Twitter Share Bairnsdale Airport - Rehabilitation of Taxiway and Hangar Apron on Linkedin Email Bairnsdale Airport - Rehabilitation of Taxiway and Hangar Apron link

Council has commenced planning for the rehabilitation of the Bairnsdale airport taxiway and hangar apron.

Extensive pavement improvement work is required on the large apron in front of the hangar precinct and taxiway C. The airport apron is the area where the aircraft are parked, unloaded or loaded, refuelled, boarded, or maintained. This apron is not open to the public. The improvement work can no longer be completed in the scheduled maintenance program.

The proposed works will improve the safety of aircraft, operators and passengers, the delivery of goods and services and better meet the operational requirements of aeromedical and other emergency services.

Objective and scope:

This project is to rehabilitate the apron and taxiway. The design work will include -

  • site investigations
  • drainage investigations
  • survey, and
  • detailed design of a compliant apron and taxiway

Consultation and community engagement

Monthly project updates will be published in the tab below.



To read more about the Bairnsdale Airport, click on one of the links below -

Bairnsdale Airport - Runway Extension and Lighting Upgrade

Bairnsdale Airport - Air Ambulance Transfer Facility

Bairnsdale Airport (eastgippsland.vic.gov.au)



Please click on the Project Updates tab below to follow the progress of this project. Information will be updated regularly as it becomes available, if you would like to stay up to date, please subscribe.

Should you wish to search for other projects in your town, simply type the town name in the search bar.


Council has commenced planning for the rehabilitation of the Bairnsdale airport taxiway and hangar apron.

Extensive pavement improvement work is required on the large apron in front of the hangar precinct and taxiway C. The airport apron is the area where the aircraft are parked, unloaded or loaded, refuelled, boarded, or maintained. This apron is not open to the public. The improvement work can no longer be completed in the scheduled maintenance program.

The proposed works will improve the safety of aircraft, operators and passengers, the delivery of goods and services and better meet the operational requirements of aeromedical and other emergency services.

Objective and scope:

This project is to rehabilitate the apron and taxiway. The design work will include -

  • site investigations
  • drainage investigations
  • survey, and
  • detailed design of a compliant apron and taxiway

Consultation and community engagement

Monthly project updates will be published in the tab below.



To read more about the Bairnsdale Airport, click on one of the links below -

Bairnsdale Airport - Runway Extension and Lighting Upgrade

Bairnsdale Airport - Air Ambulance Transfer Facility

Bairnsdale Airport (eastgippsland.vic.gov.au)



Please click on the Project Updates tab below to follow the progress of this project. Information will be updated regularly as it becomes available, if you would like to stay up to date, please subscribe.

Should you wish to search for other projects in your town, simply type the town name in the search bar.


  • 28 June 2024

    Share 28 June 2024 on Facebook Share 28 June 2024 on Twitter Share 28 June 2024 on Linkedin Email 28 June 2024 link

    Final designs are progressing. Tender for construction will be advised following the Council election caretaker period.

    Public Notice: 2024 Council Election (eastgippsland.vic.gov.au)

  • Project Update - 15 February 2024

    Share Project Update - 15 February 2024 on Facebook Share Project Update - 15 February 2024 on Twitter Share Project Update - 15 February 2024 on Linkedin Email Project Update - 15 February 2024 link

    The development of the detailed design is progressing well.

    Following the completion of the detailed design, tender for construction will be released. This is anticipated to be towards the end of April or early May 2024.

    Affected hangar operators will be communicated with prior to any construction works commencing.

  • Project Update - 8 January 2024

    Share Project Update - 8 January 2024 on Facebook Share Project Update - 8 January 2024 on Twitter Share Project Update - 8 January 2024 on Linkedin Email Project Update - 8 January 2024 link

    The rehabilitation of the Bairnsdale airport taxiway and hanger apron is progressing well.

    Survey and geotechnical investigations were completed prior to Christmas and the consultants are working on the detailed design.

    Further updates will be made available once received by Council.