July 2026
Share July 2026 on Facebook Share July 2026 on X (formerly Twitter) Share July 2026 on Linkedin Email July 2026 linkWorld Soccer Precinct Redevelopment Ready to Kick off 🎉
After years of planning, advocacy and collaboration, the WORLD Soccer Precinct Redevelopment is ready to move from concept to construction.
The project has been highly anticipated by East Gippsland’s soccer community and represents a significant milestone for sport and recreation across the region. A significant breakthrough for the project was receiving approval under the Commonwealth Environment Protection and Biodiversity Conservation (EPBC) Act 1989, along with an approved environmental offset package - a critical step that enables the project to proceed.
More than just a sporting facility, this project is about creating opportunities for participation and belonging. It is about creating a home for one of East Gippsland's largest participation sports and delivering facilities that reflect the sport’s importance and continued growth across the region.
Soccer has been at the heart of the precinct’s planning since its inclusion in the Bairnsdale Sporting Facilities Plan, with local clubs long advocating for facilities that better support players, volunteers and spectators.
With more than 800 participants involved each year, the redevelopment will bring soccer activities together at a single site and resolve the long-standing challenge of operating across multiple locations.
Council acknowledges the patience, commitment and advocacy of local clubs and the broader soccer community throughout the planning process. Their support has played an important role in bringing the project to this stage.
Works are expected to commence in the coming weeks, with site establishment and early construction activities set to get underway.
A New Home for Soccer in East Gippsland
The redevelopment will deliver a modern, purpose-built sporting precinct featuring:
One natural grass playing field
One synthetic playing field
A new pavilion
Drainage, earthworks and supporting infrastructure
Landscaping and environmental improvements across the site
Early works
An important first stage of the project involves relocating an existing water main that currently runs through the proposed playing field area. This work is required before construction of the new sporting facilities can commence.
Environmental improvements
The redevelopment has been carefully designed to balance improved sporting facilities with environmental stewardship, delivering benefits for both the community and the surrounding landscape.
Alongside the new sporting facilities, the project includes a range of environmental enhancements designed to improve the site's long-term ecological value.
Works will include:
Creation of a new wetland area
Additional revegetation planting
New landscape treatments throughout the precinct
These works will enhance biodiversity outcomes across the precinct while creating a more attractive, resilient and environmentally sustainable recreational space for the community.
Vegetation removal
To enable construction of the new facilities, some vegetation removal is required within the project footprint. These works have been carefully considered through the project's design and approvals process, including detailed environmental assessments undertaken to support the redevelopment.
Wherever possible, vegetation impacts will be minimised, with replacement planting and wetland revegetation forming a key part of the precinct's landscape and environmental strategy.
Access and traffic
Construction vehicles will access the site via Albert Street and the laneway off Wallace Street. A detailed traffic and access management plan is currently being finalised.
Any temporary impacts to roads, parking areas or nearby facilities will be communicated to the community in advance.
Stay informed
The commencement of works marks the beginning of an exciting new chapter for soccer in East Gippsland. After years of planning and perseverance, the community will soon see the transformation of the WORLD Soccer Precinct take shape.
Project updates, including construction milestones, any temporary disruptions and environmental works, will continue to be shared through Your Say East Gippsland and Council's communication channels.
World Soccer Precinct Redevelopment Ready to Kick off 🎉
After years of planning, advocacy and collaboration, the WORLD Soccer Precinct Redevelopment is ready to move from concept to construction.
The project has been highly anticipated by East Gippsland’s soccer community and represents a significant milestone for sport and recreation across the region. A significant breakthrough for the project was receiving approval under the Commonwealth Environment Protection and Biodiversity Conservation (EPBC) Act 1989, along with an approved environmental offset package - a critical step that enables the project to proceed.
More than just a sporting facility, this project is about creating opportunities for participation and belonging. It is about creating a home for one of East Gippsland's largest participation sports and delivering facilities that reflect the sport’s importance and continued growth across the region.
Soccer has been at the heart of the precinct’s planning since its inclusion in the Bairnsdale Sporting Facilities Plan, with local clubs long advocating for facilities that better support players, volunteers and spectators.
With more than 800 participants involved each year, the redevelopment will bring soccer activities together at a single site and resolve the long-standing challenge of operating across multiple locations.
