Metung Boardwalk Maintenance
Work to improve the Metung Boardwalk is about to begin, with the first stage of upgrades starting early May. The project is part of our broader asset renewal program and aims to make the boardwalk, one of the town’s most used public spaces, safer and more durable.
The boardwalk is one of Metung’s most popular features and needs to be looked after properly. This first stage is all about improving safety, extending the life of the boardwalk, and keeping it accessible for everyone.
Stage 1 of the project will run from May to July 2025, to avoid peak tourist times and reduce disruption.
Access to the boardwalk will be closed while works are underway. Some carparks at the marina will be used for plant and equipment during the works. The area indicated in the map here will be inaccessible.
Background
The boardwalk runs alongside Metung Marina and is part of a convenient walking path that circles around the township. Positioned to the east of the town, the boardwalk stretches about 750 metres towards Chinaman’s Creek. It is a popular spot for both locals and tourists, thanks to its beautiful location by Bancroft Bay, and serves as a great access point for anglers.
Project objective and scope
Around 50 metres of the boardwalk, including the ramp north of Metung Marina, will be renewed. This work will address pest activity and timber deterioration by replacing the timber decking with a fibre-reinforced polymer (FRP) surface, which provides grip in wet or sea-affected conditions and will stand up better to fire, rot and insects.
While we recognise many locals love the traditional timber boardwalk, FRP is frequently used in other marina environments and existing jetties in East Gippsland and has also been adopted due to challenges sourcing suitable timber.
This stage will also give us an indication of the condition of the substructure, which will help shape future stages of the project. Later stages will proceed dependent on funding and the findings from this first phase.
Stainless-steel handrails and solar LED bollard lighting will also be installed. Where needed, piles will be reinforced with steel that matches existing structures.
Community engagement
We will keep you informed with updates on YourSay, and local berth holders will receive ongoing updates.
Should you have any concerns during the project, please reach out to the project supervisor on 5153 9500, or email to feedback@egipps.vic.gov.au
Funding
We are completing this work through our asset renewal program. We manage more than $1 billion of assets across the shire and are committed to maintaining and improving public infrastructure for our community.
We welcome your continued interest in this project; updates will be provided on YourSay in the tab below, when available. Please click 'Subscribe' at the top of the page to follow this project and to receive important information directly to your inbox. Should you wish to search for other projects near you, simply type the town name in the search bar.