Project Update 3/4/2023
Works are progressing well.
- The new kerb and channel has now been installed.
- Internal roadworks continuing.
- Water and power trenching completed and pipes laid.
- The steel work to the building has been erected.
- Footings for stairs and external tiered seating have been excavated and prepared for concrete.
- 80 % of the new storm water pits have been installed.