14 November 2024
We are pleased to report significant progress on the maritime precinct upgrade:
- Southern Slip Road Seawall: Installation of concrete panels has now commenced for the southern section of the seawall.
- Northern Slip Road Seawall: Pile driving activities will continue over the coming months for the northern section. Following completion of this work, concrete panels will be installed.
- Floating Pontoons: The design phase for the floating pontoons is nearing completion, and we anticipate offsite prefabrication starting in February 2025.
- Boat Ramp & Service Jetty: Construction is scheduled to begin in March 2025.
We will continue to monitor progress and provide updates as Carter Marine progresses work on these key components.
We welcome your continued interest in this project. Please feel free to share this update with your local network and choose to follow this project on YourSay to receive important information regarding this project directly to your inbox.