Bairnsdale - WORLD Sporting Precinct Redevelopment
Share Bairnsdale - WORLD Sporting Precinct Redevelopment on FacebookShare Bairnsdale - WORLD Sporting Precinct Redevelopment on TwitterShare Bairnsdale - WORLD Sporting Precinct Redevelopment on LinkedinEmail Bairnsdale - WORLD Sporting Precinct Redevelopment link
Women's Organisation for Recreation, Leisure and Development (WORLD)
This project originates from Council’s adoption of the Bairnsdale Sporting Facilities Plan in September 2018, which identified the project as a high priority due to the strong participation and growth in Netball, Hockey, Soccer and Futsal.
The project has attracted significant investment from both the Australian Government and the Victorian State Government in collectively providing grant funding and the Victorian Government providing funds through a low interest loan scheme.
Construction Package 1 (completed) – Main Car Park and Hockey Pitches, Hockey and soccer carparking, infrastructure.
Construction Package 2 (completed) – Netball Courts and Carparking construction.
Construction Package 3 (completed) – Netball and Hockey Pavilion (WORLD pavilion) construction.
Construction Package 4 – Soccer Precinct.
Project Scope
When complete, this project will provide the following regional level sporting facilities:
eight court netball precinct with Marshall’s building
synthetic hockey pitch with lighting
grass hockey pitch with lighting
synthetic soccer field with lighting
grass soccer field with lighting
all associated works including access roads, paths, electrical kiosk, car parking, landscaping, and water metering system
two new pavilions to service multiple clubs across the sporting codes
The staged construction has allowed the kindergarten to continue to provide services to the community, and a second Bairnsdale Netball Association season to go ahead.
The footprint for the construction of the new soccer fields and soccer pavilion is currently undergoing environmental assessment and Environment Protectionand Biodiversity Conservation Act1999 (EPBC) approvals.
Women's Organisation for Recreation, Leisure and Development (WORLD)
This project originates from Council’s adoption of the Bairnsdale Sporting Facilities Plan in September 2018, which identified the project as a high priority due to the strong participation and growth in Netball, Hockey, Soccer and Futsal.
The project has attracted significant investment from both the Australian Government and the Victorian State Government in collectively providing grant funding and the Victorian Government providing funds through a low interest loan scheme.
Construction Package 1 (completed) – Main Car Park and Hockey Pitches, Hockey and soccer carparking, infrastructure.
Construction Package 2 (completed) – Netball Courts and Carparking construction.
Construction Package 3 (completed) – Netball and Hockey Pavilion (WORLD pavilion) construction.
Construction Package 4 – Soccer Precinct.
Project Scope
When complete, this project will provide the following regional level sporting facilities:
eight court netball precinct with Marshall’s building
synthetic hockey pitch with lighting
grass hockey pitch with lighting
synthetic soccer field with lighting
grass soccer field with lighting
all associated works including access roads, paths, electrical kiosk, car parking, landscaping, and water metering system
two new pavilions to service multiple clubs across the sporting codes
The staged construction has allowed the kindergarten to continue to provide services to the community, and a second Bairnsdale Netball Association season to go ahead.
The footprint for the construction of the new soccer fields and soccer pavilion is currently undergoing environmental assessment and Environment Protectionand Biodiversity Conservation Act1999 (EPBC) approvals.
REDEVELOPMENT of THE WOMEN'S ORGANISATION for RECREATION, LEISURE, and DEVELOPMENT (WORLD) SPORTING PRECINCT, 99 WALLACE STREET BAIRNSDALE VICTORIA 3875 (EPBC Act Ref 2022/09215)
FOR INFORMATION PURPOSES
The following notice is published pursuant to Section 95B(2) of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).
East Gippsland Shire Council (EGSC) is seeking approval under the Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) for the development of additional sporting facilities at 99 Wallace Street, Bairnsdale, Victoria. The site is zoned Public Use Zone – Education (PUZ2) and is a designated Bushfire Prone Area (BPA) under the East Gippsland Planning Scheme. It comprises open fields of grassland, as well as open woodland and a nearby natural wetland. East Gippsland Specialist School is located to the immediate south, Westdale Kindergarten to the immediate north and Bairnsdale Secondary College and Bairnsdale Aquatic and Recreation Centre to the immediate east.
