23 May 2024
The demolition and removal of the existing air handling units commenced this week.
The dividing brick wall has been removed and the new units and ducting components have arrived on-site.
Electrical rough-in is underway and anticipated to be completed this week.
Existing air handing unit which is being replaced - contains a clogged filter |
The existing air handling unit's fan |
Share 23 May 2024 on Facebook
Share 23 May 2024 on Twitter
Share 23 May 2024 on Linkedin
Email 23 May 2024 link