• Project Update - 16 October 2023

    Share Project Update - 16 October 2023 on Facebook Share Project Update - 16 October 2023 on Twitter Share Project Update - 16 October 2023 on Linkedin Email Project Update - 16 October 2023 link

    The new Eagle Point Foreshore Hub is looking fabulous!

    Hub Building

    • The roof cladding and capping are nearing completion.
    • All windows and doors are now installed.
    • Internal plastering works have begun.
    • The concrete stairs and paths on the North side have been laid.
    • The concrete base for the bleacher seating now placed.
    • Works are progressing on the concrete zig zag access ramp.
    • The external timber and steel wall cladding nearing completion.
    • The curved concrete seating at the front of the building has been installed.
    • Some internal oiling of the exposed timber rafters has taken place.

    Car park

    Initial line-marking of the new car park is complete.

    School Road

    Line marking and signage in School Road are complete.

    The Playground

    The playground has been designed by Enlocus Landscape Architects and will have swings, slides, and some play equipment to challenge young imaginations! Here are some concept images to give you an idea of what to expect -






  • Project Update - 12 September 2023

    Share Project Update - 12 September 2023 on Facebook Share Project Update - 12 September 2023 on Twitter Share Project Update - 12 September 2023 on Linkedin Email Project Update - 12 September 2023 link


    The new entry way coming together

    Glaziers installing the glass to the window frames

    Wall cladding being installed

    Roof cladding underway, window glass being installed and concrete works

    Wall cladding and roof cladding installed
    New raised pavement as part of road safety improvement works to School Road
  • Project Update - 28 August 2023

    Share Project Update - 28 August 2023 on Facebook Share Project Update - 28 August 2023 on Twitter Share Project Update - 28 August 2023 on Linkedin Email Project Update - 28 August 2023 link

    The new asphalt road pavement and road safety improvement works to School Road have been completed with line marking.

    The roof cladding has commenced, and external metal wall cladding has been installed. The installation of window frames and glazing is well underway.

    Additional concrete paving has been completed as well as the curved concrete seating. Bleacher seating on the water side of the building is taking shape.


  • Project Update - 22 June 2023

    Share Project Update - 22 June 2023 on Facebook Share Project Update - 22 June 2023 on Twitter Share Project Update - 22 June 2023 on Linkedin Email Project Update - 22 June 2023 link

    Large rock is being installed to define spaces and to support and retain levels. The rock will be softened by mass native planting and landscaping.


  • Project Update 20/04/2023

    Share Project Update 20/04/2023 on Facebook Share Project Update 20/04/2023 on Twitter Share Project Update 20/04/2023 on Linkedin Email Project Update 20/04/2023 link
    supporting image

    Works are progressing well. Carpenters have started installing floor joists to the cafe floor. The road contractor is filling and compacting the base course.

  • Project Update 3/4/2023

    Share Project Update 3/4/2023 on Facebook Share Project Update 3/4/2023 on Twitter Share Project Update 3/4/2023 on Linkedin Email Project Update 3/4/2023 link

    Works are progressing well.

    • The new kerb and channel has now been installed.
    • Internal roadworks continuing.
    • Water and power trenching completed and pipes laid.
    • The steel work to the building has been erected.
    • Footings for stairs and external tiered seating have been excavated and prepared for concrete.
    • 80 % of the new storm water pits have been installed.


  • Project Update 24/01/2023

    Share Project Update 24/01/2023 on Facebook Share Project Update 24/01/2023 on Twitter Share Project Update 24/01/2023 on Linkedin Email Project Update 24/01/2023 link
    supporting image

    Works at the Eagle Point Foreshore Hub are starting to take shape. Works on the new road and carpark, and construction of the new building are progressing well.

    The existing toilet block is now due for demolition with new facilities incorporated in the new building. Council will provide some temporary toilets on the foreshore in the interim period until the new facility is open.

    Works are currently on schedule for a September 2023 completion.

  • Project Update 9 November 2022

    Share Project Update 9 November 2022 on Facebook Share Project Update 9 November 2022 on Twitter Share Project Update 9 November 2022 on Linkedin Email Project Update 9 November 2022 link

    The wet weather has continued to hinder progress but this week the sun is out and construction is in full swing.


    The brick base has been ordered and drainage pits and pipes are on site ready for installation before the kerb and channel is installed.


  • Construction begins 19 September 2022

    Share Construction begins 19 September 2022 on Facebook Share Construction begins 19 September 2022 on Twitter Share Construction begins 19 September 2022 on Linkedin Email Construction begins 19 September 2022 link

    The project is now due to begin construction on 19 September 2022 and to be completed by mid 2023. Throughout this time Council will work hard to provide minimal interruptions to the use of this area, however please note the following:

    • The existing roadway will close to traffic from 19 September 2022, however pedestrian access will remain until late January 2023

    • Works include realignment of the existing roadway from the foreshore, including new formalised parking and improvements where they connect to the School Road intersection

    • The existing toilet block will remain open until its demolition in late January 2023

    • Foreshore access will be restricted from late January 2023 where erosion mitigation works are planned, including beach nourishment south of the existing toilet block


    Please stay tuned to the Your Say page for further updates as the construction progresses.