Project Update 3/4/2023

Works are progressing well.

  • The new kerb and channel has now been installed.
  • Internal roadworks continuing.
  • Water and power trenching completed and pipes laid.
  • The steel work to the building has been erected.
  • Footings for stairs and external tiered seating have been excavated and prepared for concrete.
  • 80 % of the new storm water pits have been installed.