Share Paynesville - Slip Road Maritime Precinct on FacebookShare Paynesville - Slip Road Maritime Precinct on TwitterShare Paynesville - Slip Road Maritime Precinct on LinkedinEmail Paynesville - Slip Road Maritime Precinct link
The upgrade of Paynesville's Slip Road Maritime Precinct originated from Council’s adoption of the Paynesville Maritime Precinct Masterplan and has been undertaken to bring significant benefits to the local economy and enhance Paynesville as a year-round destination for visitors, residents, and businesses alike.
Construction commenced in January 2022 with Carter Marine Group starting onsite piling works and offsite fabrication of precast elements for the services jetty. Works were later delayed due to a review of the project’s detailed design following the discovery of unforeseen lakebed conditions.
Carter Marine Group temporarily demobilised from the project site to work on another project in the Lakes Entrance area, and Council engaged an independent contractor to carry out further offshore geotechnical works which were used to update and improve the detailed design.
The new design will ensure the upgrade of the Slip Road Maritime Precinct is structurally secure and better caters to surrounding marine businesses and overflow tourism activities. These improvements are designed to have a lifespan of around 50 years.
Carter Marine was awarded a varied contract for construction of the seawall, jetties and boardwalk. A tender for construction of the carpark and landscaping will be advertised later this year following the finalisation of the marine based work by Carter Marine.
Once remobilised, Carter Marine Group construct the seawalls, services, jetty, and ramp. We appreciate Carter Marine’s cooperation and understanding throughout this process.
The planning and design of the carpark construction is progressing. A Project Reference Group (PRG) will guide this stage of the project and inform the development of the detailed design.
Both the Victorian and Federal governments have recognised the significance of this project by providing significant funding, and we acknowledge their understanding and support for this re-design work.
Objective and Scope
Revitalisation of the Slip Road Maritime Precinct will include -
construction of new seawall and jetties
new boat ramp
Carparking upgrade
boardwalks
pathways
landscaping and art installation
amenity block upgrade (complete)
Funding
This project has attracted significant investment, with the Australian Government, Victorian Government, and East Gippsland Shire Council all providing grant funding.
The upgrade of Paynesville's Slip Road Maritime Precinct originated from Council’s adoption of the Paynesville Maritime Precinct Masterplan and has been undertaken to bring significant benefits to the local economy and enhance Paynesville as a year-round destination for visitors, residents, and businesses alike.
Construction commenced in January 2022 with Carter Marine Group starting onsite piling works and offsite fabrication of precast elements for the services jetty. Works were later delayed due to a review of the project’s detailed design following the discovery of unforeseen lakebed conditions.
Carter Marine Group temporarily demobilised from the project site to work on another project in the Lakes Entrance area, and Council engaged an independent contractor to carry out further offshore geotechnical works which were used to update and improve the detailed design.
The new design will ensure the upgrade of the Slip Road Maritime Precinct is structurally secure and better caters to surrounding marine businesses and overflow tourism activities. These improvements are designed to have a lifespan of around 50 years.
Carter Marine was awarded a varied contract for construction of the seawall, jetties and boardwalk. A tender for construction of the carpark and landscaping will be advertised later this year following the finalisation of the marine based work by Carter Marine.
Once remobilised, Carter Marine Group construct the seawalls, services, jetty, and ramp. We appreciate Carter Marine’s cooperation and understanding throughout this process.
The planning and design of the carpark construction is progressing. A Project Reference Group (PRG) will guide this stage of the project and inform the development of the detailed design.
Both the Victorian and Federal governments have recognised the significance of this project by providing significant funding, and we acknowledge their understanding and support for this re-design work.
Objective and Scope
Revitalisation of the Slip Road Maritime Precinct will include -
construction of new seawall and jetties
new boat ramp
Carparking upgrade
boardwalks
pathways
landscaping and art installation
amenity block upgrade (complete)
Funding
This project has attracted significant investment, with the Australian Government, Victorian Government, and East Gippsland Shire Council all providing grant funding.
Share 14 November 2024 on FacebookShare 14 November 2024 on TwitterShare 14 November 2024 on LinkedinEmail 14 November 2024 link
We are pleased to report significant progress on the maritime precinct upgrade:
Southern Slip Road Seawall: Installation of concrete panels has now commenced for the southern section of the seawall.
Northern Slip Road Seawall: Pile driving activities will continue over the coming months for the northern section. Following completion of this work, concrete panels will be installed.
Floating Pontoons: The design phase for the floating pontoons is nearing completion, and we anticipate offsite prefabrication starting in February 2025.
Boat Ramp & Service Jetty: Construction is scheduled to begin in March 2025.
We will continue to monitor progress and provide updates as Carter Marine progresses work on these key components.
We welcome your continued interest in this project. Please feel free to share this update with your local network and choose to follow this project on YourSay to receive important information regarding this project directly to your inbox.
Share 16 September 2024 on FacebookShare 16 September 2024 on TwitterShare 16 September 2024 on LinkedinEmail 16 September 2024 link
Further updates will be provided on YourSay following the Council Election on 26 October 2024, and the questions/feedback tab will be reinstated.
From 12.00 noon Tuesday 17 September until 6.00 pm on Saturday 26 October (Election Day) we will be in the Local Government Election Period (also known as Caretaker Period).