Council acknowledges the patience, commitment and advocacy of local clubs and the broader soccer community throughout the planning process. Their support has played an important role in bringing the project to this stage.
Works are expected to commence in the coming weeks, with site establishment and early construction activities set to get underway.
A New Home for Soccer in East Gippsland
The redevelopment will deliver a modern, purpose-built sporting precinct featuring:
One natural grass playing field
One synthetic playing field
A new pavilion
Drainage, earthworks and supporting infrastructure
Landscaping and environmental improvements across the site
Early works
An important first stage of the project involves relocating an existing water main that currently runs through the proposed playing field area. This work is required before construction of the new sporting facilities can commence.
Environmental improvements
The redevelopment has been carefully designed to balance improved sporting facilities with environmental stewardship, delivering benefits for both the community and the surrounding landscape.
Alongside the new sporting facilities, the project includes a range of environmental enhancements designed to improve the site's long-term ecological value.
Works will include:
Creation of a new wetland area
Additional revegetation planting
New landscape treatments throughout the precinct
These works will enhance biodiversity outcomes across the precinct while creating a more attractive, resilient and environmentally sustainable recreational space for the community.
Vegetation removal
To enable construction of the new facilities, some vegetation removal is required within the project footprint. These works have been carefully considered through the project's design and approvals process, including detailed environmental assessments undertaken to support the redevelopment.
Wherever possible, vegetation impacts will be minimised, with replacement planting and wetland revegetation forming a key part of the precinct's landscape and environmental strategy.
Access and traffic
Construction vehicles will access the site via Albert Street and the laneway off Wallace Street. A detailed traffic and access management plan is currently being finalised.
Any temporary impacts to roads, parking areas or nearby facilities will be communicated to the community in advance.
Stay informed
The commencement of works marks the beginning of an exciting new chapter for soccer in East Gippsland. After years of planning and perseverance, the community will soon see the transformation of the WORLD Soccer Precinct take shape.
Project updates, including construction milestones, any temporary disruptions and environmental works, will continue to be shared through Your Say East Gippsland and Council's communication channels.
-
February 2026
Share February 2026 on Facebook Share February 2026 on X (formerly Twitter) Share February 2026 on Linkedin Email February 2026 linkWhat's happening now
The soccer precinct design package was formally released to tender on 13 February, with submissions due by 1 April. An addendum will be issued to include the sports field construction component, ensuring a complete and coordinated tender scope.
Tender now openCloses: 12.00 pm, Wednesday 1 April 2026Tender documents, along with any pre‑tender meeting or on‑site inspection details, are available via VendorPanel:What's happening next
- Environment Protection and Biodiversity Conservation Act 1999 (EPBC) assessment:
The environmental documentation to be released for a 10‑business‑day public comment period as part of the EPBC approval process.
What's happening now
The soccer precinct design package was formally released to tender on 13 February, with submissions due by 1 April. An addendum will be issued to include the sports field construction component, ensuring a complete and coordinated tender scope.
Tender now openCloses: 12.00 pm, Wednesday 1 April 2026Tender documents, along with any pre‑tender meeting or on‑site inspection details, are available via VendorPanel:What's happening next
- Environment Protection and Biodiversity Conservation Act 1999 (EPBC) assessment:
The environmental documentation to be released for a 10‑business‑day public comment period as part of the EPBC approval process.
- Environment Protection and Biodiversity Conservation Act 1999 (EPBC) assessment:
-
Tender open: WORLD Soccer Pavilion and Pitches - Construction works
Share Tender open: WORLD Soccer Pavilion and Pitches - Construction works on Facebook Share Tender open: WORLD Soccer Pavilion and Pitches - Construction works on X (formerly Twitter) Share Tender open: WORLD Soccer Pavilion and Pitches - Construction works on Linkedin Email Tender open: WORLD Soccer Pavilion and Pitches - Construction works linkCON2026 1755 - WORLD Soccer Pavilion and Pitches - Construction works.
Closes 12.00 pm, Wednesday 11 March 2026.
Any pretender meetings or on-site inspections, if applicable, please refer to Part 1 - Conditions of Tendering. All documents are available at https://vendorpanel.com/
CON2026 1755 - WORLD Soccer Pavilion and Pitches - Construction works.
Closes 12.00 pm, Wednesday 11 March 2026.
