Share Omeo - Heritage Precinct on FacebookShare Omeo - Heritage Precinct on TwitterShare Omeo - Heritage Precinct on LinkedinEmail Omeo - Heritage Precinct link
Council is pleased to have secured funding for conservation and protection works to the historically significant Omeo Justice Precinct courthouse buildings. The Old Courthouse was built in 1859 and the new Courthouse built in 1893. The project is jointly funded by Heritage Victoria and Council.
The works to be undertaken to the Old Courthouse building include repair to the brickwork, brick render repairs, extensive painting both internally and externally, repair to flooring and plastering, sub-floor ventilation, stormwater works and electrical upgrade.
Works to the new Courthouse include repairs to flooring, replacement of sub-floor timber framing, floor ventilation, roof repairs, tiling and painting, electrical upgrade works and some minor repairs to furniture.
To minimise the upcoming winter weather impact, works are currently focusing on external works to both buildings.
Works to the Omeo Heritage Precinct will provide significant improvement to the condition and ensure the preservation of these historic buildings.
For more information regarding project updates please subscribe.
Council is pleased to have secured funding for conservation and protection works to the historically significant Omeo Justice Precinct courthouse buildings. The Old Courthouse was built in 1859 and the new Courthouse built in 1893. The project is jointly funded by Heritage Victoria and Council.
The works to be undertaken to the Old Courthouse building include repair to the brickwork, brick render repairs, extensive painting both internally and externally, repair to flooring and plastering, sub-floor ventilation, stormwater works and electrical upgrade.
Works to the new Courthouse include repairs to flooring, replacement of sub-floor timber framing, floor ventilation, roof repairs, tiling and painting, electrical upgrade works and some minor repairs to furniture.
To minimise the upcoming winter weather impact, works are currently focusing on external works to both buildings.
Works to the Omeo Heritage Precinct will provide significant improvement to the condition and ensure the preservation of these historic buildings.
For more information regarding project updates please subscribe.
Share 📅 March 2026 on FacebookShare 📅 March 2026 on TwitterShare 📅 March 2026 on LinkedinEmail 📅 March 2026 link
Works at the Omeo Heritage Precinct are now around 95% complete.
The builder recommenced works in late November 2025, with progress continuing across both the Old and New Courthouses. Some coordination has been required to manage access around heritage items and to transition to a new electrician following the retirement of the original contractor.
The builder and electrician are working to finalise remaining works.
Works at the Omeo Heritage Precinct are now around 95% complete.
The builder recommenced works in late November 2025, with progress continuing across both the Old and New Courthouses. Some coordination has been required to manage access around heritage items and to transition to a new electrician following the retirement of the original contractor.
The builder and electrician are working to finalise remaining works.
Share Project Update 8/05/2023 on FacebookShare Project Update 8/05/2023 on TwitterShare Project Update 8/05/2023 on LinkedinEmail Project Update 8/05/2023 link
Omeo Court House Stables
The horse stables are nearing completion.
The pathway is to be reshaped.
The stormwater drainage will be improved.
The brick floor will be relaid.
Omeo Old Court House
A brick drain has been laid to cope with ground water.
Scaffold has been removed from the building, ready for final external paint finish.
Awaiting internal brickwork to dry out from rising damp prior to finishing internal walls.
New Courthouse
Scaffold has been removed.
Some minor internal finishing works are currently being completed.
Omeo Court House Stables
The horse stables are nearing completion.
The pathway is to be reshaped.
The stormwater drainage will be improved.
The brick floor will be relaid.
Omeo Old Court House
A brick drain has been laid to cope with ground water.
Scaffold has been removed from the building, ready for final external paint finish.
Awaiting internal brickwork to dry out from rising damp prior to finishing internal walls.
New Courthouse
Scaffold has been removed.
Some minor internal finishing works are currently being completed.
Share Project Update 16/11/2022 on FacebookShare Project Update 16/11/2022 on TwitterShare Project Update 16/11/2022 on LinkedinEmail Project Update 16/11/2022 link
Council officers are pleased to advise that works on the two Omeo Court Houses are almost complete. The works were on display at the recent combined celebrations for the 150th anniversary of the proclamation of the Shire of Omeo, and the 50th birthday of the Omeo Historical Society.
Council officers are pleased to advise that works on the two Omeo Court Houses are almost complete. The works were on display at the recent combined celebrations for the 150th anniversary of the proclamation of the Shire of Omeo, and the 50th birthday of the Omeo Historical Society.