Works are progressing well.
Construction of the court and footpath connections along the south side of Main Street are well underway.
Works surrounding the toilet block are underway, which involve additional drainage enhancements, footpaths, and landscaping. The relocation of the BBQ and the replacement of current street furniture are expected to occur in the upcoming weeks.
The installation of the electric vehicle charger proposed for the site is also anticipated to commence shortly and should be operational by June 2024
Share Project Update - 21 December 2023 on Facebook
Share Project Update - 21 December 2023 on Linkedin
Email Project Update - 21 December 2023 link
Our Contractor Fulton Hogan Industries Pty Ltd has made some real progress onsite, with a large section of the work nearly complete on the south side between the John Flynn Reserve and the Willows Café.
Drainage improvements are ongoing throughout the site, which will allow for related landscaping and tree planting to commence in the new year.
Works are scheduled to be completed by early May 2024.
Share Project Update - 8 December 2023 on Facebook
Share Project Update - 8 December 2023 on Linkedin
Email Project Update - 8 December 2023 link
Buchan Streetscape Redevelopment
Fulton Hogan Industries Pty Ltd have commenced works onsite along the south side Service Road, from the John Flynn Reserve through to Willows Café.
Following a short Christmas holiday shut down period, works will continue through the New Year along this section of the service road to the public toilets (from 29 January 2024).
This exciting Project for the Buchan Community will see not only the existing drainage infrastructure upgraded or replaced, but the overall amenity of the Buchan township improved for residents, businesses, and visitors to the area.
Buchan Linkages Project
The newly constructed Buchan Linkages Project has experienced its first flood event and has held up well. The river flat area, between the Main Road Bridge and the Caves House on Caves Road is currently having silt and debris removed by Parks Victoria staff to allow for the walking path to be re-opened. The lighting bollards certainly provided a spectacle for those who witnessed the weekend flooding event.
Further photos have been added to the photos section.
Share Project Update - 10 October 2023 on Facebook
Share Project Update - 10 October 2023 on Linkedin
Email Project Update - 10 October 2023 link
The contract for the Buchan Main Street and Linkages project civil works was awarded at the 5 September Council meeting to Fulton Hogan Industries Pty Ltd. The contractors anticipate mobilisation to site in November 2023 for the commencement of construction.
We are mindful of community activity and visitor movements leading into the peak tourist season and will make every effort to minimise the potential impact of the works within the township.
Dates will be advised when available.
Share Project Update - 10 August 2023 on Facebook
Share Project Update - 10 August 2023 on Linkedin
Email Project Update - 10 August 2023 link
The Buchan Streetscape project is progressing towards construction. An updated layout plan is available to be viewed in the documents sections (or click on the green link above).
Minor adjustments to the final design have been necessary to align with available budget, these changes will not impact the general delivery of the streetscape project.
The key outcomes that will be delivered are:
- Car parking will be increased within the town.
- Both service roads will remain two-way.
- The area near the existing playground and toilet block will be formalised and activated as shown in the previous design.
- Additional carparking will be implemented near the playground and the adjacent the CFA Shed.
- Additional carparking will be implemented adjacent the Hall.
- Roads will be re-sealed and line marked. This will improve vehicle and pedestrian safety
- Long Vehicle carparking will be created and sign posted.
- Pram crossings will be realigned to provide safer crossing points.
- Street furniture will be upgraded, and additional tables installed, where appropriate.
- Additional tree plantings and gardens will be installed.
Commencement of construction is to be confirmed once a contractor has been engaged to undertake the works.
Council will be in contact with property owners that may be impacted by the works.
Share Project Update 23 May 2023 on Facebook
Share Project Update 23 May 2023 on Linkedin
Email Project Update 23 May 2023 link
There has been a slight delay in the proposed asphalt works for this week due to weather.
We expect the works to be completed early next week (weather dependent).
Share Project Update - 18 May 2023 on Facebook
Share Project Update - 18 May 2023 on Linkedin
Email Project Update - 18 May 2023 link
The Buchan Linkages Project is nearing completion, with the newly constructed footpath link between the township and Buchan Caves Reserve now open for public use.
There will be some further asphalt works undertaken in the coming week to the John Flynn Reserve driveway and carpark area, along with the installation of safety improvements to the Caves Road Reserve. These safety improvements include updating of existing signage and the installation of four ‘raised pavement’ speed humps to ensure vehicle speed limits can be managed along the Caves Road Reserve.
Community response has been great, with regular walkers already enjoying the morning or evening stroll, with dry feet. The installation of the solar lighting looks great and compliments the pleasant location for locals and visitors to the area.
Share Project Update - 17 May 2023 on Facebook
Share Project Update - 17 May 2023 on Linkedin
Email Project Update - 17 May 2023 link
The Buchan Main Street detail design has now been completed. Copies of the detail designs can be found in the Documents section.
The construction tender will be released to the public this week and will close in 4 weeks.
Share Project Update 17/04/2023 on Facebook
Share Project Update 17/04/2023 on Linkedin
Email Project Update 17/04/2023 link
Solar bollard lighting has been installed.
Picnic tables have been installed within the John Flynn Memorial reserve
Share Project Update 4/04/2023 on Facebook
Share Project Update 4/04/2023 on Linkedin
Email Project Update 4/04/2023 link
EGSC is working with design consultants to have the streetscape documentation finalised as soon as possible.
Part of the shared path leading into the Buchan Caves Reserve will be open to the public over the Easter 2023 long weekend, however further construction is still required to complete the path link to the existing informal gravel carpark within the Buchan Caves Reserve.
Due to the risk to vegetation, there has been an amendment to the path within the Caves Reserve, (see revised plans in the documents section) with the path now stopping at the existing gravel carpark and the road into the reserve will become a shared zone with additional speed reduction and speed humps added.
Street furniture will be added within John Flynn Memorial Reserve over the coming days which will complete this piece of the shared path, connecting the recreational reserve to the town.
The installation of solar bollard lighting along the path will commence after the Easter break.