The Buchan Linkages Project is nearing completion, with the newly constructed footpath link between the township and Buchan Caves Reserve now open for public use.
There will be some further asphalt works undertaken in the coming week to the John Flynn Reserve driveway and carpark area, along with the installation of safety improvements to the Caves Road Reserve. These safety improvements include updating of existing signage and the installation of four ‘raised pavement’ speed humps to ensure vehicle speed limits can be managed along the Caves Road Reserve.
Community response has been great, with regular walkers already enjoying the morning or evening stroll, with dry feet. The installation of the solar lighting looks great and compliments the pleasant location for locals and visitors to the area.
Share Project Update - 17 May 2023 on Facebook
Share Project Update - 17 May 2023 on Linkedin
Email Project Update - 17 May 2023 link
The Buchan Main Street detail design has now been completed. Copies of the detail designs can be found in the Documents section.
The construction tender will be released to the public this week and will close in 4 weeks.
Share Project Update 17/04/2023 on Facebook
Share Project Update 17/04/2023 on Linkedin
Email Project Update 17/04/2023 link
Solar bollard lighting has been installed.
Picnic tables have been installed within the John Flynn Memorial reserve
Share Project Update 4/04/2023 on Facebook
Share Project Update 4/04/2023 on Linkedin
Email Project Update 4/04/2023 link
EGSC is working with design consultants to have the streetscape documentation finalised as soon as possible.
Part of the shared path leading into the Buchan Caves Reserve will be open to the public over the Easter 2023 long weekend, however further construction is still required to complete the path link to the existing informal gravel carpark within the Buchan Caves Reserve.
Due to the risk to vegetation, there has been an amendment to the path within the Caves Reserve, (see revised plans in the documents section) with the path now stopping at the existing gravel carpark and the road into the reserve will become a shared zone with additional speed reduction and speed humps added.
Street furniture will be added within John Flynn Memorial Reserve over the coming days which will complete this piece of the shared path, connecting the recreational reserve to the town.
The installation of solar bollard lighting along the path will commence after the Easter break.
Share Project Update 29/11/2022 on Facebook
Share Project Update 29/11/2022 on Linkedin
Email Project Update 29/11/2022 link
The shared path from the township into the Buchan Caves Reserve and providing a connection through John Flynn Reserve construction works has commenced.
The streetscape detail design is being finalised, EGSC has been working with the PRG and local community to reinvigorate the town. The design and construction of carparking adjacent the Buchan Hall will also be completed within these works adding much needed carparking to this facility.
Once the detail design documentation has been approved by Regional Road Victoria, the construction package will be released for public tender and subsequent contract award early in 2023.
The Project Reference Group has been meeting regularly and has representatives from Buchan Bush Nursing, local traders, Buchan Quarry & also community members.
Share Project Update 23/11/2022 on Facebook
Share Project Update 23/11/2022 on Linkedin
Email Project Update 23/11/2022 link
Council have received valuable feedback from the October 2022 online and face to face community consultation.
Consultants, Village Well, conducted several workshops and traffic management planning discussions in Buchan.
The key actions from the community consultation to be investigated in the Detailed Design (within the scope of works) are;
Request |
Action |
Add new long vehicle parking bay along central Main Street.
