2 September 2024
Share 2 September 2024 on Facebook Share 2 September 2024 on Twitter Share 2 September 2024 on Linkedin Email 2 September 2024 linkThe tender for the construction of Buchan Recreation Reserve Pavilion submitted by Cadbuild Construction for $4,469,597.44 ex GST was accepted at the 27 August Council meeting.
The pavilion will provide a space for social and physical activity and play a vital role in improving community resilience, social wellbeing, community identity, sense of place, and health.
Read the media release here: Council Meeting outcomes – Tuesday 27 August 2024
The tender for the construction of Buchan Recreation Reserve Pavilion submitted by Cadbuild Construction for $4,469,597.44 ex GST was accepted at the 27 August Council meeting.
The pavilion will provide a space for social and physical activity and play a vital role in improving community resilience, social wellbeing, community identity, sense of place, and health.
Read the media release here: Council Meeting outcomes – Tuesday 27 August 2024
-
30 August 2024
Share 30 August 2024 on Facebook Share 30 August 2024 on Twitter Share 30 August 2024 on Linkedin Email 30 August 2024 linkOur contractor, Clint Kelly Excavations, is quickly getting on with the job, with the possession of site issued on Monday afternoon and works starting first thing on Tuesday 27 August 2024.
Work this week has included:
- Removal of the existing Netball and front fence – Completed.
- Demolition of the hit-up wall – Completed.
- Removal of the existing light poles and fittings - Completed.
- Removal of the existing asphalt court surface - underway
The demolished concrete and asphalt are being sent to a local business for recycling.
Work for next week is.
- Removal of asbestos from the existing buildings – is programmed for Friday 6 September 2024.
- Demolition works to be continued.
- Site boundary and levels set out.
- Delivery of stormwater pipes, pits and electrical conduit.
- Sub-base investigation works.



Our contractor, Clint Kelly Excavations, is quickly getting on with the job, with the possession of site issued on Monday afternoon and works starting first thing on Tuesday 27 August 2024.
Work this week has included:
- Removal of the existing Netball and front fence – Completed.
- Demolition of the hit-up wall – Completed.
- Removal of the existing light poles and fittings - Completed.
- Removal of the existing asphalt court surface - underway
The demolished concrete and asphalt are being sent to a local business for recycling.
Work for next week is.
- Removal of asbestos from the existing buildings – is programmed for Friday 6 September 2024.
- Demolition works to be continued.
- Site boundary and levels set out.
- Delivery of stormwater pipes, pits and electrical conduit.
- Sub-base investigation works.



-
28 June 2024
Share 28 June 2024 on Facebook Share 28 June 2024 on Twitter Share 28 June 2024 on Linkedin Email 28 June 2024 linkThe local Buchan community welcomed Council’s intention to upgrade and revitalise the recreation reserve with better sporting and community facilities to enrich the lifestyle, character, and resilience of the Buchan, Gelantipy and district communities.
We are moving closer towards construction.
Works are anticipated to commence later this year following the award of the contract for construction of the Netball / Tennis Courts at the 25 June 2024 Council meeting.
We commend the local Buchan community and Project Reference Group in their efforts to progress the project to this key milestone.
Council’s ongoing collaboration with the Buchan community and Project Reference Group has progressed the concept to detailed design for pavilion and pony club shed. Other key elements of the masterplan include upgraded pony club yards, cricket nets, oval, play space.
This project is jointly funded by the Australian and Victorian Governments under the Commonwealth-State Disaster Recovery Funding Arrangements, in conjunction with Council.
Construction details and timing will be shared on YourSay once they have been established.
View the media release online:
The local Buchan community welcomed Council’s intention to upgrade and revitalise the recreation reserve with better sporting and community facilities to enrich the lifestyle, character, and resilience of the Buchan, Gelantipy and district communities.
We are moving closer towards construction.
Works are anticipated to commence later this year following the award of the contract for construction of the Netball / Tennis Courts at the 25 June 2024 Council meeting.
We commend the local Buchan community and Project Reference Group in their efforts to progress the project to this key milestone.
Council’s ongoing collaboration with the Buchan community and Project Reference Group has progressed the concept to detailed design for pavilion and pony club shed. Other key elements of the masterplan include upgraded pony club yards, cricket nets, oval, play space.
This project is jointly funded by the Australian and Victorian Governments under the Commonwealth-State Disaster Recovery Funding Arrangements, in conjunction with Council.
Construction details and timing will be shared on YourSay once they have been established.
View the media release online:
-
26 June 2024
Share 26 June 2024 on Facebook Share 26 June 2024 on Twitter Share 26 June 2024 on Linkedin Email 26 June 2024 linkTender for the construction of the pavilion is OPEN.
Tender closes Wednesday 17 July 2024.
