30 August 2024

Our contractor, Clint Kelly Excavations, is quickly getting on with the job, with the possession of site issued on Monday afternoon and works starting first thing on Tuesday 27 August 2024.

Work this week has included:

  • Removal of the existing Netball and front fence – Completed.
  • Demolition of the hit-up wall – Completed.
  • Removal of the existing light poles and fittings - Completed.
  • Removal of the existing asphalt court surface - underway


The demolished concrete and asphalt are being sent to a local business for recycling.


Work for next week is.

  • Removal of asbestos from the existing buildings – is programmed for Friday 6 September 2024.
  • Demolition works to be continued.
  • Site boundary and levels set out.
  • Delivery of stormwater pipes, pits and electrical conduit.
  • Sub-base investigation works.


Categories: Netball Tennis Courts
Share 30 August 2024 on Facebook Share 30 August 2024 on Twitter Share 30 August 2024 on Linkedin Email 30 August 2024 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>