4 April 2024

Works are progressing well.

Construction of the court and footpath connections along the south side of Main Street are well underway.

Works surrounding the toilet block are underway, which involve additional drainage enhancements, footpaths, and landscaping. The relocation of the BBQ and the replacement of current street furniture are expected to occur in the upcoming weeks.

The installation of the electric vehicle charger proposed for the site is also anticipated to commence shortly and should be operational by June 2024