To be a part of this exciting project, submit your tender application at - Tenders (eastgippsland.vic.gov.au)
We welcome your continued interest in this project. Please feel free to share this update with your local network and choose to follow this project on YourSay to receive important information regarding this project directly to your inbox.
Tender for the construction of the pavilion is OPEN.
Tender closes Wednesday 17 July 2024.
To be a part of this exciting project, submit your tender application at - Tenders (eastgippsland.vic.gov.au)
We welcome your continued interest in this project. Please feel free to share this update with your local network and choose to follow this project on YourSay to receive important information regarding this project directly to your inbox.
-
15 May 2024
Share 15 May 2024 on Facebook Share 15 May 2024 on Twitter Share 15 May 2024 on Linkedin Email 15 May 2024 linkTender for construction has closed
Tender submissions for the construction of the Netball Tennis Courts are scheduled to be presented to Council at the 25 June Council Meeting.
Further updates will be provided once the tender evaluation process has been completed.
Tender for construction has closed
Tender submissions for the construction of the Netball Tennis Courts are scheduled to be presented to Council at the 25 June Council Meeting.
Further updates will be provided once the tender evaluation process has been completed.
-
2 May 2024
Share 2 May 2024 on Facebook Share 2 May 2024 on Twitter Share 2 May 2024 on Linkedin Email 2 May 2024 linkTender for construction of the netball and tennis courts is open.
To be a part of this exciting project, submit your tender application at - Tenders (eastgippsland.vic.gov.au)
Tender closes 15 May 2024.
Tender for construction of the netball and tennis courts is open.
To be a part of this exciting project, submit your tender application at - Tenders (eastgippsland.vic.gov.au)
Tender closes 15 May 2024.
-
Project Update - 22 December 2023
Share Project Update - 22 December 2023 on Facebook Share Project Update - 22 December 2023 on Twitter Share Project Update - 22 December 2023 on Linkedin Email Project Update - 22 December 2023 linkTender for construction of the netball and tennis courts will be re-advertised in the New Year.
Loft Architects are continuing to development the detail design plans for the new pavilion, informed by community feedback and the project reference group.
Tender for construction of the netball and tennis courts will be re-advertised in the New Year.
Loft Architects are continuing to development the detail design plans for the new pavilion, informed by community feedback and the project reference group.
-
Project Update - 25 October 2023
Share Project Update - 25 October 2023 on Facebook Share Project Update - 25 October 2023 on Twitter Share Project Update - 25 October 2023 on Linkedin Email Project Update - 25 October 2023 linkTender for construction of the netball and tennis courts is now open. Tender closes 8 November 2023.
The detail design and engineering plans have been tendered for the upgrade to the Netball and Tennis courts. The tender closes on 8 November 2023.
Loft Architects are continuing the development of the detail design plans for the new pavilion, informed by community feedback and the project reference group.
Tender for construction of the netball and tennis courts is now open. Tender closes 8 November 2023.
The detail design and engineering plans have been tendered for the upgrade to the Netball and Tennis courts. The tender closes on 8 November 2023.
Loft Architects are continuing the development of the detail design plans for the new pavilion, informed by community feedback and the project reference group.
-
Project Update - 10 October 2023
Share Project Update - 10 October 2023 on Facebook Share Project Update - 10 October 2023 on Twitter Share Project Update - 10 October 2023 on Linkedin Email Project Update - 10 October 2023 linkThe Project Reference Group and Council officers have been meeting with Loft Architects to finalise detailed plans. The tender for construction of the netball tennis courts will soon be advised.
The Project Reference Group and Council officers have been meeting with Loft Architects to finalise detailed plans. The tender for construction of the netball tennis courts will soon be advised.
-
Project update - 30 March 2023
Share Project update - 30 March 2023 on Facebook Share Project update - 30 March 2023 on Twitter Share Project update - 30 March 2023 on Linkedin Email Project update - 30 March 2023 linkOver the past two months Council has been working closely with Loft Architecture (Architects) to prepare detail design documentation that will allow the project to be tendered for construction. These works will revitalise the recreational hub, providing improved facilities for local sporting groups.
The local Project Reference Group, made up of representatives from the various recreational clubs – football, tennis, netball, pony club and cricket, and the hall committee have been meeting regularly with Council and the consultants to review the detailed plan development and ensure the community is kept updated on the progress of the project.
Over the past two months Council has been working closely with Loft Architecture (Architects) to prepare detail design documentation that will allow the project to be tendered for construction. These works will revitalise the recreational hub, providing improved facilities for local sporting groups.
The local Project Reference Group, made up of representatives from the various recreational clubs – football, tennis, netball, pony club and cricket, and the hall committee have been meeting regularly with Council and the consultants to review the detailed plan development and ensure the community is kept updated on the progress of the project.