14 May 2024

The installation of the three new heating pumps is complete, the old pumps have also been removed and will be degassed and recycled.

Demolition of the dividing wall is anticipated to commence in the coming weeks, along with the arrival of the new air handling units.

This project is anticipated to be complete by early July 2024.