Any pretender meetings or on-site inspections, if applicable, please refer to Part 1 - Conditions of Tendering. All documents are available at https://vendorpanel.com/
-
Netball Association Championships - Sunday 15 June 2025
Share Netball Association Championships - Sunday 15 June 2025 on Facebook Share Netball Association Championships - Sunday 15 June 2025 on X (formerly Twitter) Share Netball Association Championships - Sunday 15 June 2025 on Linkedin Email Netball Association Championships - Sunday 15 June 2025 linkOur WORLD Sporting Complex netball courts and pavilion were buzzing on Sunday for the Netball Victoria Association Championships, featuring 500 players and in total about 1,000 supporters, volunteers and officials.
There were some tired young netballers on Sunday night, but what an opportunity for our local players to put their skills on display against the best from Gippsland on their home courts. To the band of volunteers, thank you for helping create an environment where some great memories were made.
It’s events such as these that are now possible because of the investment we’ve made in this facility.
Our WORLD Sporting Complex netball courts and pavilion were buzzing on Sunday for the Netball Victoria Association Championships, featuring 500 players and in total about 1,000 supporters, volunteers and officials.
There were some tired young netballers on Sunday night, but what an opportunity for our local players to put their skills on display against the best from Gippsland on their home courts. To the band of volunteers, thank you for helping create an environment where some great memories were made.
It’s events such as these that are now possible because of the investment we’ve made in this facility.
-
PUBLIC NOTICE
Share PUBLIC NOTICE on Facebook Share PUBLIC NOTICE on X (formerly Twitter) Share PUBLIC NOTICE on Linkedin Email PUBLIC NOTICE linkRE DEVELOPMENT of THE WOMENS ORGINISATION for RECREATION, LEISURE, and DEVELOPMENT (WORLD) SPORTING PRECINCT, 99 WALLACE STREET BAIRNSDALE VICTORIA 3875 (EPBC Act Ref 2022/09215)
INVITATION FOR PUBLIC COMMENT
The following notice is published pursuant to Section 95A(3) of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).
East Gippsland Shire Council (EGSC) is seeking approval under the Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) for the development of additional sporting facilities at 99 Wallace Street, Bairnsdale, Victoria. The site is zoned Public Use Zone – Education (PUZ2) and is a designated Bushfire Prone Area (BPA) under the East Gippsland Planning Scheme. It comprises open fields of grassland, as well as open woodland and a nearby natural wetland. East Gippsland Specialist School is located to the immediate south, Westdale Kindergarten to the immediate north and Bairnsdale Secondary College and Bairnsdale Aquatic and Recreation Centre to the immediate east.
The proposed action has been referred under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) and determined to be a “controlled action” under the EPBC Act with a Preliminary Documentation level of assessment set.
The controlling provision under the EPBC Act is “Listed threatened species and communities” (Sections 18 and 18A) – in particular the Gippsland Red Gum (Eucalyptus tereticornis subsp. mediana) Grassy Woodland and Associated Native Grassland (Gippsland Red Gum/GRGGW) ecological community – Critically Endangered and Seasonal Herbaceous Wetlands (Freshwater) of the Temperate Lowland Plains (Seasonal Herbaceous Wetlands/SHWTLP) ecological community – Critically Endangered.
Additional information has been submitted to the Department of Climate Change, Energy, the Environment and Water. Pursuant to Section 95A(3) of the EPBC Act, these documents are now available for viewing at the following locations:
- Bairnsdale Library - 22 Service Street Bairnsdale
- State Library Victoria - 328 Swanston Street, Melbourne.
The documents can also be viewed or downloaded at:
https://yoursay.eastgippsland.vic.gov.au/Interested persons are invited to comment on the draft PD information, which are to be received by close of business Wednesday, 25 of June 2025 and addressed to:
Kate Allen
Natural Environment Coordinator, Environmental Projects
EAST GIPPSLAND SHIRE COUNCIL
PO Box 1618 Bairnsdale VIC 3875
Or email KateA@egipps.vic.gov.auNote: Persons with any special needs (e.g. for whom English is a second language or who have vision impairment) may contact Kate Allen via the details above for assistance in accessing the documentation.
RE DEVELOPMENT of THE WOMENS ORGINISATION for RECREATION, LEISURE, and DEVELOPMENT (WORLD) SPORTING PRECINCT, 99 WALLACE STREET BAIRNSDALE VICTORIA 3875 (EPBC Act Ref 2022/09215)
INVITATION FOR PUBLIC COMMENT
The following notice is published pursuant to Section 95A(3) of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).