|
Included within Detail Design |
Investigate additional 45-degree parking space on Main St, Buchan Upper and/or better access to car parks out the front of the General Store from the north approach |
Additional carparking added to in front of General store |
Check all swept paths accommodate large truck movements |
Noted and carried out |
Check and design to all building access and vehicle cross over locations |
Noted and carried out |
Provide long vehicle parking at Main St, Buchan Lower |
Included within Detail Design |
Consider future treatment of the monument |
Consultants to explore options |
Tree species to be further refined. Noting that Jacaranda does not suit the environment |
Different tree species to be included within Detail Design |
Provide additional DDA car parks |
Additional carparks included within Detail design |
Liaise with RRV possibility of new bus shelter |
Consultant to follow up |
Upgrade footpath to Buchan upper |
Pending budget |
Dump Point installed at toilet amenity |
Included within Detail Design |
EV Charge point & carpark location |
Location to be directed by EGSC and DEWLP |
Reduce Speed limit to 50km through town centre |
EGSC and RRV to work through |
Share Project Update 17/10/2022 on Facebook
Share Project Update 17/10/2022 on Linkedin
Email Project Update 17/10/2022 link
COMMUNITY CONSULTATION SESSIONS - 17 and 18 October 2022
Council is progressing the Buchan Streetscape Redevelopment to the next stage through the development of a draft plan. Community members are invited to join us for the next phase of the consultation process with in-person events held over evening and morning sessions to view the draft plan and provide further feedback.
Council would like to thank all those community members who have taken part in the consultation process to date, including those who attended the Village Well place making workshops and traffic management planning discussions. Your feedback is greatly valued and appreciated, and your ideas and concerns will help inform this next stage of the draft plan.
The in-person events will be held on 17 October at 7.30 pm at the Buchan Hotel and on 18 October at 8.30 am at the CFA Building.
For anyone who is unable to make the in-person events the draft plan will be available to view and provide feedback online through this YourSay page from 17 to 23 October.
The next steps after this round of consultation will be to develop the final plan and begin construction in early 2023.
Updates will continue to be provided via Your Say so keep an eye out as the project progresses and contact Council with any queries.
Share Project Update - July 2022 on Facebook
Share Project Update - July 2022 on Linkedin
Email Project Update - July 2022 link
Project Update
The Heritage Victoria permit for the proposed shared path project linking the Buchan township to the Caves Reserve information centre has been approved. This is a fantastic achievement and a big milestone for the project which has taken many months of collaboration between Council, Heritage Victoria, Parks Victoria and GLaWAC.
The tender for the construction of the shared path into the Caves Reserve and also the linkage from the township to the swing bridge through John Flynn Reserve is open for public tender. This tender period is open until 10 August 2022.
Estimated construction start for these works is mid October for a finishing date of April 2023.
Share Project Update 24/11/2021 on Facebook
Share Project Update 24/11/2021 on Linkedin
Email Project Update 24/11/2021 link
Imagine Buchan Workshop a big success!
With COVID restrictions easing in November the team at Village Well were able to run in person workshops to develop ideas for the project in Buchan. All Buchan District community members were invited to join us at two sessions on 16-17 November 2021. On Tuesday 16 November Village Well and 'streetmakers' Complete Streets hosted an inspiring, engaging and practical workshop to hear your ideas and aspirations for the streetscape and how you think it should connect to the Buchan identity and place experience more broadly. We want to thank the community members who attended the workshop and drop in session to provide feedback and valuable ideas.
This was the first step in the community consultation process to develop the masterplan for the upgrade of Buchan's main street. The team at Village Well are working on the report which will be available for community to review early in 2022. Please subscribe to stay up to date with this project and to learn about further consultation opportunities.
Share Project Update 11/10/2021 on Facebook
Share Project Update 11/10/2021 on Linkedin
Email Project Update 11/10/2021 link
Community consultation opens
With COVID restrictions easing in November the team at Village Well will be able to run in person workshops to develop ideas for the project. All Buchan District community members are invited to join us at both of the below get togethers.
Online Meet 'n' Greet - Tuesday 26 October
Click on the above link to book your place
Village Well will kick-start their consultation journey in an online Meet 'n' Greet where community members are invited to come along, say hello, learn about the process ahead and ask questions about next steps.
In-person Imagine Buchan Community Workshop - 6pm Tuesday 16 November
Click on the above link to book your place
Village Well and 'streetmakers' Complete Streets will host an inspiring, engaging and practical workshop to hear your ideas and aspirations for the streetscape and how you think it should connect to the Buchan identity and place experience more broadly