The proposed action has been referred under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) and determined to be a “controlled action” under the EPBC Act with a Preliminary Documentation level of assessment set.
The controlling provision under the EPBC Act is “Listed threatened species and communities” (Sections 18 and 18A) – in particular the Gippsland Red Gum (Eucalyptus tereticornis subsp. mediana) Grassy Woodland and Associated Native Grassland (Gippsland Red Gum/GRGGW) ecological community – Critically Endangered and Seasonal Herbaceous Wetlands (Freshwater) of the Temperate Lowland Plains (Seasonal Herbaceous Wetlands/SHWTLP) ecological community – Critically Endangered.
The final Preliminary Documentation information has been submitted to the Department of Climate Change, Energy, the Environment and Water. Pursuant to Section 95B(2) of the EPBC Act, these documents are now available for viewing at the following locations:
Bairnsdale Library - 22 Service Street Bairnsdale
State Library Victoria - 328 Swanston Street, Melbourne.
Note: Persons with any special needs (e.g. for whom English is a second language or who have vision impairment) may contact Kate Allen via the details below for assistance in accessing the documentation.
Kate Allen Natural Environment Coordinator, Environmental Projects EAST GIPPSLAND SHIRE COUNCIL Ph 03 5153 9500 PO Box 1618 Bairnsdale VIC 3875 Or email KateA@egipps.vic.gov.au
Click here to play video
Netball Association Championships - Sunday 15 June 2025
Our WORLD Sporting Complex netball courts and pavilion were buzzing on Sunday for the Netball Victoria Association Championships, featuring 500 players and in total about 1,000 supporters, volunteers and officials.
There were some tired young netballers on Sunday night, but what an opportunity for our local players to put their skills on display against the best from Gippsland on their home courts. To the band of volunteers, thank you for helping create an environment where some great memories were made.
It’s events such as these that are now possible because of the investment we’ve made in this facility.
Click here to play video
First netball games played at the WORLD on Thursday 19 October 2023
Click here to play video
WORLD construction update - 25 September 2023
Hockey - completed.
Netball - completed.
Click here to play video
Saturday 6 May 2023 saw the first hockey matches played on the synthetic field.
Congratulations to all involved in for helping us reach this significant milestone for the sporting community of East Gippsland! We are sure all players, families and officials were excited to put the field to use.
Click here to play video
Update: new synthetic hockey pitch and progress report on netball courts
Update 7 March 2023: new synthetic hockey pitch and netball courts weeks away from completion.
Click here to play video
WORLD Sporting Precinct - May 2021 update
A flyover of early construction works at the WORLD Sporting Precinct. Check out our later video to see progress at the site.
Click here to play video
Take a bird's-eye look at progress at the WORLD Sporting Precinct site
The WORLD Sporting Precinct project Is making great progress - take a look.
The WORLD Sporting Project has faced the combined challenges of heavy rain and Covid with its related staffing and materials shortages.
Despite these challenges we’re making good progress, with the new carpark south of Westdale Kindergarten being opened for kindergarten use.
We’ve commenced site works on the new netball courts and parking area.
The hockey pitch work is progressing, with upgrades to the pitch installations (a synthetic surface to one pitch and improved drainage design to the grass pitch) being managed.
Pad preparation for the new pavilion is in progress.
Our contractors are working hard to complete the pavilion, netball and hockey playing surfaces by the end of 2022, allowing for a summer opening of these facilities.
The soccer precinct in the southern section of the site will include two pitches and a pavilion similar to the WORLD pavilion. The area where the field and pavilion will be built is currently undergoing Federal Government environmental approvals under the EPBC Act. Council is awaiting an initial assessment from the department (DAWE), which will clarify timeframes for the broader approvals process.
The footprint for the construction of the new soccer fields and soccer pavilion is currently undergoing environmental assessment and Environment Protection and Biodiversity Conservation Act 1999 (EPBC) approval.