Project Update 23/11/2022
Council have received valuable feedback from the October 2022 online and face to face community consultation.
Consultants, Village Well, conducted several workshops and traffic management planning discussions in Buchan.
The key actions from the community consultation to be investigated in the Detailed Design (within the scope of works) are;
Request |
Action |
Add new long vehicle parking bay along central Main Street. |
Included within Detail Design |
Investigate additional 45-degree parking space on Main St, Buchan Upper and/or better access to car parks out the front of the General Store from the north approach | Additional carparking added to in front of General store |
Check all swept paths accommodate large truck movements |
Noted and carried out |
Check and design to all building access and vehicle cross over locations |
Noted and carried out |
Provide long vehicle parking at Main St, Buchan Lower |
Included within Detail Design |
Consider future treatment of the monument |
Consultants to explore options |
Tree species to be further refined. Noting that Jacaranda does not suit the environment |
Different tree species to be included within Detail Design |
Provide additional DDA car parks |
Additional carparks included within Detail design |
Liaise with RRV possibility of new bus shelter |
Consultant to follow up |
Upgrade footpath to Buchan upper |
Pending budget |
Dump Point installed at toilet amenity |
Included within Detail Design |
EV Charge point & carpark location |
Location to be directed by EGSC and DEWLP |
Reduce Speed limit to 50km through town centre | EGSC and RRV to work through |
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends