3 February 2025
Works completed to date:
- Under slab plumbing and electrical works
- Site preparation and concrete slab
- Galvanised structural steel works
Works underway:
- Septic tank and field under construction
- Water and power redirected to existing canteen
A meeting was recently held with the Committee of Management to select furnishings and fittings for the new pavilion.
What's next:
- Roof framing
- Roof installation
- Window and wall cladding