East Gippsland Shire Council (EGSC) is seeking approval under the Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) for the development of additional sporting facilities at 99 Wallace Street, Bairnsdale, Victoria. The site is zoned Public Use Zone – Education (PUZ2) and is a designated Bushfire Prone Area (BPA) under the East Gippsland Planning Scheme. It comprises open fields of grassland, as well as open woodland and a nearby natural wetland. East Gippsland Specialist School is located to the immediate south, Westdale Kindergarten to the immediate north and Bairnsdale Secondary College and Bairnsdale Aquatic and Recreation Centre to the immediate east.
The proposed action has been referred under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) and determined to be a “controlled action” under the EPBC Act with a Preliminary Documentation level of assessment set.
The controlling provision under the EPBC Act is “Listed threatened species and communities” (Sections 18 and 18A) – in particular the Gippsland Red Gum (Eucalyptus tereticornis subsp. mediana) Grassy Woodland and Associated Native Grassland (Gippsland Red Gum/GRGGW) ecological community – Critically Endangered and Seasonal Herbaceous Wetlands (Freshwater) of the Temperate Lowland Plains (Seasonal Herbaceous Wetlands/SHWTLP) ecological community – Critically Endangered.
Additional information has been submitted to the Department of Climate Change, Energy, the Environment and Water. Pursuant to Section 95A(3) of the EPBC Act, these documents are now available for viewing at the following locations:
- Bairnsdale Library - 22 Service Street Bairnsdale
- State Library Victoria - 328 Swanston Street, Melbourne.
The documents can also be viewed or downloaded at:
https://yoursay.eastgippsland.vic.gov.au/Interested persons are invited to comment on the draft PD information, which are to be received by close of business Wednesday, 25 of June 2025 and addressed to:
Kate Allen
Natural Environment Coordinator, Environmental Projects
EAST GIPPSLAND SHIRE COUNCIL
PO Box 1618 Bairnsdale VIC 3875
Or email KateA@egipps.vic.gov.auNote: Persons with any special needs (e.g. for whom English is a second language or who have vision impairment) may contact Kate Allen via the details above for assistance in accessing the documentation.
-
27 November 2024
Share 27 November 2024 on Facebook Share 27 November 2024 on X (formerly Twitter) Share 27 November 2024 on Linkedin Email 27 November 2024 linkWe will formally open three major projects in coming days, celebrating with the community new facilities that are supporting people, social connections and economy.
The official opening of Orbost Forest Park will take place at 10.30am this Friday, 29 November, followed by the WORLD Sporting Precinct at 5.30pm on Thursday 5 December, and Stage 1 of the Omeo Mountain Bike Trails at 11.30am on Friday 6 December.
Each project features a formal ceremony, and community celebrations, with all residents and visitors encouraged to attend.
WORLD Sporting Precinct Building on a long history
The WORLD Sporting Precinct represents a $17.4 million investment in regional sport and recreation. Featuring new netball courts, hockey pitches, and a modern pavilion, the facility builds on decades of community effort and volunteer dedication.
“It’s not just a place for sport - it’s a hub where friendships are formed, skills are developed, and communities come together,” Fiona said.
The opening event will include an exhibition netball game by the Bairnsdale Netball Association.
Orbost Forest Park a draw for locals and visitors
The $1.9 million revitalisation has transformed the park into an inviting and accessible space, complete with enhanced amenities and new playground.
It includes enhanced walking paths, expanded parking, new picnic facilities, a barbecue area, and a modern adventure playground designed input with local students. The park is a leading example of community-focused design and reflects the importance of listening to our communities.
The result is a vibrant space that caters to everyone - from families enjoying a picnic to visitors discovering the region.
The opening event will feature a teddy bears’ picnic for kids, as well as a barbecue and formal ribbon cutting with more than 100 children expected to head to the park for the event.
Omeo Mountain Bike Trails - Putting Omeo on the MTB map
The opening of Stage 1 of the Omeo Mountain Bike Trails marks the completion of the first 50km of trails. Designed for riders of all abilities, the trails are complemented by Livingstone Park’s new facilities, including changerooms, showers, a bike wash and pump track.
When finished, the trail network will extend over 100km, positioning Omeo as a premier mountain biking destination.
