4 April 2024

Works are progressing well.

Construction of the court and footpath connections along the south side of Main Street are well underway.

Works surrounding the toilet block are underway, which involve additional drainage enhancements, footpaths, and landscaping. The relocation of the BBQ and the replacement of current street furniture are expected to occur in the upcoming weeks.

The installation of the electric vehicle charger proposed for the site is also anticipated to commence shortly and should be operational by June 2024

Share 4 April 2024 on Facebook Share 4 April 2024 on Twitter Share 4 April 2024 on Linkedin Email 4 April 2024 link

Buchan is celebrating a significant upgrade to its main road and walking path connections, following the completion of the Buchan Main Street and Linkages Project.

Undertaken in two parts, this significant project commenced in November 2022 with the creation of a 2.5m-wide, 1300m-long shared pathway connecting Buchan to the limestone Buchan Caves and surrounding park. 

In addition to the pathway, significant upgrades to the town’s streetscape include new parking areas near key locations such as the Buchan Playground, CFA facility, and Mechanics Hall. 

Roads have been re-sealed with new line markings to increase safety for both vehicles and pedestrians. The installation of new street furniture, including tables, has enhanced the town’s aesthetic appeal, making it more inviting for locals and visitors to the area.