Council have received valuable feedback from the October 2022 online and face to face community consultation.

Consultants, Village Well, conducted several workshops and traffic management planning discussions in Buchan.

The key actions from the community consultation to be investigated in the Detailed Design (within the scope of works) are;

Request

Action

Add new long vehicle parking bay along central Main Street.

Included within Detail Design

Investigate additional 45-degree parking space on Main St, Buchan Upper and/or better access to car parks out the front of the General Store from the north approach

Additional carparking added to in front of General store

Check all swept paths accommodate large truck movements

Noted and carried out

Check and design to all building access and vehicle cross over locations

Noted and carried out

Provide long vehicle parking at Main St, Buchan Lower

Included within Detail Design

Consider future treatment of the monument

Consultants to explore options

Tree species to be further refined. Noting that Jacaranda does not suit the environment

Different tree species to be included within Detail Design

Provide additional DDA car parks

Additional carparks included within Detail design

Liaise with RRV possibility of new bus shelter

Consultant to follow up

Upgrade footpath to Buchan upper

Pending budget

Dump Point installed at toilet amenity

Included within Detail Design

EV Charge point & carpark location

Location to be directed by EGSC and DEWLP

Reduce Speed limit to 50km through town centre

EGSC and RRV to work through