Lakes Entrance - Aquadome Air Handling Unit Replacement

Share Lakes Entrance - Aquadome Air Handling Unit Replacement on Facebook Share Lakes Entrance - Aquadome Air Handling Unit Replacement on Twitter Share Lakes Entrance - Aquadome Air Handling Unit Replacement on Linkedin Email Lakes Entrance - Aquadome Air Handling Unit Replacement link
Lakes Entrance - Aquadrome

The Lakes Entrance Aquadome is a facility which provides aquatic and recreational services. Comprising a six lane, 25 metre heated indoor pool, Learn to Swim pool, toddler’s pool, spas and sauna, Health Club, Group fitness sessions and a kiosk/café, the need for a more efficient heating and ventilation solution is required to meet the growing needs of the facility.

Objective and scope

Council has allocated funding to develop and design a fit for purpose hall heating and ventilation system that meets the existing capacity and requirements of the facility.

A suitably qualified consultant has been engaged to complete an Occupational Health & Safety systems assessment and review, with the following work underway:

  • Inspect the Air handling unit at Lakes Entrance Aquadome.
  • Complete a condition report of the unit.
  • Review if current equipment is fit for purpose with the facility.
  • Explore and provide recommendation paper for the best Air handling unit system for the Lakes Entrance Aquadome.
  • Draft a Scope of works for the system replacement to go out for tender for replacement.

The tender for the replacement of the Air Handling unit is out to market and closes September 2023.

This project is planned to roll out over the 2023 Christmas and New Year period.

Funding

Funding for this project is provided by Council.



Lakes Entrance Aquadome
43 Palmers Road, Lakes Entrance



Please subscribe to stay informed.

Should you wish to search for other projects in your town, simply type the town name in the search bar.

The Lakes Entrance Aquadome is a facility which provides aquatic and recreational services. Comprising a six lane, 25 metre heated indoor pool, Learn to Swim pool, toddler’s pool, spas and sauna, Health Club, Group fitness sessions and a kiosk/café, the need for a more efficient heating and ventilation solution is required to meet the growing needs of the facility.

Objective and scope

Council has allocated funding to develop and design a fit for purpose hall heating and ventilation system that meets the existing capacity and requirements of the facility.

A suitably qualified consultant has been engaged to complete an Occupational Health & Safety systems assessment and review, with the following work underway:

  • Inspect the Air handling unit at Lakes Entrance Aquadome.
  • Complete a condition report of the unit.
  • Review if current equipment is fit for purpose with the facility.
  • Explore and provide recommendation paper for the best Air handling unit system for the Lakes Entrance Aquadome.
  • Draft a Scope of works for the system replacement to go out for tender for replacement.

The tender for the replacement of the Air Handling unit is out to market and closes September 2023.

This project is planned to roll out over the 2023 Christmas and New Year period.

Funding

Funding for this project is provided by Council.



Lakes Entrance Aquadome
43 Palmers Road, Lakes Entrance



Please subscribe to stay informed.

Should you wish to search for other projects in your town, simply type the town name in the search bar.

  • 18 June 2024

    Share 18 June 2024 on Facebook Share 18 June 2024 on Twitter Share 18 June 2024 on Linkedin Email 18 June 2024 link

    Works at the Lakes Entrance Aquadome are progressing well, with many components nearing completion.

    The new air handling units and switchboard have been installed and successfully connected.

    Lintels and ductwork were fitted in the plant room, and pipework connections to the air handling units were finalised.

    New heat wheel
    New AHU Ready for installation
    New ductwork installed



    We welcome your continued interest in this project. Please choose to follow this project on YourSay to receive important information directly to your inbox.

  • 23 May 2024

    Share 23 May 2024 on Facebook Share 23 May 2024 on Twitter Share 23 May 2024 on Linkedin Email 23 May 2024 link

    The demolition and removal of the existing air handling units commenced this week.

    The dividing brick wall has been removed and the new units and ducting components have arrived on-site.

    Electrical rough-in is underway and anticipated to be completed this week.


    Existing air handing unit which is being replaced - contains a clogged filter

    The existing air handling unit's fan
  • 14 May 2024

    Share 14 May 2024 on Facebook Share 14 May 2024 on Twitter Share 14 May 2024 on Linkedin Email 14 May 2024 link

    The installation of the three new heating pumps is complete, the old pumps have also been removed and will be degassed and recycled.

    Demolition of the dividing wall is anticipated to commence in the coming weeks, along with the arrival of the new air handling units.

    This project is anticipated to be complete by early July 2024.

    Old heat pumps
    New heat pumps



    We welcome your continued interest in this project. Please feel free to share this update with your local network and choose to follow this project on YourSay to receive important information regarding this project directly to your inbox.

  • Tender awarded

    Share Tender awarded on Facebook Share Tender awarded on Twitter Share Tender awarded on Linkedin Email Tender awarded link

    The tender for construction has been awarded to ASM Chilltech. Works are anticipated to commence after the Easter holiday period.

    Please choose to follow this project on Your Say to receive important information regarding this project directly to your inbox.

  • Project Update - 21 November 2023

    Share Project Update - 21 November 2023 on Facebook Share Project Update - 21 November 2023 on Twitter Share Project Update - 21 November 2023 on Linkedin Email Project Update - 21 November 2023 link

    Tender for construction was endorsed on 14 November 2023.


Page last updated: 13 Sep 2024, 02:39 PM