During this time, we will limit our printed communications, website content, social media activity, and community consultations. The ability for people to comment on our social media content will also be disabled during the Election Period.
Each of these steps is to ensure our content does not affect voting in the election and is consistent with steps taken by other Victorian Councils and the Local Government Act 2020.
These changes are only temporary; we'll be back to normal communication activity after the election.
Share 12 September 2024 on FacebookShare 12 September 2024 on TwitterShare 12 September 2024 on LinkedinEmail 12 September 2024 link
Using the barge, piles are installed ready for splicing/welding.
A third-party contractor is conducting tests on the driven piles to ensure they have reached the necessary refusal strength. This process allows us to quickly evaluate key factors such as the pile’s load-bearing capacity, the stress on the steel, the overall integrity of the pile, and the effectiveness of the pile driving process.
Once the piles have successfully passed these tests, we will move forward with installing the seawall panels.
Carter Marine are anticipated to complete the seawall, jetties, and all associated works by December 2025.
The carpark design is in the concept stage and will progress to the preliminary stage over the coming month. The preliminary design will be made available on YourSay following the Council Election period.
Share 14 August 2024 on FacebookShare 14 August 2024 on TwitterShare 14 August 2024 on LinkedinEmail 14 August 2024 link
Carter Marine is progressing well.
The pile driving is well underway and is anticipated to continue over the coming months.
Coming up.... carpark design.
A consultant has been engaged to design the upgrade of the carpark, enhancing usability for all while protecting the natural environment of the precinct. The consultant will undertake investigations in the carpark area, which are scheduled to commence in the coming weeks. Outcomes of the investigations will provide insight on the existing pavement conditions within the proposed carpark location and inform the development of the carpark concept design.
A project reference group (PRG) will help progress the development of the carpark concept design; successful PRG applicants will soon be notified by our Project Engineer.
Assembled on a voluntary basis, the PRG includes representation of Slip Road businesses and regular users of the area. The PRG members will support and co-operate with all parties and inform the consultant of their needs and use of the area.
The first PRG meeting will be scheduled to occur after the 2024 council caretaker period (17 September 2024 to 26 October 2024) and all pavement investigations have been completed.
Further project updates will be provided following the 2024 council caretaker period (17 September 2024 to 26 October 2024). In the meantime, we encourage your continued interest in this project and other projects available on YourSay. Please choose to follow projects on YourSay to receive important information directly to your inbox.
Share 17 July 2024 on FacebookShare 17 July 2024 on TwitterShare 17 July 2024 on LinkedinEmail 17 July 2024 link
Despite the poor weather, works at Slip Road continue to progress. Our contractor, Carter Marine have completed fabrication of the concrete seawall panels and are now in the process of driving extra piles to increase the horizontal stability of the seawall.
Share 28 May 2024 on FacebookShare 28 May 2024 on TwitterShare 28 May 2024 on LinkedinEmail 28 May 2024 link
Representatives from our funding partners, the Department of Jobs, Skills, Industry, and Regions, visited the site on Friday 24 May 2024 to check on the progress.
Our officers shared insights on the design and layout, giving them a firsthand look at the project. They saw several of the 57 new seawall panels already poured, galvanised piles ready for installation, and the general layout of the site.
We're pleased to have their continued interest and support in this shared project. A big thank you to our contractor, Carter Marine Group, for their hard work and dedication in bringing the Slip Road Maritime Precinct project to life - their expertise and commitment has been invaluable in making this project a success.
The next steps -
Panels to be installed between piles to form seawall
Backfill behind seawall in preparation for new carpark
Prefabrication of pontoons and service jetty to happen offsite
PHOTO [from left to right]: Renee Wicks – Manager Infrastructure Projects East Gippsland Shire Council; Shayna Millar - Visitor Economy Project Delivery Coordinator - Department of Jobs, Skills, Industry and Regions; Sean Heinemann – Project Supervisor East Gippsland Shire Council; Katrina Cranwell - Department of Jobs, Skills, Industry and Regions; Nick George – Carter Marine Group – Principal Contractor; Johan Janse Van Rensburg – Project Engineer East Gippsland Shire Council.
Share 21 February 2024 - works set to recommence on FacebookShare 21 February 2024 - works set to recommence on TwitterShare 21 February 2024 - works set to recommence on LinkedinEmail 21 February 2024 - works set to recommence link
Construction is set to restart following a comprehensive design update to create a revitalised precinct for boaters that will include a new boat ramp, two pontoon jetties providing additional berthing, and a services jetty for minor works.
East Gippsland Shire Council Mayor Cr Tom Crook welcomed completion of the new design and recommencement of works.
“The new design is vital to the project’s overall success, and we acknowledge the delay and appreciate the community’s understanding and support for this re-design work,” Cr Crook said.
Council’s engaged contractor, Carter Marine, has been awarded a varied contract for construction of the seawall, jetties and boardwalk. A tender for construction of the carpark and landscaping will be advertised later this year following the finalisation of the marine based work by Carter Marine.
“We also thank Carter Marine for their patience,” Cr Crook said. “The updated design ensures that the waterfront structures it constructs will be safe, stable, and offer tangible benefits in terms of boating and the local economy for decades to come.”
We welcome your continued interest in this project; project updates will be provided on YourSay, when available. Please click on 'Subscribe' at the top of the page to follow this project and to receive important information directly to your inbox.