Locals and visitors are invited to bring a bike and give the trails a try after the formal opening.
To read more, visit:
Media Release: Council to launch major sports and recreation projects (eastgippsland.vic.gov.au)
We will formally open three major projects in coming days, celebrating with the community new facilities that are supporting people, social connections and economy.
The official opening of Orbost Forest Park will take place at 10.30am this Friday, 29 November, followed by the WORLD Sporting Precinct at 5.30pm on Thursday 5 December, and Stage 1 of the Omeo Mountain Bike Trails at 11.30am on Friday 6 December.
Each project features a formal ceremony, and community celebrations, with all residents and visitors encouraged to attend.
WORLD Sporting Precinct Building on a long history
The WORLD Sporting Precinct represents a $17.4 million investment in regional sport and recreation. Featuring new netball courts, hockey pitches, and a modern pavilion, the facility builds on decades of community effort and volunteer dedication.
“It’s not just a place for sport - it’s a hub where friendships are formed, skills are developed, and communities come together,” Fiona said.
The opening event will include an exhibition netball game by the Bairnsdale Netball Association.
Orbost Forest Park a draw for locals and visitors
The $1.9 million revitalisation has transformed the park into an inviting and accessible space, complete with enhanced amenities and new playground.
It includes enhanced walking paths, expanded parking, new picnic facilities, a barbecue area, and a modern adventure playground designed input with local students. The park is a leading example of community-focused design and reflects the importance of listening to our communities.
The result is a vibrant space that caters to everyone - from families enjoying a picnic to visitors discovering the region.
The opening event will feature a teddy bears’ picnic for kids, as well as a barbecue and formal ribbon cutting with more than 100 children expected to head to the park for the event.
Omeo Mountain Bike Trails - Putting Omeo on the MTB map
The opening of Stage 1 of the Omeo Mountain Bike Trails marks the completion of the first 50km of trails. Designed for riders of all abilities, the trails are complemented by Livingstone Park’s new facilities, including changerooms, showers, a bike wash and pump track.
When finished, the trail network will extend over 100km, positioning Omeo as a premier mountain biking destination.
Locals and visitors are invited to bring a bike and give the trails a try after the formal opening.
To read more, visit:
Media Release: Council to launch major sports and recreation projects (eastgippsland.vic.gov.au)
-
6 June 2024
Share 6 June 2024 on Facebook Share 6 June 2024 on X (formerly Twitter) Share 6 June 2024 on Linkedin Email 6 June 2024 linkThe WORLD Sporting Precinct caters to a diverse range of sports, promoting unity and inclusion through engaged recreation.
These modern fit-for-purpose facilities promote inclusivity by accommodating the needs of all participants regardless of gender and ability, ensuring every player feels valued and respected.
WORLD Pavilion
The WORLD Pavilion was completed in June 2024, and comprises:
- four gender neutral change rooms
- umpires changerooms and amenities
- first aid room
- function space that is furnished to accommodate 80 seated patrons
- a commercial kitchen with two canteens to service east and west sporting fields/ courts
- toilet facilities
- disabled access across the building and precinct
This facility is home to Bairnsdale Netball Association, East Gippsland Hockey Association, Bairnsdale Hockey Club, Nagle Hockey Club, Swan Reach Hockey Club.The new WORLD Pavilion is a valuable asset for our community and is available for hire.
Promoting social interaction, recreation, education, and community engagement across a wide spectrum of activities, these versatile facilities serve various purposes beyond sports. The function space with its commercial kitchen and accommodations for 80 patrons makes it an ideal venue for community events such as fundraisers, social gatherings, meetings, and workshops, fitness classes, art classes, wellness programs and health screenings, hosting volunteer recruitment drives, voting stations during elections, and other community service programs – the possibilities are endless!
Key inclusions in the precinct are an eight-court precinct with Marshall’s building, a synthetic playing surface with lighting, a turf field, associated access roads, paths, car parking, and landscaping.
We are grateful for the financial support of the Australian and Victorian Governments, which was invaluable in realising our vision of creating inclusive and accessible recreational spaces for all members of the community.








The WORLD Sporting Precinct caters to a diverse range of sports, promoting unity and inclusion through engaged recreation.
These modern fit-for-purpose facilities promote inclusivity by accommodating the needs of all participants regardless of gender and ability, ensuring every player feels valued and respected.
