π May 2025
Share π May 2025 on Facebook Share π May 2025 on Twitter Share π May 2025 on Linkedin Email π May 2025 linkWorks on the Swifts Creek Recreation Reserve pavilion are progressing smoothly and on schedule.
β Plastering is complete, giving the interior a clean and finished look.
π¨ Painting and vinyl work are currently underway, adding colour and comfort to the space.
π§ The external driveway and retaining wall have now been completed, improving access and enhancing the overall layout of the reserve.
π§ Installation of bollards, the spoon drain, external drainage, and the meter box has also been finalised.Thanks to the hard work of everyone involved, the project remains on track for completion by June 30, 2025.
We canβt wait to welcome the community into the upgraded space very soon!
Stay tuned for more updates as we move closer to the finish line. Thank you for your continued support and enthusiasm.
-
π March 2025
Share π March 2025 on Facebook Share π March 2025 on Twitter Share π March 2025 on Linkedin Email π March 2025 linkCompleted since last update:
- roofing
Works underway:- window installation
What's next:- external brickwork
- internal plumbing
- electrical
- mechanical installations
We are collaborating with the reserve committee to ensure the provision of temporary toilets and showers for the upcoming football season. These facilities will remain in place until construction is complete. -
3 February 2025
Share 3 February 2025 on Facebook Share 3 February 2025 on Twitter Share 3 February 2025 on Linkedin Email 3 February 2025 linkWorks completed to date:
- Under slab plumbing and electrical works
- Site preparation and concrete slab
- Galvanised structural steel works
Works underway:
- Septic tank and field under construction
- Water and power redirected to existing canteen
A meeting was recently held with the Committee of Management to select furnishings and fittings for the new pavilion.
What's next:
- Roof framing
- Roof installation
- Window and wall cladding
-
20 December 2024
Share 20 December 2024 on Facebook Share 20 December 2024 on Twitter Share 20 December 2024 on Linkedin Email 20 December 2024 link -
11 December 2024
Share 11 December 2024 on Facebook Share 11 December 2024 on Twitter Share 11 December 2024 on Linkedin Email 11 December 2024 linkUnfortunately, the Swifts Creek Recreation Reserve construction site was hit hard by a storm on 7 December 2024, which caused significant damage. Concrete is now scheduled to be poured on Friday 13 December.
-
22 November 2024
Share 22 November 2024 on Facebook Share 22 November 2024 on Twitter Share 22 November 2024 on Linkedin Email 22 November 2024 linkThe demolition of the previous buildings has been finalised, and site preparation was completed on Friday 25 October 2024.
We are currently in the final stages of underground plumbing installation, with concreting scheduled to begin next week.
-
16 September 2024
Share 16 September 2024 on Facebook Share 16 September 2024 on Twitter Share 16 September 2024 on Linkedin Email 16 September 2024 linkFurther updates will be provided on YourSay following the Council Election on 26 October 2024, and the questions/feedback tab will be reinstated.
From 12.00 noon Tuesday 17 September until 6.00 pm on Saturday 26 October (Election Day) we will be in the Local Government Election Period (also known as Caretaker Period).
During this time, we will limit our printed communications, website content, social media activity, and community consultations. The ability for people to comment on our social media content will also be disabled during the Election Period.
Each of these steps is to ensure our content does not affect voting in the election and is consistent with steps taken by other Victorian Councils and the Local Government Act 2020.
These changes are only temporary; we'll be back to normal communication activity after the election.
-
13 September 2024
Share 13 September 2024 on Facebook Share 13 September 2024 on Twitter Share 13 September 2024 on Linkedin Email 13 September 2024 linkWe are pleased to advise that the contract for construction of the Swifts Creek Recreation Reserve Upgrade was awarded to Design Co Builders at the 10 September 2024 Council meeting. This was the last major contract for construction for this term of Council.
Works will involve replacing the existing buildings (changerooms, umpire rooms, toilets, tennis clubroom) with one multipurpose community pavilion which will be accessible and fully compliant to meet netball and AFL sporting body guidelines.
We would like to take this opportunity to congratulate everyone involved in achieving this significant milestone and we look forward to working with the Design Co team to enrich community with upgraded facilities that ensure community connectedness, exceed visitor expectations, and assist in building resilience and capacity into the future.
-
9 August 2024
Share 9 August 2024 on Facebook Share 9 August 2024 on Twitter Share 9 August 2024 on Linkedin Email 9 August 2024 linkTender for construction has closed.
Thank you to all who submitted applications for the recent tender. Please be aware that the assessment process may take some time as we thoroughly review each submission to ensure the best outcomes for the project. For tenders that require approval at a Council meeting, there may be additional delays before announcements are made.
We appreciate your patience and understanding as we complete this important process.
Further project updates will be provided once the tender evaluation process has been completed.
-
24 July 2024 - Tender open
Share 24 July 2024 - Tender open on Facebook Share 24 July 2024 - Tender open on Twitter Share 24 July 2024 - Tender open on Linkedin Email 24 July 2024 - Tender open linkThe tender for construction is now open and is scheduled to close at midnight on Friday 9 August 2024.
CON2025 1701R - Swifts Creek Recreation Reserve Pavilion Construction Works
All documents are available at tenderlink.com/egipps