WORLD Pavilion
The WORLD Pavilion was completed in June 2024, and comprises:
- four gender neutral change rooms
- umpires changerooms and amenities
- first aid room
- function space that is furnished to accommodate 80 seated patrons
- a commercial kitchen with two canteens to service east and west sporting fields/ courts
- toilet facilities
- disabled access across the building and precinct
This facility is home to Bairnsdale Netball Association, East Gippsland Hockey Association, Bairnsdale Hockey Club, Nagle Hockey Club, Swan Reach Hockey Club.The new WORLD Pavilion is a valuable asset for our community and is available for hire.
Promoting social interaction, recreation, education, and community engagement across a wide spectrum of activities, these versatile facilities serve various purposes beyond sports. The function space with its commercial kitchen and accommodations for 80 patrons makes it an ideal venue for community events such as fundraisers, social gatherings, meetings, and workshops, fitness classes, art classes, wellness programs and health screenings, hosting volunteer recruitment drives, voting stations during elections, and other community service programs – the possibilities are endless!
Key inclusions in the precinct are an eight-court precinct with Marshall’s building, a synthetic playing surface with lighting, a turf field, associated access roads, paths, car parking, and landscaping.
We are grateful for the financial support of the Australian and Victorian Governments, which was invaluable in realising our vision of creating inclusive and accessible recreational spaces for all members of the community.








-
Project Update - 5 March 2024
Share Project Update - 5 March 2024 on Facebook Share Project Update - 5 March 2024 on X (formerly Twitter) Share Project Update - 5 March 2024 on Linkedin Email Project Update - 5 March 2024 linkWorks at the WORLD are progressing well.
The power in the pavilion has been turned on, the joinery has been installed, and the internal vinyl work is nearing completion.
A large external concrete pour around the exterior of the building was completed last week, and the first section of exposed aggregate was poured on Thursday.
The pavilion is on schedule to be completed by May 2024.
Additional photos are available in the photos tab:
Photos - WORLD Sporting Precinct Redevelopment


Works at the WORLD are progressing well.
The power in the pavilion has been turned on, the joinery has been installed, and the internal vinyl work is nearing completion.
A large external concrete pour around the exterior of the building was completed last week, and the first section of exposed aggregate was poured on Thursday.
The pavilion is on schedule to be completed by May 2024.
Additional photos are available in the photos tab:
Photos - WORLD Sporting Precinct Redevelopment


-
Project Update - 12 February 2024
Share Project Update - 12 February 2024 on Facebook Share Project Update - 12 February 2024 on X (formerly Twitter) Share Project Update - 12 February 2024 on Linkedin Email Project Update - 12 February 2024 linkThe WORLD pavilion is quickly taking shape, with the following activities already complete:
- Brickwork
- Internal rough-in
- Plastering - complete.
- External high-level cladding – The cladding will provide enhanced insulation and weather protection.
- Painting of ceilings
- Internal lights to be installed this week
- Storm water drainage
- Mains power wiring
Installation of the perforated mesh cladding has commenced.The installation of vinyl flooring, wall cladding, and external concreting will be commencing in the next two weeks.




The WORLD pavilion is quickly taking shape, with the following activities already complete:
- Brickwork
- Internal rough-in
- Plastering - complete.
- External high-level cladding – The cladding will provide enhanced insulation and weather protection.
- Painting of ceilings
- Internal lights to be installed this week
- Storm water drainage
- Mains power wiring
Installation of the perforated mesh cladding has commenced.The installation of vinyl flooring, wall cladding, and external concreting will be commencing in the next two weeks.




-
Project Update - 17 January 2024
Share Project Update - 17 January 2024 on Facebook Share Project Update - 17 January 2024 on X (formerly Twitter) Share Project Update - 17 January 2024 on Linkedin Email Project Update - 17 January 2024 linkThe WORLD pavilion is progressing well.
The pavilion brickwork and internal rough-in are now complete, and plastering inside the pavilion is underway.
External high-level cladding is underway, which will provide enhanced insulation and weather protection.
The WORLD pavilion is progressing well.
The pavilion brickwork and internal rough-in are now complete, and plastering inside the pavilion is underway.
External high-level cladding is underway, which will provide enhanced insulation and weather protection.